# Washington ISGP Due Dates and Duties

> Every recurring duty in the ISGP with its due date rule and permit section, checked November 25, 2026. Get your own dates free.

Canonical page: https://stormdue.com/permits/us-wa-isgp

[States](https://stormdue.com/states) / [Washington](https://stormdue.com/states/wa)

# ISGP due dates and duties

The Industrial Stormwater General Permit (NPDES and State Waste Discharge General Permit) (No general permit number is printed in the permit or on Ecology's permit page (checked 2026-11-25); facility coverage numbers use WAR prefixes) sets 33 duties below, each with when it is due and the permit section it comes from. Rules last checked November 25, 2026.

[Get my permit calendar](https://stormdue.com/lookup?state=WA)

Free, no account. Each date comes with the permit section and the permit's own words.

Next: choose your coverage and answer a few questions. You get your next due dates and a calendar file.

StormDue reminds and keeps records. It does not file anything with the agency and does not certify or guarantee compliance. Check each duty against your permit; you are responsible for your filings.

## What is this permit, and where do I file?

- **Permit number**
  No general permit number is printed in the permit or on Ecology's permit page (checked 2026-11-25); facility coverage numbers use WAR prefixes
- **Agency**
  [Washington State Department of Ecology, Water Quality Program](https://ecology.wa.gov/regulations-permits/permits-certifications/stormwater-general-permits/industrial-stormwater-permit)
- **Effective**
  January 1, 2025
- **Expires**
  December 31, 2028
- **Where you file**
  [Water Quality Permitting Portal (WQWebPortal), via Secure Access Washington (SAW)](https://secureaccess.wa.gov/ecy/wqwebportal/)
- **Official page**
  [ecology.wa.gov](https://ecology.wa.gov/regulations-permits/permits-certifications/stormwater-general-permits/industrial-stormwater-permit)
- **Rules last checked**
  November 25, 2026 (version 2026-11-26.1 )

**Notes on the permit's status and renewal**

The 2026 modification (issued October 21, 2026, effective November 20, 2026; Washington State Register WSR 26-20-080) moved the expiration date from December 31, 2029 to December 31, 2028 and the duty-to-reapply date from July 3, 2029 to July 3, 2028, and (per the response to comments) moved the Puget Sound sediment cleanup site waiver request deadline from May 15, 2029 to May 15, 2028. Permittees covered under the 2025 ISGP are automatically covered under the modified permit. The February 2025 errata (Level 2 deadline August 31, gross revenue form March 15, Table 3 PFAS rows, S8.D three-quarter wording) are incorporated in the modified permit text. The 2025 ISGP was affirmed by the Pollution Control Hearings Board on June 12, 2026; an appeal to King County Superior Court was filed July 13, 2026 and Ecology's page says the permit "remains in full effect". Ecology has started reissuance for a permit effective January 1, 2029 (draft planned early 2028, final decision November 2028). All checked 2026-11-25.

## What does full permit coverage require?

- Every month 1
- Every quarter 3
- Every year 5
- One time 1
- When something happens 17
- Ongoing 2
- Only if... 3

### Every month  1 duty

#### Monthly site inspection, at least a week apart, signed by two people

Each month, qualified personnel inspect sampling locations and discharge points, look for sheen, discoloration, turbidity, odor and illicit discharges, verify the pollutant source list and site map, and assess BMPs. The report states compliance or noncompliance and is signed by the inspector and by the G2 signatory (or duly authorized representative).

By the end of each month; at least 7 days apart.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.
- The permit says this is done by qualified personnel, as the permit defines them.
- Signed or certified by the inspector and the permit signatory (G2).

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S7.A-C , page 51](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=60)

> "The Permittee shall conduct and document visual inspections of the site each month with at least one week between inspections."

