# Oklahoma OPDES MSGP OKR05 Due Dates and Duties

> Every recurring duty in the Oklahoma OPDES MSGP OKR05 with its due date rule and permit section, checked November 27, 2026. Get your own dates free.

Canonical page: https://stormdue.com/permits/us-ok-okr05

[States](https://stormdue.com/states) / [Oklahoma](https://stormdue.com/states/ok)

# Oklahoma OPDES MSGP OKR05 due dates and duties

Every duty in the OPDES Multi-Sector General Permit OKR05 for Stormwater Discharges from Industrial Activity within the State of Oklahoma, with when it is due and the section it comes from.

[Get my permit calendar](https://stormdue.com/lookup?state=OK)

Free, no account. Your own dates in a minute.

- 62duties, each cited
- 11on a schedule
- 51when something happens

Set up your facility free to date the ones that count from your own records, such as your last training.

StormDue reminds and keeps records. It does not file anything with the agency and does not certify or guarantee compliance. Check each duty against your permit; you are responsible for your filings.

## What is this permit, and where do I file?

Today

July 5, 2022 July 4, 2027

**Notes on the permit's status and renewal**

The 2022 OKR05 was issued June 3, 2022, took effect July 5, 2022 and expires July 4, 2027 (2023 modification fact sheet; ODEQ's industrial stormwater page FAQ says "June 2027", open question q7). It was modified effective November 1, 2023 (cover page) to stop requiring ACSCER submittal to DEQ: ACSCERs are completed each year by March 1 and kept with the SWP3. Permittees covered before the modification stayed covered without reapplying. On November 27, 2026 the permit was current, not administratively continued; ODEQ's permits-for-public-review list showed no draft renewal. The application fee and annual permit fee are set in OAC 252:606 and a fee applies; ODEQ invoices existing permittees for the annual fee. Transition dates for 2017 permittees and earlier no exposure holders (90 days after July 5, 2022) have passed and are not shown.

## What does full permit coverage require?

Permit coverage: SWP3 first, then an NOI with maps and fees; discharge is authorized only after DEQ issues an authorization.

- Every quarter 2
- Every year 4
- One time 3
- When something happens 18
- Ongoing 2
- Only if... 28
- Where the permit is unclear 1

### Every quarter  2 duties

#### Collect and look at a stormwater sample from each outfall every quarter

By the end of each calendar quarter.

Once each calendar quarter, collect a grab sample from each outfall within the first 30 minutes of discharge from a storm greater than 0.1 inch (at least 72 hours after the last one), examine it in daylight within 60 minutes for color, odor, clarity, solids, foam and oil sheen, and record the results with the SWP3.

- **Does not apply if:** the facility is inactive and unstaffed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 4.2.1.1, page 35**

> "You must perform visual monitoring or assessment of stormwater discharges from your facility and must collect a stormwater sample from each outfall for visual assessment, except as noted in Part 4.2.1.3, once per quarter for the entire permit term."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=43)

#### Inspect the facility once each calendar quarter

By the end of each calendar quarter.

A qualified person familiar with the facility inspects exposed industrial areas, potential pollutant sources, areas with spills or leaks in the past three years, all discharge points and all control measures at least once each calendar quarter, and records the findings on an inspection form kept with the SWP3.

- **Does not apply if:** the facility is inactive and unstaffed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.
- Signed or certified by a responsible official or duly authorized representative.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 3.1, page 31**

> "The qualified personnel must conduct inspections at least quarterly, i.e., once each calendar quarter, or in some instances more frequently, e.g., monthly or weekly; see Part 10 of this permit for sector-specific inspection requirements."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=39)

### Every year  4 duties

#### Do one quarterly inspection each year while stormwater is discharging

By December 31 each year.

At least one routine facility inspection each calendar year must take place while a stormwater discharge is occurring, observing the control measures and all outfalls.

- **Does not apply if:** the facility is inactive and unstaffed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 3.1, page 31**

> "At least once each calendar year, the routine facility inspection must be conducted during a period when a stormwater discharge is occurring."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=39)

#### Complete the Annual Comprehensive Site Compliance Evaluation Report by March 1

By March 1, for the calendar year before.

Each year by March 1, complete the ACSCER on DEQ Form 606-005 for the past calendar year (inspections, visual monitoring, effluent limit violations, noncompliance, corrective actions and the SWP3 review, with a signed certification) and keep it with the SWP3. Send it to DEQ only if DEQ asks.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 7.3, page 58**

> "You must complete an Annual Comprehensive Site Compliance Evaluation Report (ACSCER) using the DEQ Form 606-005, which is available on the DEQ’s website, each year by March 1, containing information generated from the past calendar year"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=66)

#### Review the SWP3 and update the site map at least once a year

Within 1 year after the last review.

Review the SWP3 at least annually, update the site maps for changes during the past year, and modify the SWP3 after significant changes, when controls are not enough, when a control is missing or not maintained, or when an inspection or visual monitoring shows pollution. Modifications are signed and dated.

Further steps with their own deadlines:

- **Update the site maps after the annual review.** The permit gives the timing in words, quoted below. [Section 6.2.9, page 56](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=64)
  > "After conducting annual review of your SWP3, you must update site map(s) of your facility for any changes that occurred during the past year."

