# South Dakota Industrial Storm Water General Permit SDR000000 due dates and duties

Every duty in the General Permit for Storm Water Discharges Associated with Industrial Activities, Authorization to Discharge under the Surface Water Discharge System, with when it is due and the section it comes from.

[Get my permit calendar](https://stormdue.com/lookup?state=SD)

Free, no account. Your own dates in a minute.

- 49duties, each cited
- 11on a schedule
- 38when something happens

Set up your facility free to date the ones that count from your own records, such as your last training.

StormDue reminds and keeps records. It does not file anything with the agency and does not certify or guarantee compliance. Check each duty against your permit; you are responsible for your filings.

## What is this permit, and where do I file?

**Notes on the permit's status and renewal**

Cover page: "This general permit shall become effective on October 1, 2012" and "shall expire at midnight, September 30, 2017"; the pages carry "Amended: August 27, 2012". The statement of basis names the general permit SDR000000; each facility gets its own SDR00xxxx number. DANR's industrial stormwater page, read November 28, 2026, says the "Industrial General Permit (effective October 1, 2012) has been administratively continued and is in full force and effect until a renewal is issued" and links this file, so it is the current permit (Section 6.2.1). No renewal draft, public notice or modification was posted on DANR's industrial stormwater or public notices pages that day. The agency was the Department of Environment and Natural Resources when the permit was issued; the text still says DENR and SDDENR. Facilities covered when the permit took effect had to update their SWPPP by February 1, 2013 (4.2.2); that date has passed and is not shown. The annual fee (January 31) comes from ARSD chapter 74:52:12 and DANR's page, not the permit. The permit refers to a Section 6.17 for spill reporting that it does not have; Section 2.10 holds the release reporting rules.

## What does full permit coverage require?

Coverage under SDR000000: a SWPPP first, then a signed NOI at least 15 days before industrial activity starts; coverage begins with DANR's letter of authorization.

- Every half year 1
- Every year 4
- One time 4
- When something happens 26
- Ongoing 5
- Only if... 6

### Every half year  1 duty

#### Inspect the site at least twice a year

Within 181 days after the last inspection.

An appropriately trained person familiar with the permit and the SWPPP inspects the site at least semi-annually, to find control measures that need maintenance or changes and to check that the SWPPP is complete and accurate.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 3.9.1. Check your copy of the permit.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.9.1, page 17**

> "site inspections shall be conducted by the permittee at least semi-annually. An appropriately trained person familiar with the general permit conditions and the SWPPP must conduct the inspections."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=17)

### Every year  4 duties

#### Inspect within 24 hours of a large storm or snowmelt once each calendar year

By December 31 each year.

At least one of the site inspections each calendar year is done within 24 hours of a storm event greater than 2 inches, or of snowmelt large enough to cause runoff.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.9.2, page 17**

> "At least one inspection each calendar year must be conducted within 24 hours of a storm event greater than 2 inches or snowmelt large enough to cause runoff."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=17)

#### Monitor storm water once each calendar year

By December 31 each year.

Once each calendar year, within 24 hours of a storm event greater than 2 inches or snowmelt large enough to cause runoff, monitor the discharge for the presence or absence of an oil sheen and of visible pollutants (discoloration and similar), and take an Oil and Grease grab sample (Standard Methods 1664A) if a sheen is seen.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.9.3, page 17**

> "Monitoring shall be performed in accordance with Section 5.1 for the following parameters at least once per calendar year."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=17)

#### Pay the annual permit fee by January 31

By January 31 each year.

Pay DANR the annual industrial stormwater fee by January 31 of each year the facility is covered. A fee applies; the amount depends on the industrial sector (or, for Sector J mining, the unreclaimed acreage) and is listed on DANR's fee page.

- You send it to the agency (DANR, as billed (ARSD chapter 74:52:12)).

**Source: DANR, Stormwater Permit for Industrial Activities (program page: annual fees, electronic reporting, forms), section Annual Fees**

> "Annual fees for coverages under the General Permit for Stormwater Discharges Associated with Industrial Activities (General Permit) will be due annually on January 31 and are based on industrial sectors."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/stormwater/StormwaterIndustrial.aspx#:~:text=will%20be%20due%20annually%20on%20January%2031)

#### Do the comprehensive site compliance evaluation once a year

Within 1 year after the last evaluation.

