# Industrial SWPPP Requirements: Updates, Training, Records

> When an industrial SWPPP must be revised and uploaded, how often staff are trained, and how long records are kept, under each stormwater permit.

Canonical page: https://stormdue.com/guides/swppp-requirements

[Guides](https://stormdue.com/guides) / SWPPP, training and records

# Industrial SWPPP requirements: updates, training and records

The plan has to be kept current, and some changes come with a deadline. Implement SWPPP changes within 90 days of the Annual Evaluation (California Industrial General Permit (IGP)); Upload a significantly revised inactive mining SWPPP within 30 days (California Industrial General Permit (IGP)); Upload a significantly revised SWPPP within 30 days (California Industrial General Permit (IGP)); Update the exposed-materials inventory and narrative within 30 days of a significant change (Texas MSGP); Update the public SWPPP within 45 days after the year's last routine inspection (EPA 2021 MSGP). How long each permit says to keep records:

- **California Industrial General Permit (IGP):** Keep all monitoring records and reports for five years; Track NAL exceedances and Level status for each parameter.
- **Texas MSGP:** Keep records three years.
- **Washington ISGP:** Keep records five years and produce them within 14 days of a written request.
- **EPA 2021 MSGP:** Keep records for three years after coverage ends.

[Get my permit calendar](https://stormdue.com/lookup)

Free, no account. Pick your state and coverage and see the next date for each duty.

Next: answer a few questions about your site. You get your dates, the permit section for each, and a calendar file.

StormDue reminds and keeps records. It does not file anything with the agency and does not certify or guarantee compliance. Check each duty against your permit; you are responsible for your filings.

Compared here: California Industrial General Permit (IGP), rules checked November 25, 2026; Texas MSGP, rules checked November 25, 2026; Washington ISGP, rules checked November 25, 2026; EPA 2021 MSGP, rules checked November 26, 2026. Duties for other states are not listed until their rules are checked: [find your state](https://stormdue.com/states).

## SWPPP, training and record duties by permit

**SWPPP, training and record duties by permit and frequency**

| Permit | Every week | Every quarter | Every year | When something happens | Ongoing | Only if... |
| --- | --- | --- | --- | --- | --- | --- |
| California Industrial General Permit (IGP) | - | 1 | 1 | 6 | 4 | 3 |
| Texas MSGP | 1 | 1 | 2 | 2 | 2 | 1 |
| Washington ISGP | - | 1 | 1 | 1 | 2 | - |
| EPA 2021 MSGP | - | - | 1 | 1 | 3 | 1 |

"When something happens" duties start from a change at the site, such as a significant revision. "Only if..." duties apply to some sectors or sites.

## Worked example: if it happens on March 3, 2027

Some deadlines count from something that happens at the site. If that event fell on March 3, 2027, the permit's rule puts the deadline here. Your own dates come from your own events.

**Deadlines counted from an event on March 3, 2027**

| Permit | Duty | Counts from | Due |
| --- | --- | --- | --- |
| California Industrial General Permit (IGP) | Implement SWPPP changes within 90 days of the Annual Evaluation | annual evaluation date | June 1, 2027 |
| California Industrial General Permit (IGP) | Facility discharging to ocean waters sets up an Ocean Plan monitoring program before operating | start of industrial activity | By February 24, 2027 |
| California Industrial General Permit (IGP) | Upload a significantly revised inactive mining SWPPP within 30 days | date of significant revision | April 2, 2027 |
| California Industrial General Permit (IGP) | Upload a significantly revised SWPPP within 30 days | date of significant revision | April 2, 2027 |
| Texas MSGP | Update the exposed-materials inventory and narrative within 30 days of a significant change | date of significant change | April 2, 2027 |
| EPA 2021 MSGP | Update the public SWPPP within 45 days after the year's last routine inspection | final routine inspection of year | April 17, 2027 |
| EPA 2021 MSGP | Document the triggering condition within 24 hours and the response within 14 days | awareness of condition | March 4, 2027 |

The [deadline calculator](https://stormdue.com/tools/deadline-calculator) works out the same dates from your own event date.