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

Inferred from section 6.2.9. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 6.2.9, page 55**

> "You must review your SWP3 at least annually and modify your SWP3 if:"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=63)

#### Train employees at least once a year

Within 1 year after the last training.

Train every employee who works in exposed industrial areas or carries out permit duties, including the stormwater pollution prevention team, at least annually, or more often if turnover is high. Keep training records and attendance lists with the SWP3.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

Inferred from section 2.1.2.10. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 2.1.2.10, page 26**

> "Employee training must be conducted at least annually or more frequently if employee turnover is high."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=34)

### One time  3 duties

#### Apply for coverage under the next permit once DEQ issues it

No set date. The deadline will be set by the next permit, which DEQ had not issued or proposed on 2026-11-27. See open question q7.

To keep discharging after this permit expires, apply for and obtain an authorization under the new permit once DEQ issues it. Missing the new permit's NOI deadline ends coverage.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 8.2, page 61**

> "If you wish to continue an activity regulated by this permit after the expiration date of this permit, you must apply for and obtain an authorization as required by the new permit once DEQ issues it."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=69)

#### Post a permit coverage sign within 60 days of coverage

Within 60 days after you obtain permit coverage.

Post a sign or other notice of permit coverage at a safe, publicly accessible location near the facility, with the authorization number and a contact name or title and phone number, within 60 days of obtaining coverage, and keep it legible until coverage ends.

Further steps with their own deadlines:

- **Update the sign within 14 days of a contact change.** Within 14 days after the contact information on the sign changes. [Section 1.18, page 20](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=28)
  > "If there is any change in the contact information, you must update the sign within 14 days from the date of such change."

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 1.18, page 20**

> "You must post a sign or other notice of your permit coverage at a safe, publicly accessible location in close proximity to your facility ... within 60 days from the date of obtaining permit coverage."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=28)

#### Write the SWP3 before submitting the NOI

No set date. Before the NOI is submitted; the NOI certifies that the SWP3 was prepared or updated (Parts 1.10.1, 1.10.3).

Prepare a Stormwater Pollution Prevention Plan (SWP3) under Part 6 of the permit, signed and certified, before submitting a Notice of Intent. A facility that had an SWP3 under an earlier permit must update it to this permit first.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 6.1, page 45**

> "You must prepare an SWP3 for your industrial facility/activity before submitting an NOI to DEQ for permit coverage."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=53)

### When something happens  18 duties

#### Facilities in a sensitive water or watershed: inspect significant activity areas monthly

By the end of each month.

A facility located within a federal or state sensitive water or watershed (Appendix A, for endangered and threatened species) includes in its SWP3 a schedule of monthly inspections of areas with significant activities.

- **When:** the facility is in a sensitive water or watershed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

Inferred from Appendix A, Step 2.1.c. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section Appendix A, Step 2.1.c, page 152**

> "Monthly inspection shall be conducted for areas of the facility with significant activities."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=160)

#### Coal storage pile runoff: sample once a year against the coal pile limits

By December 31 each year.

Any facility with stormwater runoff from coal storage piles meets the Table 2-2 limits (TSS and pH) for all discharges containing that runoff, and takes and analyzes grab samples once each year from January 1 to December 31. Do not dilute coal pile runoff to meet the limits.

- **When:** the facility discharges coal storage pile runoff.

- You file it in the agency's system (DEQ eDMR tool).
- Keep the records 3 years.
- The permit says this is done by an accredited laboratory.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 4.1.3, page 33**

> "If you discharge coal storage pile runoff, you must conduct effluent monitoring and collect grab samples and analyze the samples annually within the following time periods:"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=41)

#### Inspect and maintain baghouses at least quarterly

By the end of each calendar quarter.

If the facility has baghouses, inspect and maintain them at least quarterly to prevent the escape of dust, and immediately remove dust accumulated at the base of the exterior baghouse.

- **When:** the facility has baghouses.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

Inferred from section 2.1.2.3.c. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 2.1.2.3.c, page 23**

> "Inspecting and maintaining baghouses, if present, at least quarterly to prevent the escape of dust from the system and immediately removing any accumulated dust at the base of the exterior baghouse"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=31)

#### Change of owner or operator: file the NOT and the new NOI at least 30 days before the change

At least 30 days before you take over operational control.

Coverage cannot be transferred. When ownership or operational control changes, the previous operator submits a Notice of Termination and the new operator submits an NOI (or a No Exposure Certification) at least 30 days before taking over operational control.

- **When:** ownership or operational control changes.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 1.17, page 19**

> "the new operator must submit a complete and accurate NOI or NEC form certified by the new owner or operator to DEQ at least 30 days prior to taking over operational control of the facility."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=27)

#### Discharging through an MS4: send a signed copy of the NOI to the MS4 operator

No set date. The permit sets no separate deadline for the MS4 copy.

If the facility discharges through or into a municipal separate storm sewer system, send a signed copy of the NOI to the MS4 operator, and a copy of the SWP3 if the MS4 operator asks.

- **When:** the facility discharges through an MS4.

- You send a copy to the operator of your storm sewer system (MS4).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 1.10.6, page 16**

> "If your facility discharges through an MS4, or into an MS4 that has been designated by the permitting authority, you must also submit a signed copy of the NOI to the MS4 operator."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=24)

#### Document a corrective action condition within 24 hours

Within 24 hours after you become aware of the condition.