Once a year, as part of one of the two semiannual inspections, do a comprehensive site compliance evaluation: inspect areas draining to a discharge for pollutants, judge whether control measures are adequate, check structural controls and inspect spill response and other SWPPP equipment. Summarize it in a signed written report kept with the SWPPP.

Further steps with their own deadlines:

- **Revise the description of potential pollutant sources within two weeks.** Within 14 days after the evaluation. [Section 3.8.2, page 16](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=16)
  > "Within two weeks of the inspection, the description of potential pollutant sources identified in the Plan shall be revised based on the results of the inspection."
- **Implement the plan changes within 12 weeks.** Within 84 days after the evaluation. [Section 3.8.2, page 16](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=16)
  > "Within 12 weeks after the inspection, the changes to the plan shall be implemented."

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by qualified personnel, as the permit defines them.
- Signed or certified by a responsible official or duly authorized representative.

Inferred from section 3.8. Check your copy of the permit.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.8, page 16**

> "The permittee shall conduct a comprehensive site compliance evaluation at least once a year as part of one of the two semiannual site inspections required in Section 3.9."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=16)

### One time  4 duties

#### Certify in the SWPPP that the drainage system was checked for non-storm water

No set date. Part of the SWPPP (4.4.5); no separate date.

Include in the SWPPP the signed certification that the storm water drainage system has been tested or evaluated for non-storm water discharges, based on a dry weather screening of all discharge conveyances, inlets and floor drains. A facility that cannot certify notifies the Secretary.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 4.4.5, page 21**

> "The plan shall include a certification the discharge has been tested or evaluated for the presence of non-storm water discharges."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=21)

#### Sample for your industry's parameters in the first year of coverage

No set date. Each industry's own duty below carries the date; this is the general rule (5.1.4).

Facilities in the industries listed in Section 5.1.7 (air transportation with vehicle maintenance, food manufacturing, lumber and wood products, scrap yards, landfills and ethanol manufacturing) sample storm water at least once during their first year of coverage, and report the results with the facility's industrial category. DANR may require more sampling case by case.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 5.1.4, page 25**

> "Sampling and testing of storm water for specific parameters is required at least once during the first year of coverage under the general permit, with additional semiannual monitoring for facilities with coal pile runoff."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=25)

#### Submit an updated NOI to continue under the next permit

No set date. Before the new general permit is issued, as the renewal notice directs (2.6.5, 6.2.2). DANR has not announced a new permit, so there is no date yet.

To keep coverage when DANR issues a new general permit, submit an updated Notice of Intent and Certification of Applicant, with the current permit number, before the new permit is issued and as the renewal notice directs. The current permit ends on the new permit's effective date.

- You file it in the agency's system (EPA NeT (NETMSGP) through a CDX account, or the paper form mailed to DANR Surface Water Quality).
- Keep the records 3 years.
- Signed or certified by a responsible official per sdr000000 6.8.1.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 2.6.5, page 12**

> "If permittees authorized under the existing General Permit need to continue coverage under the new General Permit, an updated Notice of Intent and Certification of Applicant shall be submitted prior to the issuance of the new General Permit"

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=12)

#### Write the SWPPP before the NOI and put it in place before industrial activity starts

No set date. Before the NOI is submitted (4.2.1); the permit gives no number of days.

A new facility develops its Storm Water Pollution Prevention Plan (SWPPP) meeting Part 4 before submitting the Notice of Intent, and puts it in place before any industrial activity begins. The SWPPP stays at the site and is not sent to DANR unless the Secretary asks for it.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 4.2.1, page 19**

> "New facilities. The Plan must be developed prior to the submittal of the NOI form. The Plan must be implemented before initiating any industrial activity."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=19)

### When something happens  26 duties

#### Coal pile runoff: sample twice a year

By the end of each half year (June 30 and December 31).

A facility with storm water discharges from coal pile runoff collects and analyzes at least one sample of a runoff event in each half of the year for Oil and Grease, pH, total suspended solids, and total recoverable copper, nickel and zinc (daily maximum; grab samples, pH instantaneous).

- **When:** the facility discharges storm water from coal pile runoff.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by an accredited laboratory.