## California Industrial General Permit (IGP)

General Permit for Storm Water Discharges Associated with Industrial Activities, run by State Water Resources Control Board (with the nine Regional Water Quality Control Boards). Rules checked November 25, 2026. [Every duty in this permit](https://stormdue.com/permits/us-ca-igp) · [California permit facts](https://stormdue.com/states/ca) · [Official permit page](https://www.waterboards.ca.gov/water_issues/programs/stormwater/igp_20140057dwq.html)

- Every quarter 1
- Every year 1
- When something happens 6
- Ongoing 4
- Only if... 3

### Every quarter  1 duty

#### (Question) Upload non-significant SWPPP revisions each quarter

No set date. X.B.3: "not required to certify and submit via SMARTS their SWPPP revisions more than once every three (3) months"; To-Do List: updates "are required to be uploaded in SMARTS at least once a quarter". Which governs?

Whether non-significant SWPPP revisions must be certified and uploaded in SMARTS once a quarter is not settled: the order only limits how often they can be required, while the Water Board's To-Do List says quarterly uploads are required. Shown as a question until the Water Board answers.

- You file it in the agency's system (SMARTS).
- Keep the records 5 years.
- Signed or certified by the Legally Responsible Person or a Duly Authorized Representative.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section X.B.3, page 29**

> "With the exception of significant revisions, the Discharger is not required to certify and submit via SMARTS their SWPPP revisions more than once every three (3) months in the reporting year."

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=32)

### Every year  1 duty

#### Implement SWPPP changes within 90 days of the Annual Evaluation

Within 90 days after annual evaluation date.

Revise the SWPPP as appropriate and implement the revisions within 90 days of the Annual Evaluation.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XV, page 64**

> "The Discharger shall revise the SWPPP, as appropriate, and implement the revisions within 90 days of the Annual Evaluation."

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=67)

### When something happens  6 duties

#### (Optional) Submit the Qualified Combined Samples justification

No set date. optional; must be submitted before the reduction is used.

To have the lab combine equal-volume samples from up to four discharge locations, certify and submit in SMARTS the Monitoring Implementation Plan revisions with the Qualified Combined Samples justification before combining. The Regional Board may reject it.

- **When:** qualified combined samples elected.
- **Does not apply if:** inactive mining certification in effect.

- You file it in the agency's system (SMARTS).
- Keep the records 5 years.
- Signed or certified by the Legally Responsible Person or a Duly Authorized Representative.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XI.C.5.c-d, page 51**

> "A Discharger that satisfies the conditions of subsection 5.b.i through iv above shall submit and certify via SMARTS the revisions to the Monitoring Implementation Plan that includes the Qualified Combined Samples justification."

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=54)

#### Facility discharging to ocean waters sets up an Ocean Plan monitoring program before operating

At least 7 days before start of industrial activity.

A facility with outfalls to ocean waters that are subject to the California Ocean Plan's model monitoring provisions must develop and implement a monitoring plan meeting those provisions at least 7 days before operations begin; otherwise it is not eligible for coverage. The XI.C sampling reductions and exceptions do not apply to those outfalls.

- **When:** new facility; discharges to ocean waters subject to ocean plan model monitoring.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section VIII.A, page 27**

> "Dischargers who have not developed and implemented a monitoring program in compliance with the California Ocean Plan's model monitoring provisions by July 1, 2015, or seven (7) days prior to commencing of operations"

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=30)

#### Recertify the site map after a significant layout change

No set date. No deadline in II.B.3.a. For NOI sites the 30-day significant SWPPP revision rule (X.B.2) likely applies (inferred); no deadline for NEC sites.

When the facility layout changes significantly (new building, storage locations, boundary), revise the site map and certify and submit it in SMARTS.

- **When:** significant layout change.

- You file it in the agency's system (SMARTS).
- Keep the records 5 years.
- Signed or certified by the Legally Responsible Person.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section II.B.3.a, page 19**

> "a revision to the site map is required and shall be certified and submitted via SMARTS."