Within 24 hours of becoming aware of a Part 5.1 or 5.2 condition, document it (what happened, when, any discharge, immediate actions). Within 14 days, document the corrective actions, their dates, whether the SWP3 changes, and a signed certification. Keep the report with the SWP3.

Further steps with their own deadlines:

- **Document the corrective actions within 14 days.** Within 14 days after you discover the condition. [Section 5.3.3, page 43](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=51)
  > "Within 14 days from the time of discovery of any of those conditions listed in Part 5.1 or Part 5.2, you must document the following information:"

- **When:** a corrective action condition happens.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 5.3.3, page 43**

> "You must document the existence of any of the conditions listed in Part 5.1 or Part 5.2 within 24 hours of becoming aware of such condition."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=51)

#### Finish corrective action within 14 days of finding the problem

Within 14 days after you discover the condition.

When a Part 5.1 condition occurs (unauthorized release, effluent limit violation, controls not stringent enough, a control missing or not maintained, or evidence of pollution), act immediately to minimize discharges, and complete the corrective action before the next storm if possible and within 14 calendar days.

Further steps with their own deadlines:

- **Update the SWP3 within 14 days of finishing the work.** Within 14 days after the corrective action work is finished. [Section 5.3.2, page 43](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=51)
  > "you must modify your SWP3 accordingly within 14 calendar days of completing corrective action work."

- **When:** a corrective action condition happens.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 5.3.2, page 42**

> "you must complete the corrective actions (e.g., install a new or modified control and make it operational, complete the repair) ... within 14 calendar days from the time of discovery of the corrective action condition."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=50)

#### Finish repairs or replacement of stormwater controls within 14 days

Within 14 days after you discover the problem.

Do routine maintenance immediately. When a control needs repair or replacement, take all reasonable steps at once to minimize discharges and complete the final repair within 14 days, or notify DEQ and document the reason if it will take longer.

- **When:** a control measure needs repair or replacement.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 2.1.2.3, page 24**

> "Final repairs/replacement of stormwater controls should be completed as soon as feasible but must be no later than the timeframe established in Part 5.3 for corrective actions, i.e., within 14 days."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=32)

#### Give DEQ written notice at least 30 days before significant planned changes

At least 30 days before the alteration starts.

Give DEQ written notice no later than 30 days before planned physical alterations or additions that would make the facility a new source or could significantly change the nature or increase the quantity of pollutants discharged.

- **When:** a physical alteration is planned.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 7.5, page 59**

> "You must give written notice to DEQ promptly, no later than 30 days prior to making any planned physical alterations or additions to the permitted facility"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=67)

#### In an Outstanding Resource Water watershed: send the certification of industrial existence with the NOI

No set date. With the NOI.

A facility located within the watershed of a designated Outstanding Resource Water submits DEQ Form 606-006, a certification of industrial existence, along with its NOI. New discharges to ORW waters that began after June 25, 1992 are not eligible for this permit.

- **When:** the facility is in an Outstanding Resource Water watershed.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 1.9.8, page 14**

> "If your facility is located within the watershed of a designated ORW, you must submit a certification of industrial existence using the DEQ Form 606-006 along with your NOI."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=22)

#### New facility, new operator or new location: submit the NOI at least 30 days before operating

At least 30 days before operation starts.

Submit a complete NOI (DEQ Form 606-002B) with a general location map, site maps and the fees, at least 30 days before operation, and receive DEQ's authorization before starting operation with industrial stormwater discharges.

- **When:** there is a new discharge, a new operator or a new location.

- You file it in the agency's system (DEQ OKR05 online application, or email, fax or mail to the ECLS Stormwater Unit).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 1.10.4, Table 1-4, page 16**

> "An NOI must be submitted to DEQ at least 30 days prior to operation."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=24)

#### New facility: SWP3 preparer visits within one year after construction

Within 1 year after construction is finished.

For a new facility, the SWP3 preparer visits the site within one year after construction is completed and makes any needed updates to the SWP3.

- **When:** construction of the new facility is complete.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 6.1, page 45**

> "For new facilities, the SWP3 preparer must visit the site within one year after construction is completed and make any necessary updates to the SWP3."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=53)

#### Promptly correct missing or wrong facts in the NOI or a report

No set date. Promptly; the permit sets no number of days.

If you learn that relevant facts were left out of the NOI, or that the NOI or a report had incorrect information, promptly submit the facts to DEQ.

- **When:** you find missing or incorrect information.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 7.5, page 60**

> "You must promptly submit facts or information if you become aware that you failed to submit relevant facts in your NOI, or that you submitted incorrect information in your NOI or in any report."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=68)

#### Report a reportable quantity spill as soon as you know of it

No set date. As soon as you have knowledge of the discharge.

When a leak, spill or other release of a hazardous substance or oil at or above a reportable quantity (40 CFR Parts 110, 117 or 302) occurs in a 24-hour period, notify the National Response Center or EPA Region 6 and the DEQ Hotline as soon as you know of it.

- **When:** a release of a reportable quantity happens.

- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 2.1.2.4, page 25**

> "you must notify the National Response Center (NRC) at (800) 424-8802 or EPA Region 6 at 1-800-887-6063 and the DEQ Hotline at 1-800-522-0206 as soon as you have knowledge of the discharge."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=33)

#### Report other noncompliance with the monitoring reports

No set date. With the next monitoring report.

Report all instances of noncompliance not reported elsewhere at the time monitoring reports are submitted.

- **When:** noncompliance happens that has not been reported.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 7.5, page 60**

> "You must report all instances of noncompliance not reported in your annual report, compliance schedule report, or 24-hour report at the time monitoring reports are submitted"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=68)

#### Send DEQ an updated SWP3 within 14 days of a request

Within 14 days after you receive the request.

When DEQ asks for the SWP3, submit an updated version within 14 days of receiving the request.

- **When:** DEQ asks for the SWP3.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 1.10.2, page 15**

> "You must submit an updated version of your SWP3 within 14 days upon receipt of such request from DEQ."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=23)

#### Submit a Notice of Termination within 30 days when coverage should end

Within 30 days after a condition for ending coverage is met.

Submit a complete NOT (DEQ Form 606-003) within 30 days after a new owner or operator takes over, operations stop with no more industrial stormwater discharges (and needed erosion controls are in place), or all discharges are covered by another permit. Coverage ends when DEQ issues its termination letter.

- **When:** a condition for ending coverage is met.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 1.15.2, page 18**

> "You must submit an NOT form within 30 days after one or more of the following conditions have been met:"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=26)

#### Tell DEQ in advance about planned changes expected to cause noncompliance

No set date. In advance; the permit sets no number of days.

Give DEQ advance notice of any planned change in the facility or activity that you expect will result in noncompliance with permit requirements.

- **When:** a planned change is expected to cause noncompliance.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 7.5, page 59**

> "You must give advance notice to DEQ of any planned changes in the permitted facility or activity which you anticipate will result in noncompliance with permit requirements."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=67)

### Ongoing  2 duties

#### Keep permit records for three years after coverage ends

No set date. A standing duty with no date.

Keep the SWP3 and its changes, the NOI and DEQ correspondence, the authorization, maintenance records, inspection reports, monitoring data, lab reports, corrective action records, ACSCERs and other reports for at least three years from the date coverage expires or is terminated.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 7.6, page 60**

> "You must retain all the following documents for a period of at least three years from the date that your coverage under this permit expires or is terminated:"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=68)

#### Keep the SWP3 and its records at the facility

No set date. A standing duty with no date.

Keep a complete, current SWP3 at the facility with the authorization, maintenance records, inspection reports, monitoring data, lab reports, corrective action records and completed ACSCERs, immediately available to employees, DEQ, EPA, the MS4 and the U.S. Fish and Wildlife Service during an inspection.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 6.3, page 57**

> "Regardless of the format, the SWP3 and other associated documents must be immediately available to facility employees, DEQ, EPA, the staff of an MS4 into which you discharge"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=65)

### Only if...  28 duties

These apply only in the situation named on each one. Answer the questions to sort them.

#### Sector E: sweep weekly where cement, aggregate or dust is handled

By the end of each week.

Sweep or vacuum (or wash down and collect) paved areas at least once a week where cement, aggregate, kiln dust, fly ash or settled dust are handled or processed and may be discharged in stormwater; record the frequency in the SWP3.

- **Only if:** your permit sector is E; the facility handles cement, aggregate, kiln dust, fly ash or settled dust.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.E.3, page 82**

> "it must be performed at least once a week in areas where cement, aggregate, kiln dust, fly ash or settled dust are being handled or processed and may be discharged in stormwater."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=90)

#### Sector I: inspect erosion and sediment controls every 7 days

By the end of each week.

Inspect all erosion and sediment controls once every 7 calendar days, or once every 14 calendar days and within 24 hours of a storm of 0.5 inches or more. Remote, unstaffed, temporarily or permanently inactive sites inspect at least annually.

- **Only if:** your permit sector is I.
- **Does not apply if:** the site is a remote, unstaffed, inactive oil and gas site.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 10.I.5.3. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.I.5.3, page 94**

> "All erosion and sediment controls must be inspected either: 1) once every 7 calendar days or 2) once every 14 calendar days and within 24 hours of a storm event of 0.5 inches or greater."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=102)

#### Sector L operating landfills and land application sites: inspect every seven days

By the end of each week.

Inspect operating landfills and land application sites at least once every seven days, focusing on areas not finally stabilized, active application areas, exposed storage, controls, leachate systems and vehicle entrances.

- **Only if:** your permit sector is L.
- **Does not apply if:** the landfill is inactive; the landfill is stabilized or land application is complete.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.L.7.3, page 115**

> "Inspect operating landfills, and land application sites at least once every seven days."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=123)

#### Sector S airports: inspect weekly during deicing season

By the end of each week.

Conduct routine facility inspections at least once a week during the deicing season (for example October through April) and in any other week deicing chemicals may be used, and keep weekly inspections while large spills or water quality impacts continue.

- **Only if:** your permit sector is S; it is the deicing season.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.S.5.5, page 134**

> "At a minimum, conduct routine facility inspections at least once per week during deicing season (e.g., October through April)."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=142)

#### Sector A wood surface protection or preserving: inspect treatment areas monthly

By the end of each month.