Inferred from section 5.1.6.a. Check your copy of the permit.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 5.1.6.a, page 25**

> "The facility is required to collect and analyze at least one sample of a storm water runoff event semi-annually for the following:"

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=25)

#### After a spill, add controls and record it in the SWPPP

No set date. The permit sets no date (3.7.1).

Keep the capacity to control, contain and remove spills. If a spill happens, put control measures in place to protect storm water and add the spill location and any new control measures to the SWPPP.

- **When:** a spill happens at the site.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.7.1, page 16**

> "If spills do occur, the permittee shall implement control measures to minimize the potential for contamination of the storm water and modify the SWPPP with the location of the spill and any new control measures."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=16)

#### Ask for a temporary shutdown exemption

No set date. The permit sets no date (2.4.1).

A facility that is temporarily inactive and meets the no exposure checklist may submit the Temporary Shutdown Notice (Attachment E) with a description of what it did to protect storm water. Once the Secretary approves it in writing, monitoring and inspections are suspended during the shutdown.

- **When:** the facility is temporarily inactive and wants an exemption from monitoring and inspections.

- You send it to the agency (DANR Surface Water Quality Program, 523 East Capitol, Pierre, SD 57501-3182 (Attachment E)).
- Keep the records 3 years.
- Signed or certified by a responsible official per sdr000000 6.8.1.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 2.4.1, page 11**

> "To qualify, the facility must submit a "Temporary Shutdown Notice" form provided by SDDENR (Attachment E) and must be approved by the Secretary for exemption from the monitoring and inspection requirements."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=11)

#### Change the SWPPP if results could cause a water quality violation

No set date. The permit sets no date (5.1.8).

If sample results show pollutant levels that could cause or contribute to exceedances of water quality standards, modify the SWPPP to prevent it happening again.

- **When:** sample results show pollutant levels that could cause or contribute to a water quality standards exceedance.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 5.1.8, page 28**

> "If the sample results show pollutant levels that could cause or contribute to exceedances of water quality standards, the SWPPP must be modified to prevent future occurrences."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=28)

#### Clean up pollutants that leave the site and revise the SWPPP

No set date. At a frequency sufficient to minimize impacts (3.4.2); no date is set.

Minimize dust and vehicle tracking off site, with street sweeping if other practices are not enough. If pollutants escape the site, remove the off-site accumulations often enough to minimize impacts, revise the SWPPP and add controls to prevent more track-out.

- **When:** pollutants escape the industrial site.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.4.2, page 15**

> "If pollutants escape the industrial site, the permittee shall remove the off-site accumulations of pollutants at a frequency sufficient to minimize impacts."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=15)

#### Coal pile runoff: meet the TSS and pH limits

No set date. Effluent limits apply at all times (3.11).

Coal pile runoff must not exceed 50 mg/L total suspended solids at any time, and its pH must stay between 6.0 and 9.0 standard units at all times.

- **When:** the facility discharges storm water from coal pile runoff.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.11, page 18**

> "The Total Suspended Solids (TSS) shall not exceed 50 mg/L at any time, and the pH shall be maintained between 6.0 standard units and 9.0 standard units at all times."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=18)

#### Enclose or cover salt piles

No set date. Standing requirement (3.10).

Salt storage piles that generate a storm water discharge to waters of the state are enclosed or covered, except while material is added or removed.

- **When:** the facility has salt storage piles that discharge storm water.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.10, page 18**

> "Storage piles of salt that generate a storm water discharge to waters of the state shall be enclosed or covered to prevent exposure to precipitation, except when adding or removing materials from the pile."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=18)

#### Fix control measures within 7 days, or before the next storm if sooner

Within 7 days after you identify the need for maintenance.

Keep storm water control measures in effective working order. When one is not working effectively, maintain it before the next anticipated storm event or within seven days of finding the need, whichever comes first.

- **When:** a control measure is not operating effectively.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.3.1, page 15**

> "before the next anticipated storm event or within seven (7) days of identifying the need for maintenance, whichever comes first."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=15)

#### Fix the SWPPP within 30 days of a DANR notice and certify it

Within 30 days after the Secretary's notice.

If the Secretary notifies you that the SWPPP does not meet the permit's minimum requirements, make the required changes and send the Secretary a written certification that they have been made, within 30 days of the notice.

- **When:** the Secretary notifies you that the SWPPP does not meet the permit's minimum requirements.