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=22)

#### Submit any alternative discharge location in SMARTS

No set date. No deadline stated in XI.C.3.b.

Certify and submit in SMARTS any alternative discharge location, or revisions to alternative discharge locations, in the Monitoring Implementation Plan.

- **When:** alternative discharge location designated or revised.
- **Does not apply if:** inactive mining certification in effect.

- You file it in the agency's system (SMARTS).
- Keep the records 5 years.
- Signed or certified by the Legally Responsible Person or a Duly Authorized Representative.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XI.C.3.b, page 49**

> "The Discharger shall submit and certify via SMARTS any alternative discharge location or revisions to the alternative discharge locations in the Monitoring Implementation Plan."

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=52)

#### Upload a significantly revised inactive mining SWPPP within 30 days

Within 30 days after date of significant revision.

While an inactive mining certification is in effect, certify and submit any significantly revised SWPPP in SMARTS within 30 days of the revision. Significant updates are signed by a California licensed PE.

- **When:** inactive mining certification in effect.

- You file it in the agency's system (SMARTS).
- Keep the records 5 years.
- The permit says this is done by a California licensed professional engineer.
- Signed or certified by the Legally Responsible Person or a Duly Authorized Representative.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XIII.C.3-4, page 62**

> "The Discharger shall certify and submit via SMARTS any significantly revised SWPPP within 30 days of the revision(s)."

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=65)

#### Upload a significantly revised SWPPP within 30 days

Within 30 days after date of significant revision.

Certify and submit the SWPPP in SMARTS within 30 days whenever it contains significant revisions. Other revisions need not be uploaded more than once every three months.

- **When:** significant swppp revision.

- You file it in the agency's system (SMARTS).
- Keep the records 5 years.
- Signed or certified by the Legally Responsible Person or a Duly Authorized Representative.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section X.B.2-3, page 29**

> "Certify and submit via SMARTS their SWPPP within 30 days whenever the SWPPP contains significant revision(s)"

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=32)

### Ongoing  4 duties

#### Keep all monitoring records and reports for five years

Ongoing, no set date.

Keep a paper or electronic copy of all storm water monitoring information, records, data and reports the permit requires for at least five years, available to Water Board staff at the facility during scheduled operating hours.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XXI.J.4, page 76**

> "Dischargers shall retain, for a period of at least five (5) years, either a paper or electronic copy of all storm water monitoring information, records, data, and reports required by this General Permit."

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=79)

#### Keep the SWPPP current and on site

Ongoing, no set date.

Revise the on-site SWPPP whenever necessary and keep a copy at the facility.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section X.B.1; X.C.2, page 29**

> "Revise their on-site SWPPP whenever necessary;"

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=32)

#### Track NAL exceedances and Level status for each parameter

No set date. Status changes take effect July 1 after the reporting year of the exceedance.

Compare results with Table 2 NALs (and Attachment E TNALs). An annual NAL exceedance is a reporting-year average above the annual NAL; an instantaneous exceedance is two or more results in a reporting year above the instantaneous maximum (or outside pH 6.0 to 9.0). An exceedance moves the parameter from Baseline to Level 1, or Level 1 to Level 2, on July 1 after the reporting year in which it occurred.

- **Does not apply if:** inactive mining certification in effect.

- Keep the records 5 years.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XII.A-D, page 54**

> "Level 1 status will commence on July 1 following the reporting year during which the exceedance(s) occurred."

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=57)

#### Train the team members who carry out the permit

No set date. The permit requires a training schedule but sets no frequency; the facility's own SWPPP schedule governs.

Run the employee training program described in the SWPPP (materials, who is trained, a training schedule) and keep training records. Once the facility is in Level 1, the appropriate team members must be trained by a QISP.

- If a parameter is at level 1 or higher: a different schedule.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section X.H.1.f; X.H.1.g.iii, page 37**

> "Ensure that all team members implementing the various compliance activities of this General Permit are properly trained to implement the requirements of this General Permit"

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=40)

### Only if...  3 duties

These apply only in the situation named on each one. Answer the questions to sort them.