### Every quarter  3 duties

#### Sample each designated discharge point every quarter

Sample each designated sampling location at least once per quarter for Table 2 parameters (turbidity, pH, oil sheen, copper, zinc) and any Table 3 sector parameters. Collect within the first 12 hours of a discharge event; if that is not possible, sample as soon as practicable afterwards and record why. Sampling is not required outside regular business hours, in unsafe conditions or in quarters with no discharge, but a DMR is still due. Record sample details and keep lab reports from an accredited lab (pH and turbidity exempt).

By the end of each calendar quarter.

- You file it in the agency's system (WQWebPortal DMR).
- Keep the records 5 years.
- The permit says this is done by an accredited laboratory.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S4.B.1.a , page 27](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=36)

> "The Permittee shall sample the discharge from each designated location at least once per quarter:"

#### Vacuum-sweep paved surfaces at least once a quarter

Vacuum paved surfaces with a vacuum sweeper (or a sweeper with a vacuum attachment) at least once each quarter to remove accumulated pollutants, on the schedule in the SWPPP.

By the end of each calendar quarter.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S3.B.4.b.i.2).a) , page 19](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=28)

> "Vacuum paved surfaces with a vacuum sweeper (or a sweeper with a vacuum attachment) to remove accumulated pollutants a minimum of once per quarter."

#### Submit the quarterly DMR (even with no discharge)

Submit a Discharge Monitoring Report for each quarter by May 15 (Q1), August 15 (Q2), November 15 (Q3) and February 15 (Q4), starting with the first full quarter of coverage; report "no discharge" or "no sample obtained" with an explanation when applicable.

By May 15 (Q1), August 15 (Q2), November 15 (Q3) and February 15 (Q4).

- You file it in the agency's system (WQWebPortal DMR application).
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S9.B.2 Table 10; S9.B.4 , page 58](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=67)

> "Upon permit coverage, the Permittee shall ensure that DMRs are submitted to Ecology by the DMR due dates below:"

### Every year  5 duties

#### Inspect dumpsters for holes or defects once a year

As part of the inspections, check dumpsters annually for holes or defects that could leak.

By December 31 each year.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.
- The permit says this is done by qualified personnel, as the permit defines them.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S7.B.3 , page 51](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=60)

> "Permittees shall inspect dumpsters annually for holes or defects to identify and control leakage."

#### Train all employees every year; new hires within 90 or 30 days

Train all employees on the SWPPP at least annually. All employees, contractors and vendors with duties in areas of industrial activity: within 90 days of hire. Part-time and seasonal employees, contractors and vendors: within 30 days of hire. Keep a log of training dates with the SWPPP. Contractors and vendors may be excluded if a trained employee supervises their activity at all times.

By December 31 each year.

- If new hire in industrial area: Within 90 days after hire date.
- If new part time seasonal or contractor: Within 30 days after hire date.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S3.B.4.b.i.5).c) , page 23](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=32)

> "The Permittee shall train all employees annually, at a minimum."

#### Submit the Annual Gross Revenue Form by March 15

Submit the ISGP Annual Gross Revenue Form electronically through WQWebPortal (used for fee assessment).

By March 15 each year.

- You file it in the agency's system (WQWebPortal).
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S11.C , page 64](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=73)

> "The Permittee shall submit an ISGP Annual Gross Revenue Form to Ecology on or before March 15th"

#### Submit the Annual Report by May 15

Submit the Annual Report through WQWebPortal with corrective action documentation (triggers, problems, dates, Level 1-3 actions completed, status of open Level 2/3 actions). Not required if there was no coverage in the previous calendar year. Keep a copy on site.

By May 15, for the calendar year before.

- You file it in the agency's system (WQWebPortal Permit Submittals).
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S9.C.1 , page 59](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=68)

> "The Permittee shall submit a complete and accurate Annual Report to the Department of Ecology no later than May 15th of each year"

#### Pay permit fees assessed by Ecology

Pay permit fees set by Chapter 173-224 WAC until coverage is terminated or revoked.

No set date. Billed by Ecology; due date not in the permit.

- You send it to the agency (Ecology invoice).

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S11.A-B , page 64](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=73)

> "The Permittee shall pay permit fees assessed by Ecology and established in Chapter 173-224 WAC."