- You send it to the agency (DANR Surface Water Quality (Section 5.3 address)).
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 4.3.2, page 19**

> "Within thirty (30) days of notification, the permittee shall make the required changes to the Plan and shall submit to the Secretary a written certification that the requested changes have been made."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=19)

#### Give DANR advance notice of planned changes

No set date. In advance (6.1.1); the permit gives no number of days.

Give the Secretary advance notice of any planned change at the facility, or of any activity that may result in permit noncompliance.

- **When:** a change at the facility, or an activity that may cause noncompliance, is planned.

- You send it to the agency (DANR Surface Water Quality (Section 5.3 address)).
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 6.1.1, page 30**

> "The permittee shall give the Secretary advance notice of any planned changes at the permitted facility or of an activity that may result in permit noncompliance."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=30)

#### Give the MS4 the SWPPP when it asks

No set date. On request (4.6.2); the permit gives no number of days.

A facility discharging into a municipal separate storm sewer system makes the SWPPP available to the municipality on request.

- **When:** the municipality asks for the SWPPP.

- You send a copy to the operator of your storm sewer system (MS4).
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 4.6.2, page 24**

> "Any permittee that discharges storm water into a municipal separate storm sewer system shall make the pollution prevention plan available to the municipality upon request."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=24)

#### Monitor storm water released from a containment structure

No set date. When the water is discharged (5.1.10); no separate date.

When storm water held in a containment structure (a pond, secondary containment and similar) needs to be discharged, monitor it the same way as other storm water under Section 5.1.

- **When:** storm water held in a containment structure needs to be discharged.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 5.1.10, page 28**

> "If storm water from a containment structure (pond, secondary containment, etc.) needs to be discharged, monitoring shall be performed in accordance with section 5.1 of this permit."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=28)

#### Promptly correct missing or wrong information

No set date. Promptly (6.7); no number of days.

When you learn that relevant facts were left out of, or wrong in, the NOI or any other report to the Secretary, promptly submit the facts or correct information.

- **When:** you find missing or incorrect information in the NOI or a report.

- You send it to the agency (DANR Surface Water Quality (Section 5.3 address)).
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 6.7, page 31**

> "When the permittee becomes aware that he or she failed to submit any relevant facts or submitted incorrect information ... he or she shall promptly submit such facts or information."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=31)

#### Record why a sample could not be taken

No set date. The permit sets no date (3.9.4, 5.1.2).

When adverse climatic conditions (flooding, high winds, tornadoes, electrical storms, extended frozen conditions and similar) prevent a sample, include a description of why it could not be taken. This waiver may be used only once in a two-year period.

- **When:** adverse climatic conditions prevent a sample from being taken.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.9.4, page 18**

> "When a facility is unable to collect a sample due to adverse climatic conditions (e.g., local flooding, high winds, tornadoes, electrical storms, extended frozen conditions, etc.), the facility must include a description of why samples could not be taken."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=18)

#### Report a release of a regulated substance within 24 hours

Within 24 hours after the release happens.

If a regulated substance (such as fertilizer, pesticide, oil or gasoline) is released, notify the DANR Ground Water Quality Program at (605) 773-3296, or Emergency Management at (605) 773-3231 outside business hours, as soon as reasonably practicable and no later than 24 hours after the release. Releases causing an oil sheen are reported immediately to the National Response Center at 1-800-424-8802.

- **When:** a regulated substance such as fertilizer, pesticide, oil or gasoline is released.

- You send it to the agency (DANR Ground Water Quality Program by phone, (605) 773-3296; Emergency Management (605) 773-3231 outside business hours).
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 2.10, page 14**

> "All notifications must be made as soon as reasonably practicable, but in no case greater than 24 hours after the release."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=14)

#### Send a new authorization letter when the signing representative changes

No set date. Before or with the next report the representative signs (6.8.2.b).

A duly authorized representative is named in writing by the responsible official and sent to the Secretary. If that authorization is no longer accurate, send a new letter before, or together with, any report it will sign.

- **When:** the authorization of the duly authorized representative is no longer accurate.

- You send it to the agency (DANR Surface Water Quality (Section 5.3 address)).
- Keep the records 3 years.
- Signed or certified by a responsible official per sdr000000 6.8.1.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 6.8.2.b, page 32**

> "a new letter of authorization satisfying the requirements of this section must be submitted to the Secretary prior to, or together with, any reports, information, or applications to be signed by an authorized representative."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=32)

#### Send a signed copy of the NOI to the MS4 operator

No set date. With the NOI (2.7); the permit gives no separate date.