Facilities that protect or preserve wood surfaces inspect processing areas, transport areas and treated wood storage areas monthly.

- **Only if:** your permit sector is A; the facility does wood surface protection or preservation.
- **Does not apply if:** the facility is inactive and unstaffed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 10.A.5.4. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.A.5.4, page 76**

> "If your facility performs wood surface protection and preservation activities, inspect processing areas, transport areas, and treated wood storage areas monthly"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=84)

#### Sector D asphalt and roofing: inspect at least once a month

By the end of each month.

Sector D facilities inspect at least once per month, with attention to material storage and handling areas, liquid storage tanks, hoppers and silos, vehicle and equipment areas and processing areas, and take corrective action as needed.

- **Only if:** your permit sector is D.
- **Does not apply if:** the facility is inactive and unstaffed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 10.D.4.1. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.D.4.1, page 80**

> "Inspect at least once per month. Special attention must be given to the following areas:"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=88)

#### Sector G active metal mines: inspect at least monthly

By the end of each month.

Inspect active metal mining sites at least monthly. Temporarily inactive sites inspect at least quarterly unless weather makes them inaccessible.

- **Only if:** your permit sector is G.
- **Does not apply if:** the mine is temporarily inactive; the facility is inactive and unstaffed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 10.G.7.4. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.G.7.4, page 88**

> "Inspect active mining sites at least monthly. Inspect temporarily inactive sites at least quarterly unless adverse weather conditions make the site inaccessible."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=96)

#### Sector J mines discharging to waters impaired for sediment or nitrogen: inspect monthly

By the end of each month.

Mineral mining sites that discharge to waters impaired for sediment or nitrogen inspect monthly instead of quarterly.

- **Only if:** your permit sector is J; the facility discharges to a water impaired for sediment or nitrogen.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 10.J.7.7. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.J.7.7, page 103**

> "Sites which discharge to waters which are impaired for sediment or nitrogen must be inspected monthly."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=111)

#### Sector L stabilized areas: inspect at least once a month

By the end of each month.

For stabilized sites, areas where land application is completed, or arid or semi-arid sites, inspect at least once every month.

- **Only if:** your permit sector is L; the landfill is stabilized or land application is complete.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 10.L.7.3. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.L.7.3, page 115**

> "For stabilized sites and areas where land application has been completed, or where the climate is arid or semi-arid, conduct inspections at least once every month."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=123)

#### Sector O steam electric: inspect coal, ash, fuel and storage areas monthly

By the end of each month.

Inspect coal handling, loading and unloading, switchyards, fueling, bulk storage, ash handling, areas next to disposal ponds and landfills, maintenance areas, liquid tanks and material storage areas monthly.

- **Only if:** your permit sector is O.
- **Does not apply if:** the facility is inactive and unstaffed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 10.O.5.3. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.O.5.3, page 124**

> "As part of the inspection, the following areas must be inspected monthly: coal handling areas, loading or unloading areas, switchyards, fueling areas, bulk storage areas, ash handling areas"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=132)

#### Sector V textiles and leather: inspect at least monthly

By the end of each month.

Inspect at least monthly transfer and transmission lines, spill prevention, good housekeeping, process waste management and all management practices.

- **Only if:** your permit sector is V.
- **Does not apply if:** the facility is inactive and unstaffed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 10.V.5.3. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.V.5.3, page 139**

> "Inspect at least monthly, the following activities and areas (at a minimum): transfer and transmission lines, spill prevention, good housekeeping practices"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=147)

#### Sectors Q and R: clean blasting debris and paint chips from conveyances monthly

By the end of each month.

At least once per month, clean stormwater conveyances of deposits of abrasive blasting debris and paint chips.

- **Only if:** your permit sector is Q, R.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

Inferred from section 10.Q.4.1.b. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.Q.4.1.b, page 127**

> "At least once per month, you must clean stormwater conveyances of deposits of abrasive blasting debris and paint chips."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=135)

#### Discharging through a regulated MS4: send signed DMR copies to the MS4 operator

By December 31 each year.

If the facility discharges through a regulated MS4, also send signed copies of its DMRs to the MS4 operator.

- **Only if:** your discharge is subject to federal effluent limitation guidelines (ELGs); the facility discharges through a regulated MS4.

- You send a copy to the operator of your storm sewer system (MS4).
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

Inferred from section 7.2. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 7.2, page 58**

> "If you discharge stormwater associated with industrial activity through a regulated MS4, you must also submit signed copies of your DMR to the operator of the MS4 in accordance with dates in Part 4.1."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=66)

#### Discharging to a water with a TMDL: monitor the TMDL pollutants at least once a year

By December 31 each year.

Where a TMDL or watershed plan sets a wasteload or load allocation for the facility's discharge, monitor those pollutants at the frequency the TMDL sets or at least once a year, and adopt the allocation as a measurable goal in the SWP3.

- **Only if:** a TMDL applies to your discharge.
- **Does not apply if:** the facility is inactive and unstaffed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by an accredited laboratory.

Inferred from section 4.2.3.1. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 4.2.3.1, page 40**

> "You must monitor all pollutants for which a WLA or LA has been established for your discharges at the frequencies established in the TMDL or watershed plan, or at a minimum of once per year."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=48)

#### Discharging to an impaired water without a TMDL: sample once a year for the impairment pollutants

By December 31 each year, starting with the calendar year that includes the first full quarter after your coverage begins.