#### (Optional) Submit the Representative Sampling Reduction justification

No set date. optional; must be submitted before the reduction is used.

To sample fewer locations in a drainage area, certify and submit in SMARTS the Monitoring Implementation Plan revisions with the Representative Sampling Reduction justification before using the reduction. The Regional Board may reject it.

- **Only if:** not: your discharge is subject to federal effluent limitation guidelines (ELGs); representative sampling reduction elected.
- **Does not apply if:** inactive mining certification in effect.

- You file it in the agency's system (SMARTS).
- Keep the records 5 years.
- Signed or certified by the Legally Responsible Person or a Duly Authorized Representative.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XI.C.4.c-d, page 50**

> "A Discharger that satisfies the conditions of subsection 4.b.i through v above shall submit and certify via SMARTS the revisions to the Monitoring Implementation Plan that includes the Representative Sampling Reduction justification."

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=53)

#### Amend the SWPPP with TNAL or NEL exceedance information

No set date. No deadline stated in VII.C.3.

Responsible Dischargers under an Attachment E TMDL amend the SWPPP with the TNAL or NEL exceedance information and certify and submit it in SMARTS.

- **Only if:** a TMDL applies to your discharge; tnal or nel exceedance.

- You file it in the agency's system (SMARTS).
- Keep the records 5 years.
- Signed or certified by the Legally Responsible Person or a Duly Authorized Representative.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section VII.C.3, page 26**

> "The SWPPP is required to be amended with the TNAL or NEL exceedance information, and to be certified and submitted via SMARTS."

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=29)

#### Annual training for employees handling plastic materials

No set date. "annually"; calendar vs reporting year not stated.

Plastics facilities using the eight-BMP alternative to a 1 mm containment system must train employees handling plastic materials every year (hazards, corrective-action duties, cleanup).

- **Only if:** the facility handles plastic materials (a plastics facility); plastics eight bmp option in use.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

**Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XVIII.A.2.b.i, page 70**

> "Plastics Facilities shall annually train employees handling Plastic Materials."

[Open the permit at this section](https://www.waterboards.ca.gov/water_issues/programs/stormwater/docs/industrial/2014indgenpermit/order.pdf#page=73)

## Texas MSGP

TPDES Multi-Sector General Permit for Stormwater Discharges Associated with Industrial Activity, run by Texas Commission on Environmental Quality (TCEQ). Rules checked November 25, 2026. [Every duty in this permit](https://stormdue.com/permits/us-tx-txr050000) · [Texas permit facts](https://stormdue.com/states/tx) · [Official permit page](https://www.tceq.texas.gov/permitting/stormwater/industrial)

- Every week 1
- Every quarter 1
- Every year 2
- When something happens 2
- Ongoing 2
- Only if... 1

### Every week  1 duty

#### Check and log the rain gauge weekly (daily during storms)

By the end of each week.

Keep an on-site rain gauge or use a representative weather station; check it at least weekly and daily during storms, recording date and rainfall (zero if none). May pause for a period once that period's sampling and observations are done.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: 2026 Multi-Sector General Permit TXR050000, section III.D.1(c), page 61**

> "must be monitored a minimum of once per week, and once per day during storm events."

[Open the permit at this section](https://www.tceq.texas.gov/downloads/permitting/stormwater/general/multi-sector/2026-msgp-renewal.pdf#page=61)

### Every quarter  1 duty

#### Update the SWP3 list of spills and leaks every quarter

By the end of each calendar quarter.

Each quarter, update the SWP3 list of spills and leaks: reportable quantity spills plus all other spills and leaks that could add pollutants to stormwater (the list may be limited to the previous five years).

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: 2026 Multi-Sector General Permit TXR050000, section III.A.3(e), page 44**

> "The list must be updated on a quarterly basis and must include all additional spills and leaks that could contribute pollutants to stormwater discharges"

[Open the permit at this section](https://www.tceq.texas.gov/downloads/permitting/stormwater/general/multi-sector/2026-msgp-renewal.pdf#page=44)

### Every year  2 duties

#### Employee stormwater training at least once a year

No set date. "Training must be conducted at least once per year" (III.A.4(g)(1)): TCEQ to confirm whether this means once each calendar year or no more than 12 months between sessions.