### One time  1 duty

#### Reapply for coverage by July 3, 2028

Permittees who want to keep operating after the December 31, 2028 expiration must reapply at least 180 days before expiration; Ecology states the date as July 3, 2028.

By July 3, 2028.

- You file it in the agency's system (WQWebPortal).
- Keep the records 5 years.
- Signed or certified by a responsible official per isgp G2A.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section G8 , page 69](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=78)

> "the permittee must reapply for the permit at least 180 days prior to the expiration date of this permit."

### When something happens  17 duties

#### Inspect and maintain baghouses every month

Inspect and maintain baghouses monthly to prevent dust escaping, and immediately remove accumulated dust at the base of exterior baghouses.

By the end of each month.

- **When:** baghouses on site.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S3.B.4.b.i.2).c) , page 19](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=28)

> "Inspect and maintain bag houses monthly to prevent the escape of dust from the system."

#### Clean storm drain lines and sample storm drain solids once this permit term (Puget Sound sediment cleanup sites)

Facilities discharging to a Puget Sound Sediment Cleanup Site remove accumulated solids from storm drain lines on or beneath the facility, and sample and analyze storm drain solids under Table 8, at least once in the permit term (which now ends December 31, 2028). Waiver requests are due May 15, 2028; solids results go on a Solids Monitoring Report by that quarter's DMR due date.

By December 31, 2028.

Further steps with their own deadlines:

- **Sample and analyze storm drain solids (Table 8).** The permit gives the timing in words, quoted below. [Section S6.C.2.e , page 47](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=56)
  > "Permittees shall sample and analyze storm drain solids in accordance with Table 8 at least once in the term of the permit."
- **Line cleaning waiver request (Modification of Coverage).** By May 15, 2028. [Section S6.C.2.d.ii , page 47](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=56)
  > "The due date for line cleaning waiver requests is May 15, 2028."
- **Report solids data on a Solids Monitoring Report.** The permit gives the timing in words, quoted below. [Section S6.C.2.f , page 48](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=57)
  > "All storm drain solids sampling data shall be reported to Ecology on a Solids Monitoring Report (SMR) no later than the DMR due date for the reporting period in which the solids were sampled"

- **When:** discharges to puget sound sediment cleanup site.

- You file it in the agency's system (WQWebPortal (Solids Monitoring Report with the DMR)).
- Keep the records 5 years.
- The permit says this is done by an accredited laboratory.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S6.C.2.d-f , page 47](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=56)

> "Permittees shall remove accumulated solids from storm drain lines (including inlets, catch basins, sumps, conveyances lines, and oil/water separators) on or beneath your facility at least once in the term of the permit."

#### Apply for coverage at least 60 days before discharging

New facilities submit a complete application (NOI) in WQWebPortal at least 60 days before stormwater discharge begins, certifying public notice and SEPA compliance.

At least 60 days before start of stormwater discharge.

- **When:** new facility.

- You file it in the agency's system (WQWebPortal).
- Keep the records 5 years.
- Signed or certified by a responsible official per isgp G2A.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S2.A.1.b , page 11](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=20)

> "Submit a complete and accurate permit application to Ecology at least 60 days before the commencement of stormwater discharge from the facility."

#### Apply to modify coverage 60 days before a significant process change

Submit a Modification of Coverage form (with public notice and, for process changes, SEPA) at least 60 days before a significant process change; to request a Level 2 or 3 extension or waiver, submit it before that corrective action deadline.

At least 60 days before planned change date.

- **When:** planned significant process change.

- You file it in the agency's system (WQWebPortal).
- Keep the records 5 years.
- Signed or certified by a responsible official per isgp G2A.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S2.B.1 , page 12](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=21)

> "Apply for modification of coverage at least 60 days before implementing a significant process change;"

#### File a Notice of Termination when coverage is no longer needed

When industrial discharges cease with nothing exposed, the responsible party sells or transfers the activity, or all discharges go to sanitary sewer or ground, submit a signed Notice of Termination through WQWebPortal; fees continue until Ecology terminates coverage.