A facility within one mile of a 303(d)-listed water (Part 2.2.2) with no TMDL or watershed plan monitors each outfall to it once a year for every pollutant causing the impairment that has a standard analytical method, or its indicator (TSS for sediment, E. coli for bacteria).

- **Only if:** your stormwater reaches an impaired water body.
- **Does not apply if:** a TMDL applies to your discharge; the facility is inactive and unstaffed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by an accredited laboratory.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 4.2.3.1, page 39**

> "Beginning in the first full quarter following October 1, 2022, or your date of discharge authorization, whichever date comes later, you must monitor all pollutants for which the waterbody is impaired and for which a standard analytical method exists"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=47)

#### Effluent limit discharges: sample each outfall once a year

By December 31 each year, starting with the calendar year that includes the first full quarter after your coverage begins.

Facilities with a discharge covered by a numeric effluent limit (Table 4-2: Sectors A wet decking, C phosphate fertilizer, D asphalt emulsion, E cement storage piles, J mine dewatering, K and L landfills, O coal piles, S airport deicing) sample each such outfall once each calendar year for the parameters in Part 10. An exceedance is a permit violation.

- **Only if:** your discharge is subject to federal effluent limitation guidelines (ELGs).

- You file it in the agency's system (DEQ eDMR tool).
- Keep the records 3 years.
- The permit says this is done by an accredited laboratory.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 4.2.2.1, page 38**

> "Beginning in the first full quarter following October 1, 2022, or your date of discharge authorization, whichever date comes later, you must monitor once per year (the yearly monitoring period is from January 1 to December 31)"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=46)

#### Inactive and unstaffed site with no exposure: inspect once a year

By December 31 each year.

A facility that is inactive and unstaffed with no industrial materials or activities exposed to stormwater inspects once per year instead of quarterly, with a signed statement in the SWP3. Routine inspections resume immediately if that changes.

- **Only if:** the facility is inactive and unstaffed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 3.3. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 3.3, page 32**

> "Such a facility is only required to conduct site inspections once per year in accordance with Part 3.1."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=40)

#### Report the annual monitoring results on the eDMR by January 15

By January 15, for the calendar year before.

Report effluent limit monitoring (and coal pile monitoring) through DEQ's eDMR tool no later than the 15th day of the month after the reporting period ends, which for the January to December monitoring year is January 15. With no discharge in the year, submit an eDMR stating "No Discharge" by January 15.

Further steps with their own deadlines:

- **No discharge in the year: submit a No Discharge eDMR.** By January 15, for the calendar year before. [Section 7.1, page 58](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=66)
  > "If your facility does not have any discharges during the reporting period, you are still required to submit an eDMR to DEQ stating “No Discharge” each year by January 15."

- **Only if:** your discharge is subject to federal effluent limitation guidelines (ELGs).

- You file it in the agency's system (DEQ eDMR tool).
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

Inferred from section 7.1. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 7.1, page 58**

> "to DEQ electronically using the eDMR (electronic Discharge Monitoring Report) tool available on DEQ’s website no later than the 15th day of the month after the end of the reporting period"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=66)

#### After an effluent limit violation: change the SWP3 and controls within 14 days

Within 14 days after you discover an effluent limit violation.

Investigate at once. Start SWP3 changes adding structural controls and document all corrective actions, including BMP improvements, no later than 14 days after discovery; finish installation or repair within 28 days if 14 is not feasible; do follow-up sampling within 30 days of the corrective action; then sample quarterly until the discharge meets the limit.

Further steps with their own deadlines:

- **Finish the installation or repair.** Within 28 days after you discover an effluent limit violation. [Section 4.2.2.3, page 39](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=47)
  > "Install a new or repair an existing control measure to make it operational as soon as possible. ... no later than 28 days after discovery."
- **Follow-up monitoring after the corrective action.** Within 30 days after the corrective action is in place. [Section 4.2.2.3, page 38](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=46)
  > "conduct follow-up monitoring within 30 calendar days (or during the next qualifying runoff event, should none occur within 30 days) of implementing corrective action(s) taken in accordance with Part 5."
- **Monitor quarterly until the discharge meets the limit.** The permit gives the timing in words, quoted below. [Section 4.2.2.3, page 38](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=46)
  > "You must continue to monitor at least quarterly and submit quarterly eDMRs until your discharge is in compliance with the effluent limit or until DEQ waives the requirement for additional monitoring."

- **Only if:** your discharge is subject to federal effluent limitation guidelines (ELGs); an effluent limit is exceeded.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 4.2.2.3, page 39**

> "Initiate modifications to the SWP3 to include additional structural controls/BMPs and document all corrective actions necessary to meet the applicable effluent limit ... no later than 14 days after discovery of an effluent limit violation."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=47)

#### Impairment pollutant detected: change the SWP3 and controls within 14 days

Within 14 days after you discover the detection.

If a pollutant of concern is detected in impaired waters monitoring, keep monitoring it and start SWP3 changes adding structural controls no later than 14 days after discovery, finishing the work within 28 days if 14 is not feasible.