A facility that discharges storm water to a permitted municipal separate storm sewer system (MS4) sends signed copies of the NOI form to the municipal operator.

- **When:** the facility discharges storm water to a permitted municipal separate storm sewer system (MS4).

- You send a copy to the operator of your storm sewer system (MS4).
- Keep the records 3 years.
- Signed or certified by a responsible official per sdr000000 6.8.1.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 2.7, page 12**

> "Facilities that discharge storm water to a permitted municipal separate storm sewer system (MS4) shall submit signed copies of the NOI form to the municipal operator."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=12)

#### Send DANR requested information and records

No set date. Within a reasonable time (6.6.1); no number of days.

Give the Secretary, within a reasonable time, any information requested to decide on the permit or to judge compliance, and copies of records the permit requires.

- **When:** DANR asks for information or records.

- You send it to the agency (DANR Surface Water Quality (Section 5.3 address)).
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 6.6.1, page 31**

> "The permittee shall furnish to the Secretary, within a reasonable time, any information which the Secretary may request"

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=31)

#### Submit a Notice of Termination to end coverage

No set date. The permit sets no date (2.9.1).

To end coverage once all industrial storm water discharges are eliminated, submit a Notice of Termination (Attachment B), signed and certified. The permit applies until DANR approves the NOT.

- **When:** you want to end permit coverage.

- You file it in the agency's system (EPA NeT (NETMSGP) through a CDX account, or the paper form mailed to DANR Surface Water Quality).
- Keep the records 3 years.
- Signed or certified by a responsible official per sdr000000 6.8.1.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 2.9.1, page 13**

> "Permittees wishing to terminate coverage under this general permit must submit a Notice of Termination that is signed in accordance with Section 6.8.3 of this general permit."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=13)

#### Submit monitoring results within one month of the end of the sampling year

Within 28 days after a monitoring sample is taken.

Send DANR the effluent monitoring results for a year within one month after that year ends, on the Attachment G Discharge Monitoring Summary Form with the facility's industrial category, signed and certified under Section 6.8.3.

- You file it in the agency's system (EPA NeT (NETMSGP) through a CDX account, or the paper form mailed to DANR Surface Water Quality).
- Keep the records 3 years.
- Signed or certified by a responsible official or duly authorized representative.

Inferred from section 5.3. Check your copy of the permit.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 5.3, page 29**

> "Effluent monitoring results obtained during the permit period shall be submitted to SDDENR within one month of the end of the year the samples were taken."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=29)

#### Submit the NOI at least 15 days before industrial activity starts

At least 15 days before industrial activity starts.

Submit a Notice of Intent (Attachment A), signed under Section 6.8, with the Certification of Applicant, at least 15 days before starting any industrial activity at the site. Coverage begins when DANR sends its letter of authorization.

- **When:** a new facility is seeking coverage.

- You file it in the agency's system (EPA NeT (NETMSGP) through a CDX account, or the paper form mailed to DANR Surface Water Quality).
- Keep the records 3 years.
- Signed or certified by a responsible official per sdr000000 6.8.1.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 2.6.1, page 12**

> "This information must be submitted at least 15 days prior to commencing any industrial activity at the site."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=12)

#### Submit the Transfer of Ownership form 30 working days before the change

At least 30 working days before the change of owner or operator.

When the owner or operator changes, the new owner or operator submits the Transfer of Ownership form (Attachment F) at least 30 working days before the change, with the written agreement between the old and new permittees that sets the transfer date.

- **When:** the owner or operator of the facility is changing.

- You send it to the agency (DANR Surface Water Quality, PMB 2020, Joe Foss Building, 523 East Capitol, Pierre SD 57501-3182 (Attachment F)).
- Keep the records 3 years.
- Signed or certified by a responsible official per sdr000000 6.8.1.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 2.8, page 13**

> "the new owner or operator of the facility must submit a Transfer of Ownership form (Attachment F) to the Secretary at least 30 working days prior to the change."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=13)

#### Take an Oil and Grease grab sample at once if a sheen is seen

When an oil sheen or floating oil is seen in the discharge.