Train all employees responsible for SWP3 activities at least once per year on material handling, spill prevention and response, and SWP3 goals; keep training records and attendance lists in the SWP3.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

**Source: 2026 Multi-Sector General Permit TXR050000, section III.A.4(g)(1), page 48**

> "Training must be conducted at least once per year and records of training activities and attendance lists must be maintained in the SWP3"

[Open the permit at this section](https://www.tceq.texas.gov/downloads/permitting/stormwater/general/multi-sector/2026-msgp-renewal.pdf#page=48)

#### Update the summary of all lab results once a year

No set date. "Updated on an annual basis"; no date stated.

Keep a summary of all laboratory results for stormwater samples, updated once a year to add new results, attached to or referenced in the SWP3 and available on request.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: 2026 Multi-Sector General Permit TXR050000, section III.A.3(f), page 44**

> "All data from the laboratory analyses of stormwater discharge samples must be summarized. The summary must be updated on an annual basis to include the results of all additional analyses."

[Open the permit at this section](https://www.tceq.texas.gov/downloads/permitting/stormwater/general/multi-sector/2026-msgp-renewal.pdf#page=44)

### When something happens  2 duties

#### Update stormwater treatment waste records monthly

By the end of each month.

Facilities that remove sludge or other waste from a stormwater treatment process keep records (volumes generated and disposed, dates, hauler, disposal site and method), update them every month and keep them five years.

- **When:** stormwater treatment waste generated.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

**Source: 2026 Multi-Sector General Permit TXR050000, section III.E.7(a)(5), page 73**

> "The above records must be updated on a monthly basis. The records must be retained at the facility or must be readily available for review by authorized representatives of TCEQ for at least five years."

[Open the permit at this section](https://www.tceq.texas.gov/downloads/permitting/stormwater/general/multi-sector/2026-msgp-renewal.pdf#page=73)

#### Update the exposed-materials inventory and narrative within 30 days of a significant change

Within 30 days after date of significant change.

Update the SWP3 inventory of exposed materials, and the narrative description of pollutant sources, within 30 days after a significant change in the materials exposed to precipitation or in how they are managed.

- **When:** significant change in exposed materials.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: 2026 Multi-Sector General Permit TXR050000, section III.A.3(a)-(b), page 42**

> "The inventory must be updated within 30 days following a significant change in the types of materials that are exposed to precipitation or runoff"

[Open the permit at this section](https://www.tceq.texas.gov/downloads/permitting/stormwater/general/multi-sector/2026-msgp-renewal.pdf#page=42)

### Ongoing  2 duties

#### Keep records three years

Ongoing, no set date.

Keep monitoring and reporting records, all other required records and application data for three years from the record date; keep prior SWP3 versions (or a revision log) for three years; keep the SWP3 one year after coverage ends.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: 2026 Multi-Sector General Permit TXR050000, section III.D.5, page 65**

> "for a period of three (3) years from the date of the record or sample, measurement, report, application, or certification."

[Open the permit at this section](https://www.tceq.texas.gov/downloads/permitting/stormwater/general/multi-sector/2026-msgp-renewal.pdf#page=65)

#### Keep the SWP3 current, dated and available

Ongoing, no set date.

Develop and implement the SWP3 before the NOI, keep it at the site or readily available, modify it as often as necessary, date every revision, and keep prior versions (or a revision log) for three years.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- Signed or certified by a responsible official per 30 TAC 305.128.

**Source: 2026 Multi-Sector General Permit TXR050000, section III.A.6, page 49**

> "The SWP3 must be modified by the permittee as often as necessary. Each revision must be dated, and all revisions must be retained according to Part III, Section D.5."