Further steps with their own deadlines:

- **Finish the work if 14 days is not feasible.** Within 28 days after you discover the detection. [Section 4.2.3.1, page 40](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=48)
  > "If the permittee is unable to complete the installation or repair within 14 calendar days, the permittee shall document why it is infeasible within the 14-day timeframe and complete the necessary work as soon as practicable but no later than 28 days after discovery."

- **Only if:** your stormwater reaches an impaired water body; a pollutant of concern is detected.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 4.2.3.1, page 40**

> "Initiate modifications to the SWP3 to include additional structural controls/BMPs and document all corrective actions necessary, including improvements to BMP, immediately but no later than 14 days after discovery of a pollutant of concern’s detection."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=48)

#### Sector I: start vegetating disturbed areas within 14 days

Within 14 days after the last activity in the area.

Begin appropriate vegetative practices on all disturbed areas within 14 days after the last activity in that area.

- **Only if:** your permit sector is I; an area is disturbed.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.I.4.1, page 93**

> "Begin implementing appropriate vegetative practices on all disturbed areas within 14 days following the last activity in that area."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=101)

#### Sector J mine site preparation: inspect every 14 days and after 0.5 inch storms

Within 14 days after the last inspection.

During earth-disturbing work before active mining, inspect disturbed areas, controls, stabilized areas, storage areas, flow paths and discharge points at least once every 14 calendar days and within 24 hours of a storm of 0.5 inches or more, and complete a signed report within 24 hours.

Further steps with their own deadlines:

- **Complete the inspection report within 24 hours.** Within 24 hours after the inspection. [Section 10.J.6.3, page 102](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=110)
  > "Within 24 hours of an inspection, you must complete a report that includes the inspection date"

- **Only if:** your permit sector is J; earth-disturbing activities are under way before active mining.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.J.6.3, page 102**

> "You must inspect at least once every 14 calendar days and within 24 hours of a storm event of 0.5 inches or greater."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=110)

#### Sector J mine site preparation: stabilize within 14 days after work stops

Within 14 days after earth-disturbing activities stop.

Start stabilization immediately where earth-disturbing work for mine site preparation stops, and in no case more than 14 days after it stops; then seed or install non-vegetative measures within 14 days of starting stabilization.

Further steps with their own deadlines:

- **Seed or install stabilization within 14 days of starting it.** Within 14 days after stabilization starts. [Section 10.J.6.1.p, page 101](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=109)
  > "If using vegetative measures, by no later than 14 days after initiating stabilization:"

- **Only if:** your permit sector is J; earth-disturbing activities are under way before active mining.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.J.6.1.p, page 101**

> "but in no case more than 14 days after such activities have temporarily ceased."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=109)

#### Sector L new cell construction: inspect every 14 days and after 0.5 inch storms

Within 14 days after the last inspection.

During new cell construction at an operating landfill, inspect at least once every 14 calendar days and within 24 hours of a storm of 0.5 inches or more, and complete a signed report within 24 hours.

- **Only if:** your permit sector is L; a new cell is being built.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.L.6.3, page 114**

> "You must perform inspections at least once every 14 calendar days and within 24 hours of a storm event of 0.5 inches or greater."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=122)

#### Sector M: final inspection within 30 days before filing the NOT

Before you file the NOT.

Within 30 days before filing a Notice of Termination, inspect the facility and document that spill materials, recoverable fluids, mercury switches, batteries, fluid tanks and salvaged parts have been removed or properly handled.

- **Only if:** your permit sector is M; you plan to file a Notice of Termination.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

Inferred from section 10.M.4.3. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.M.4.3, page 117**

> "Within 30 days prior to filing an NOT to terminate permit coverage, you are required to conduct a final inspection of your facility."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=125)

#### Sector M: inspect arriving vehicles for leaks

No set date. Immediately, or as soon thereafter as practicable.

Inspect vehicles arriving at the salvage yard for leaks immediately, or as soon as practicable.

- **Only if:** your permit sector is M; the vehicle arrives.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 10.M.4.3, page 117**

> "Immediately (or as soon thereafter as practicable) inspect vehicles arriving at the site for leaks."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=125)

#### Send DEQ an exceedance report within 30 days of the follow-up lab results

Within 30 days after you receive the follow-up laboratory results.

Submit an exceedance report to DEQ with the authorization number, facility, receiving water, monitoring data from this and earlier events, what was done and is planned to correct the violation, and a contact, no later than 30 days after receiving the laboratory results.

- **Only if:** your discharge is subject to federal effluent limitation guidelines (ELGs); an effluent limit is exceeded.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

Inferred from section 7.4. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 7.4, page 59**

> "If follow-up monitoring per Part 4.2.2.3 exceeds a numeric effluent limit, you must submit an exceedance report to DEQ no later than 30 days after you have received your laboratory results"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=67)

#### Water with a TMDL: evaluate the TMDL BMPs at least once a year

Within 1 year after the last evaluation.

An existing discharger to a water with a TMDL or watershed plan evaluates its TMDL BMPs at least once per year and reports the results in the ACSCER; a BMP found ineffective is replaced within one year.