If an oil sheen or floating oil is seen during a discharge, take a grab sample for Oil and Grease immediately, have it analyzed and report the result.

- **When:** an oil sheen or floating oil is seen in the discharge.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.9.3, page 17**

> "If an oil sheen is visible, a grab sample for Oil and Grease shall be taken immediately, analyzed, and reported."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=17)

#### Tell DANR within 5 business days after resuming activity

Within 5 working days after the facility resumes activity.

After a temporary shutdown, notify DANR in writing or by phone of the shutdown and its dates within 5 business days of resuming activity. Monitoring and inspections apply again at once.

- **When:** DANR has approved a temporary shutdown.

- You send it to the agency (DANR Surface Water Quality Program, in writing or by phone at (605) 773-3351).
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 2.4.2, page 11**

> "The facility shall notify the SDDENR either in writing or by phone at (605) 773-3351 of the temporary shutdown, including dates, within 5 business days of resuming activity."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=11)

#### Update the SWPPP after a release

No set date. The permit sets no date (2.10).

After a release of a regulated substance, modify the SWPPP and put the changes in place: how to prevent it happening again, the proper response, and steps to keep pollutants out of storm water runoff.

- **When:** a regulated substance such as fertilizer, pesticide, oil or gasoline is released.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 2.10, page 13**

> "If a release occurs, the storm water pollution prevention plan shall be modified and changes implemented, as appropriate."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=13)

#### Update the SWPPP when the site changes or the plan does not work

No set date. The permit sets no date (4.3.1).

Modify the SWPPP whenever a change in design, construction, operation or maintenance changes the potential for discharging pollutants, or when the plan proves ineffective.

- **When:** a change in design, construction, operation or maintenance changes the potential for discharging pollutants, or the SWPPP proves ineffective.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 4.3.1, page 19**

> "The permittee shall modify the Plan whenever there is a change in design, construction, operation, or maintenance that changes the potential for the discharge of pollutants to waters of the state."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=19)

### Ongoing  5 duties

#### Keep records for at least three years

No set date. Standing duty (5.2.2).

Keep the SWPPP, a copy of the permit, the coverage letter, inspection records, all monitoring information (with calibration and maintenance records), copies of all reports and the application data for at least three years. Each monitoring record shows the date, place and time, who sampled and analyzed, methods, results, the storm's date and length, rainfall, days since the last measurable rain and the estimated volume discharged.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 5.2.2, page 28**

> "for a period of at least three (3) years from the date of the sample, measurement, report, or application."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=28)

#### Keep the SWPPP at the site

No set date. Standing duty (4.1.2).

Keep the SWPPP at the permitted site. It is sent to DANR only if the Secretary asks for it.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 4.1.2, page 19**

> "The Plan is not submitted to the SDDENR unless requested by the Secretary, but it must be retained at the permitted site."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=19)

#### Record inspection results and corrective actions in the SWPPP

No set date. With each inspection (3.9.5); no separate date.

Document each inspection's results, and the corrective actions taken for any deficiency or improvement it found, in the SWPPP.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.9.5, page 18**

> "Inspection results and corrective actions taken in response to any deficiencies or opportunities for improvement identified during the inspection must be documented in the Plan."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=18)

#### Remove sediment when a control has lost half its capacity

No set date. Whenever sediment has reduced a control's design capacity by 50% (3.3.2).

Remove sediment from controls, at the latest when their design capacity has been reduced by 50 percent.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 3.3.2, page 15**

> "At a minimum, the permittee shall remove sediment from controls when design capacity has been reduced by 50%."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=15)

#### Train personnel on the dates the SWPPP sets

No set date. On the periodic dates the SWPPP identifies (4.5.5); the permit sets no frequency.

Train all personnel on their role in carrying out the SWPPP (spill response, good housekeeping, material management, truck wash out and equipment washdown), on the periodic training dates the plan identifies. Inform contractors and temporary staff too.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 4.5.5, page 23**

> "All personnel shall be trained on their role in implementing activities identified in the plan."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=23)

### Only if...  6 duties

These apply only in the situation named on each one. Answer the questions to sort them.

#### Air transportation with vehicle maintenance: sample in the first year

Within 1 year after your coverage began.