[Open the permit at this section](https://www.tceq.texas.gov/downloads/permitting/stormwater/general/multi-sector/2026-msgp-renewal.pdf#page=49)

### Only if...  1 duty

These apply only in the situation named on each one. Answer the questions to sort them.

#### Sweep cement, aggregate and dust areas at least weekly (Sector E)

By the end of each week.

Sector E facilities sweep, or use an equivalent control, at least once a week where cement, aggregate, kiln dust, fly ash or settled dust are handled or processed.

- **Only if:** your permit sector is E.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: 2026 Multi-Sector General Permit TXR050000, section V.E.3(c), page 89**

> "Sweeping or an equivalent control measure must be performed at least once each week in areas where cement, aggregate, kiln dust, fly ash, or settled dust are being handled or processed."

[Open the permit at this section](https://www.tceq.texas.gov/downloads/permitting/stormwater/general/multi-sector/2026-msgp-renewal.pdf#page=89)

## Washington ISGP

Industrial Stormwater General Permit (NPDES and State Waste Discharge General Permit), run by Washington State Department of Ecology, Water Quality Program. Rules checked November 25, 2026. [Every duty in this permit](https://stormdue.com/permits/us-wa-isgp) · [Washington permit facts](https://stormdue.com/states/wa) · [Official permit page](https://ecology.wa.gov/regulations-permits/permits-certifications/stormwater-general-permits/industrial-stormwater-permit)

- Every quarter 1
- Every year 1
- When something happens 1
- Ongoing 2

### Every quarter  1 duty

#### Vacuum-sweep paved surfaces at least once a quarter

By the end of each calendar quarter.

Vacuum paved surfaces with a vacuum sweeper (or a sweeper with a vacuum attachment) at least once each quarter to remove accumulated pollutants, on the schedule in the SWPPP.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

**Source: 2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026), section S3.B.4.b.i.2).a), page 19**

> "Vacuum paved surfaces with a vacuum sweeper (or a sweeper with a vacuum attachment) to remove accumulated pollutants a minimum of once per quarter."

[Open the permit at this section](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=28)

### Every year  1 duty

#### Train all employees every year; new hires within 90 or 30 days

By December 31 each year.

Train all employees on the SWPPP at least annually. All employees, contractors and vendors with duties in areas of industrial activity: within 90 days of hire. Part-time and seasonal employees, contractors and vendors: within 30 days of hire. Keep a log of training dates with the SWPPP. Contractors and vendors may be excluded if a trained employee supervises their activity at all times.

- If new hire in industrial area: Within 90 days after hire date.
- If new part time seasonal or contractor: Within 30 days after hire date.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

**Source: 2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026), section S3.B.4.b.i.5).c), page 23**

> "The Permittee shall train all employees annually, at a minimum."

[Open the permit at this section](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=32)

### When something happens  1 duty

#### Newly covered facilities certify the SWPPP by the end of the first full quarter

No set date. End of the first full quarter after coverage begins; depends on the facility's coverage date (S3.A.3.c).

A facility that was not permitted before must develop and certify its SWPPP by the end of the first full monitoring period (quarter) after coverage starts, and implement the SWPPP and sampling by the first day of the second full monitoring period.

- **When:** new permit coverage.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

**Source: 2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026), section S3.A.3.c, page 15**

> "Unpermitted facilities shall develop and certify their SWPPP no later than the end of the first full monitoring period following the effective date of permit coverage,"

[Open the permit at this section](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=24)

### Ongoing  2 duties

#### Keep records five years and produce them within 14 days of a written request

Ongoing, no set date.

Keep the permit, coverage letter, sampling records, inspection reports, calibration and BMP maintenance records, lab reports, all reports and application data on site for five years (longer during litigation or on request); make them available immediately or within 14 days of Ecology's written request.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

**Source: 2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026), section S9.D, page 60**

> "The Permittee shall retain the following documents as hardcopies or electronically, onsite for a minimum of five years:"

[Open the permit at this section](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=69)

#### Keep the SWPPP current and re-sign it after each required revision

No set date. Event-driven; 30 days after an Ecology deficiency notice (S3.A.3.a.ii).