Further steps with their own deadlines:

- **Put an alternative BMP in place within one year.** Within 1 year after you determine that a BMP is not working. [Section 2.2.2.1, page 29](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=37)
  > "If a selected BMP does not reduce the discharge of pollutants of concern, implement alternative BMP within one year of determining a BMP is ineffective."

- **Only if:** a TMDL applies to your discharge.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

Inferred from section 2.2.2.1. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 2.2.2.1, page 29**

> "These BMPs shall be evaluated at least once per year to assess the effectiveness in reducing the discharge of pollutants of concern."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=37)

### Where the permit is unclear  1 duty

The permit text leaves the timing of these open, so no date is shown. Each one quotes the clause and names the section to check.

#### Contact or address change: submit an NOI modification

No set date. Part 8.16.3 says a change in contact information or facility address is submitted "within the time frame specified in Part 1.10.4". Table 1-4 sets deadlines only for 2017 permittees and for new discharges, owners, operators or locations. What deadline applies to a contact or address change?

If only the contact information or the facility address on the NOI changes, submit a modification to the existing NOI. The permit points to the time frame in Part 1.10.4, which does not name this case, so no date is shown.

- **When:** the contact or address in your NOI changes.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 8.16.3, page 66**

> "The change in authorization must be submitted within the time frame specified in Part 1.10.4 and sent to the address specified in Part 1.10.5."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=74)

## What does no-exposure certification require?

No Exposure Certification (DEQ Form 606-004) with maps, confirmed by DEQ; resubmitted every five years.

- Every few years 1
- One time 1
- When something happens 2

### Every few years  1 duty

#### No exposure: submit the NEC again every five years

Within 5 years after your last no exposure certification.

Submit a new No Exposure Certification to DEQ once every five years.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

Inferred from section 1.16. Check your copy of the permit.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 1.16, page 19**

> "You must submit an NEC form to DEQ once every 5 years."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=27)

### One time  1 duty

#### No exposure: file the No Exposure Certification with maps

No set date. The permit sets no date for a first certification.

A facility that qualifies for the no exposure exclusion files DEQ Form 606-004 with a general location map and site maps. Once DEQ confirms it, no authorization or SWP3 is needed. The exclusion covers the whole facility, not single outfalls.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 1.16, page 19**

> "you may file a No Exposure Certification (NEC) form, DEQ Form 606-004, along with a general location map of your facility in accordance with Part 6.2.2.4 and site map(s) of your facility"

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=27)

### When something happens  2 duties

#### No exposure: get permit coverage before a change that ends no exposure

No set date. Before the change starts; the permit sets no number of days. A new NOI is due at least 30 days before operation (Table 1-4).

Before making any change that would end the condition of no exposure, apply for permit coverage and receive an authorization.

- **When:** a planned change will end no exposure.

- You send it to the agency (DEQ Environmental Complaints and Local Services Division, Stormwater Unit: ecls-stormwaterpermitting@deq.ok.gov, fax or mail).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 1.16, page 19**

> "If you plan to make any changes to your facility that will result in failure to maintain a condition of no exposure at the facility, you must apply for permit coverage and receive an authorization before commencing any changes."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=27)

#### No exposure: send a copy of the NEC to the MS4 operator

No set date. The permit sets no deadline.

A facility that qualifies for the exclusion and used to discharge stormwater to an MS4 gives the MS4 operator a copy of the NEC form.

- **When:** the facility used to discharge to an MS4.

- You send a copy to the operator of your storm sewer system (MS4).
- Keep the records 3 years.

**Source: OPDES Multi-Sector General Permit OKR05 (2022, modified effective November 1, 2023), with Appendices A to C, section 1.16, page 19**

> "Facilities that qualify for this exclusion and that used to contribute stormwater discharges to an MS4 shall provide a copy of the NEC form to the operator of the MS4."

[Open the permit at this section](https://oklahoma.gov/content/dam/ok/en/deq/documents/water-division/2022-OKR05_Modified_Permit_11-2023.pdf#page=27)

## Get your own dates

Choose your coverage and answer a few questions. You get each duty's next date and a calendar file.

## Oklahoma OPDES MSGP OKR05 duties, topic by topic

How the Oklahoma OPDES MSGP OKR05 compares with the other checked permits on each kind of duty, in the permit's own words with the section for each:

- [Inspection requirements](https://stormdue.com/guides/stormwater-inspection-requirements#permit-us-ok-okr05)
- [Sampling and qualifying storms](https://stormdue.com/guides/stormwater-sampling-requirements#permit-us-ok-okr05)
- [Report due dates](https://stormdue.com/guides/stormwater-annual-report-due-dates#permit-us-ok-okr05)
- [Exceedance response](https://stormdue.com/guides/benchmark-exceedance-response#permit-us-ok-okr05)
- [No-exposure certification](https://stormdue.com/guides/no-exposure-certification#permit-us-ok-okr05)
- [SWPPP, training and records](https://stormdue.com/guides/swppp-requirements#permit-us-ok-okr05)

- [Every state's permit](https://stormdue.com/states)
- [How we check permit rules](https://stormdue.com/about-the-rules)
- [Deadline calculator](https://stormdue.com/tools/deadline-calculator)
- [Benchmark comparison](https://stormdue.com/tools/benchmark-comparison)
- [More free tools](https://stormdue.com/tools)
- [Duties compared across permits](https://stormdue.com/guides)

---