Within the first year of coverage, sample storm water once and analyze it for: presence or absence of an oil sheen (visual), Oil and Grease in mg/L (grab, if oil is observed, Standard Methods 1664A), 5-day biochemical oxygen demand in mg/L (grab), and presence or absence of visible pollutants (visual).

- **Only if:** your SIC code starts with 45, or your NAICS code starts with 481, 487990, 488190, 488119, 492110, 561720, 621910; the air transportation facility is involved in vehicle maintenance (mechanical repairs, painting, fueling, lubrication).

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by an accredited laboratory.

Inferred from section 5.1.7.a. Check your copy of the permit.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 5.1.7.a, page 26**

> "Air Transportation Facilities (SIC beginning 45; NAICS beginning 481, and NAICS 487990, 488190, 488119, 492110, 561720, 621910) that are involved in vehicle maintenance"

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=26)

#### Ethanol and similar organic chemical manufacturing: sample in the first year

Within 1 year after your coverage began.

Within the first year of coverage, sample storm water once and analyze it for: pH (daily maximum and minimum, instantaneous, measured within 15 minutes with a calibrated meter), presence or absence of an oil sheen (visual), Oil and Grease in mg/L (grab, Standard Methods 1664A), 5-day biochemical oxygen demand in mg/L (grab), total suspended solids in mg/L (grab) and presence or absence of visible pollutants (visual).

- **Only if:** your SIC code starts with 2869.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by an accredited laboratory.

Inferred from section 5.1.7.f. Check your copy of the permit.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 5.1.7.f, page 27**

> "Ethanol Manufacturing and similar Industrial Organic Chemical Manufacturing, (SIC 2869):"

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=27)

#### Food manufacturing: sample in the first year

Within 1 year after your coverage began.

Within the first year of coverage, sample storm water once and analyze it for: presence or absence of an oil sheen (visual), Oil and Grease in mg/L (grab, if oil is observed, Standard Methods 1664A), 5-day biochemical oxygen demand in mg/L (grab) and total suspended solids in mg/L (grab).

- **Only if:** your SIC code starts with 20, or your NAICS code starts with 311.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by an accredited laboratory.

Inferred from section 5.1.7.b. Check your copy of the permit.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 5.1.7.b, page 26**

> "Food Manufacturing (SIC beginning 20; NAICS beginning 311):"

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=26)

#### Landfills: sample in the first year

Within 1 year after your coverage began.

Within the first year of coverage, sample storm water once and analyze it for: pH (daily maximum and minimum, instantaneous, measured within 15 minutes of collection with a meter calibrated at two points and reading to 0.01 standard units), 5-day biochemical oxygen demand in mg/L (grab) and total suspended solids in mg/L (grab).

- **Only if:** your SIC code starts with 4953, or your NAICS code starts with 562211, 562212, 562213, 562219, 562920.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by an accredited laboratory.

Inferred from section 5.1.7.e. Check your copy of the permit.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 5.1.7.e, page 27**

> "Landfills (SIC 4953; NAICS 562211, 562212, 562213, 562219, and 562920):"

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=27)

#### Lumber and wood products: sample in the first year

Within 1 year after your coverage began.

Within the first year of coverage, sample storm water once and analyze it for: 5-day biochemical oxygen demand in mg/L (grab), total suspended solids in mg/L (grab) and presence or absence of visible pollutants (visual).

- **Only if:** your SIC code starts with 24, or your NAICS code starts with 113310, 321.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by an accredited laboratory.

Inferred from section 5.1.7.c. Check your copy of the permit.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 5.1.7.c, page 26**

> "Lumber and wood products except furniture (SIC beginning 24; NAICS 113310 or beginning 321):"

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=26)

#### Scrap yards and metal salvage: sample in the first year

Within 1 year after your coverage began.

Within the first year of coverage, sample storm water once and analyze it for: presence or absence of an oil sheen (visual), Oil and Grease in mg/L (grab, Standard Methods 1664A) and total suspended solids in mg/L (grab).

- **Only if:** your SIC code starts with 5015, 5093, or your NAICS code starts with 421140, 441310, 421930.

- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
- The permit says this is done by an accredited laboratory.