Modify the SWPPP when it proves ineffective, within 30 days of Ecology's written notice of deficiencies, and when design or operations change pollutant discharges significantly; sign and certify it (Appendix 3 form) each time it is revised for an update, inspection or corrective action.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

**Source: 2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026), section S3.A.3; S3.A.5, page 15**

> "The Permittee shall sign and certify all SWPPPs in accordance with General Condition G2, each time they revise or modify a SWPPP"

[Open the permit at this section](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=24)

## EPA 2021 MSGP

NPDES Multi-Sector General Permit for Stormwater Discharges Associated with Industrial Activity, run by U.S. Environmental Protection Agency (EPA Regions 1-10). Rules checked November 26, 2026. [Every duty in this permit](https://stormdue.com/permits/us-epa-msgp-2021) · [Official permit page](https://www.epa.gov/npdes/stormwater-discharges-industrial-activities-epas-2021-msgp)

- Every year 1
- When something happens 1
- Ongoing 3
- Only if... 1

### Every year  1 duty

#### Update the public SWPPP within 45 days after the year's last routine inspection

Within 45 days after final routine inspection of year.

Update the SWPPP made public through the NOI attachment, a URL, or SWPPP information in the NOI, no later than 45 days after the final routine facility inspection of the year.

- You file it in the agency's system (NeT-MSGP Change NOI, or the facility's SWPPP URL).
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

**Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 6.4.1, page 63**

> "no later than 45 days after conducting the final routine facility inspection for the year required in Part 3.1."

[Open the permit at this section](https://www.epa.gov/sites/default/files/2021-01/documents/2021_msgp_-_permit_parts_1-7.pdf#page=63)

### When something happens  1 duty

#### Document the triggering condition within 24 hours and the response within 14 days

Within 1 day after awareness of condition.

Record the condition (and spill details) within 24 hours of becoming aware of it, and the corrective action or AIM response taken or planned, with dates, within 14 days of discovery. Keep with the SWPPP; summarize in the Annual Report.

- **When:** corrective action condition, or aim triggering event.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

**Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 5.3.1; 5.3.3, page 54**

> "You must document the existence of any of the conditions listed in Parts 5.1.1, 5.2.3, 5.2.4, or 5.2.5 within 24 hours of becoming aware of"

[Open the permit at this section](https://www.epa.gov/sites/default/files/2021-01/documents/2021_msgp_-_permit_parts_1-7.pdf#page=54)

### Ongoing  3 duties

#### Keep records for three years after coverage ends

Ongoing, no set date.

Keep the SWPPP and modifications, Part 6.5 documentation, corrective action and AIM records, reports, certifications, monitoring data and NOI data.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 after coverage expires or is terminated years.

**Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.7, page 68**

> "for a period of at least three years from the date that your coverage under this permit expires or is terminated."

[Open the permit at this section](https://www.epa.gov/sites/default/files/2021-01/documents/2021_msgp_-_permit_parts_1-7.pdf#page=68)

#### Keep the SWPPP current, signed and on site

Ongoing, no set date.

Keep a complete, signed SWPPP at the facility, immediately available at inspections; modify it based on corrective actions and deadlines under Part 5 and sign each modification.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.
- Signed or certified by a responsible official or duly authorized representative.

**Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 6.1; 6.3; 6.4, page 62**

> "You must modify your SWPPP based on any corrective actions and deadlines required under Part 5."

[Open the permit at this section](https://www.epa.gov/sites/default/files/2021-01/documents/2021_msgp_-_permit_parts_1-7.pdf#page=62)

#### Train employees on the SWPPP

No set date. The permit requires the SWPPP to state the training frequency/schedule (6.2.5.1.e) but does not set one.