Inferred from section 5.1.7.d. Check your copy of the permit.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 5.1.7.d, page 27**

> "Scrap Yards and Metal Salvage (SIC 5015 and 5093; NAICS 421140, 441310, or 421930):"

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=27)

## What does no-exposure certification require?

Exemption for no exposure: a No Exposure Certification (Attachment D) approved in writing by the Secretary, resubmitted at least every five years.

- Every few years 1
- One time 1
- When something happens 1

### Every few years  1 duty

#### Resubmit the No Exposure Certification every five years

Within 5 years after the last certification.

Submit a new No Exposure Certification to DANR at least once every five years, and to the MS4 operator if it asks.

- You file it in the agency's system (EPA NeT (NETMSGP) through a CDX account, or the paper form mailed to DANR Surface Water Quality).
- Keep the records 3 years.
- Signed or certified by executive officer or owner notarized.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section Attachment D, part D, page 53**

> "I understand that I am obligated to submit a no exposure certification form once every five years to SDDENR"

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=53)

### One time  1 duty

#### Submit the No Exposure Certification and get DANR approval

No set date. The permit sets no date (2.3.1).

A facility whose industrial materials and activities are all protected from rain, snow, snowmelt and runoff may submit the No Exposure Certification form (Attachment D). The exemption applies only once the Secretary approves it in writing; for a covered facility, approval ends permit coverage without a Notice of Termination.

- You file it in the agency's system (EPA NeT (NETMSGP) through a CDX account, or the paper form mailed to DANR Surface Water Quality).
- Keep the records 3 years.
- Signed or certified by executive officer or owner notarized.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section 2.3.1, page 11**

> "To qualify, the facility must submit a "No Exposure Certification form" provided by SDDENR (Attachment D) and must be approved by the Secretary for exemption from the permitting requirements."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=11)

### When something happens  1 duty

#### Get permit coverage before any exposed discharge

No set date. Before any point source discharge of storm water (Attachment D, part D).

If materials or activities become exposed to storm water, the no exposure exemption no longer applies: obtain coverage under the permit before any point source discharge of storm water from the facility.

- **When:** industrial materials or activities become exposed to storm water.

- You file it in the agency's system (EPA NeT (NETMSGP) through a CDX account, or the paper form mailed to DANR Surface Water Quality).
- Keep the records 3 years.
- Signed or certified by a responsible official per sdr000000 6.8.1.

**Source: General Permit for Storm Water Discharges Associated with Industrial Activities (SDR000000), Sections 1.0 to 6.15 (34 printed pages) and Attachments A to G, 66 PDF pages, section Attachment D, part D, page 53**

> "I understand that I must obtain coverage under a storm water SWD permit prior to any point source discharge of storm water from the facility."

[Open the permit at this section](https://danr.sd.gov/OfficeOfWater/SurfaceWaterQuality/docs/DANR_SW_Ind_GPermit.pdf#page=53)

## Get your own dates

Choose your coverage and answer a few questions. You get each duty's next date and a calendar file.

## South Dakota Industrial Storm Water General Permit SDR000000 duties, topic by topic

How the South Dakota Industrial Storm Water General Permit SDR000000 compares with the other checked permits on each kind of duty, in the permit's own words with the section for each:

- [Inspection requirements](https://stormdue.com/guides/stormwater-inspection-requirements#permit-us-sd-sdr000000)
- [Sampling and qualifying storms](https://stormdue.com/guides/stormwater-sampling-requirements#permit-us-sd-sdr000000)
- [Report due dates](https://stormdue.com/guides/stormwater-annual-report-due-dates#permit-us-sd-sdr000000)
- [No-exposure certification](https://stormdue.com/guides/no-exposure-certification#permit-us-sd-sdr000000)
- [SWPPP, training and records](https://stormdue.com/guides/swppp-requirements#permit-us-sd-sdr000000)

- [Every state's permit](https://stormdue.com/states)
- [How we check permit rules](https://stormdue.com/about-the-rules)
- [Deadline calculator](https://stormdue.com/tools/deadline-calculator)
- [Benchmark comparison](https://stormdue.com/tools/benchmark-comparison)
- [More free tools](https://stormdue.com/tools)
- [Duties compared across permits](https://stormdue.com/guides)

---

StormDue reminds and keeps records. It does not file anything with the agency and does not certify or guarantee compliance. Check each duty against your permit; you are responsible for your filings.

StormDue does not guarantee that these facts are accurate or current. Verify them with your agency before you rely on them.