Train all employees who work in exposed areas or carry out permit duties (including the pollution prevention team) on the topics in Part 2.1.2.8, on the frequency set in the SWPPP, and keep a training log.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 2.1.2.8; 6.2.5.1.e, page 23**

> "You must train all employees who work in areas where industrial materials or activities are exposed to stormwater, or who are responsible for implementing activities necessary to comply with this permit"

[Open the permit at this section](https://www.epa.gov/sites/default/files/2021-01/documents/2021_msgp_-_permit_parts_1-7.pdf#page=23)

### Only if...  1 duty

These apply only in the situation named on each one. Answer the questions to sort them.

#### (Guam) Keep a Spill Prevention and Containment Plan and spill response materials

Ongoing, no set date.

Facilities in Guam develop and implement a Spill Prevention and Containment Plan and keep adequate spill response materials on hand for releases of oil, petroleum or other materials into territorial waters.

- **Only if:** the facility is in Guam.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.9.4.2.g, page 231**

> "The Permittee shall develop and implement a Spill Prevention and Containment Plan."

[Open the permit at this section](https://www.epa.gov/sites/default/files/2021-01/documents/2021_msgp_-_permit_part_9_-_cwa_401_conditions.pdf#page=23)

## Try it with your own numbers

The free tools use the same permit data as this page. No account.

[Work out a revision deadline](https://stormdue.com/tools/deadline-calculator)

## Questions people ask

**When do I have to update my SWPPP?**

California Industrial General Permit (IGP): Implement SWPPP changes within 90 days of the Annual Evaluation. When: Within 90 days after annual evaluation date. Facility discharging to ocean waters sets up an Ocean Plan monitoring program before operating. When: At least 7 days before start of industrial activity. Upload a significantly revised inactive mining SWPPP within 30 days. When: Within 30 days after date of significant revision. Upload a significantly revised SWPPP within 30 days. When: Within 30 days after date of significant revision. Keep the SWPPP current and on site. When: Ongoing, no set date. Texas MSGP: Update the exposed-materials inventory and narrative within 30 days of a significant change. When: Within 30 days after date of significant change. Keep the SWP3 current, dated and available. When: Ongoing, no set date. Washington ISGP: Keep the SWPPP current and re-sign it after each required revision. When: No set date. Event-driven; 30 days after an Ecology deficiency notice (S3.A.3.a.ii). EPA 2021 MSGP: Update the public SWPPP within 45 days after the year's last routine inspection. When: Within 45 days after final routine inspection of year. Keep the SWPPP current, signed and on site. When: Ongoing, no set date.

**How long do I keep stormwater records?**

California Industrial General Permit (IGP): Keep all monitoring records and reports for five years; Track NAL exceedances and Level status for each parameter. Texas MSGP: Keep records three years. Washington ISGP: Keep records five years and produce them within 14 days of a written request. EPA 2021 MSGP: Keep records for three years after coverage ends.

**How often is stormwater training required?**

California Industrial General Permit (IGP): Train the team members who carry out the permit. When: No set date. The permit requires a training schedule but sets no frequency; the facility's own SWPPP schedule governs. Annual training for employees handling plastic materials. When: No set date. "annually"; calendar vs reporting year not stated. Texas MSGP: Employee stormwater training at least once a year. When: No set date. "Training must be conducted at least once per year" (III.A.4(g)(1)): TCEQ to confirm whether this means once each calendar year or no more than 12 months between sessions. Washington ISGP: Train all employees every year; new hires within 90 or 30 days. When: By December 31 each year. EPA 2021 MSGP: Train employees on the SWPPP. When: No set date. The permit requires the SWPPP to state the training frequency/schedule (6.2.5.1.e) but does not set one.

## More permit duty guides

- ### Inspection requirements
  Monthly, quarterly and yearly checks, and what to record.
- ### Sampling and qualifying storms
  Which storm counts, how many samples, and the windows.
- ### Report due dates
  Annual reports, DMRs and where each one is filed.
- ### Exceedance response
  Level 1, 2 and 3 steps and their deadlines.
- ### No exposure certification
  The eleven questions and how often to renew.

## See the dates for your own permit

Pick your state and coverage. You get each duty's next date and the section it comes from, free.

[Get my permit calendar](https://stormdue.com/lookup) [All guides](https://stormdue.com/guides)

---