No set date. No deadline stated in S13; permit fees continue until coverage is terminated (S11.B).

- **When:** termination condition met.

- You file it in the agency's system (WQWebPortal).
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S13.B , page 65](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=74)

> "The Permittee shall submit the completed NOT form to Ecology through the WQWebPortal."

#### File a Transfer of Coverage form with the new owner

The current permittee and the new discharger submit a signed Transfer of Coverage form with a specific transfer date; coverage transfers on that date unless Ecology objects.

Before transfer date.

- **When:** change of operator.

- You file it in the agency's system (Transfer of Coverage Form (Ecology)).
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S2.D , page 13](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=22)

> "Coverage under this general permit shall automatically transfer to a new discharger, if all of the following conditions are met:"

#### Give 45 days' notice of planned changes that may cause noncompliance

Submit a new or supplemental application to Ecology at least 45 days before facility expansions, production increases or other planned changes that may result in noncompliance with permit limits or conditions.

At least 45 days before planned change date.

- **When:** planned change may cause noncompliance.

- You file it in the agency's system (Ecology (new or supplemental application)).
- Keep the records 5 years.
- Signed or certified by a responsible official per isgp G2A.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section G21 , page 72](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=81)

> "The Permittee shall give advance notice to Ecology by submission of a new application, or supplement to the existing application, at least 45 days prior to commencement of such discharges,"

#### Give the public access to the SWPPP within 14 days of a written request

Provide a copy (or a viewing appointment, notified within 10 days) within 14 days of a written public request, unless the current SWPPP is posted at a URL given in the NOI.

Within 14 days after receipt of written request.

- **When:** public swppp request.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S9.G , page 62](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=71)

> "Provide a copy of the SWPPP to the requestor within 14 days of receipt of the written request, or"

#### Level 1 corrective action after any benchmark exceedance

Within 14 days of results showing a quarterly exceedance (or the end of the quarter, if later, for parameters other than pH and oil sheen): inspect to find the cause, review the SWPPP, add operational source control BMPs. Sign and fully implement the revised SWPPP by the DMR due date for that quarter. Summarize in the Annual Report.

Within 14 days after later of results receipt or quarter end.

- **When:** benchmark exceedance in quarter.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S8.B , page 53](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=62)

> "Within 14 days of receipt of sampling results that indicate a benchmark exceedance during a given quarter"

#### Level 2 structural source control after two exceeding quarters in a calendar year

If a parameter exceeds its benchmark in any two quarters of a calendar year (facility-wide), review the SWPPP, add structural source control BMPs for the exceeding areas, and sign and fully implement by August 31 of the following year (or skip to Level 3). Extensions or waivers require a Modification of Coverage request before the deadline.

By August 31, for the calendar year before (after level 2 triggered).

- **When:** two quarters exceeded same parameter in calendar year.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S8.C , page 54](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=63)

> "fully implement the revised SWPPP according to Permit Condition S3 and the applicable Stormwater Management Manual as soon as possible, but no later than August 31st of the following year."

#### Level 3 treatment after three exceeding quarters in a calendar year

If a parameter exceeds its benchmark in any three quarters of a calendar year, add treatment BMPs; a qualified industrial stormwater professional reviews and certifies the revised SWPPP; if treatment needs site-specific design, submit a PE-certified engineering report by June 30 of the following year and an O&M manual within 30 days after installation; implement by September 30 of the following year.

By September 30, for the calendar year before (after level 3 triggered).

Further steps with their own deadlines:

- **Engineering report (certified by a licensed professional engineer).** By June 30, for the calendar year before (after level 3 triggered). [Section S8.D.3.b , page 56](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=65)
  > "The engineering report shall be submitted no later than 6 months after the last day of the calendar year in which the Level 3 was triggered, i.e., due June 30th"
- **Operation and Maintenance Manual.** Within 30 days after installation complete. [Section S8.D.3.c , page 56](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=65)
  > "An Operation and Maintenance Manual (O&M Manual) shall be submitted to Ecology no later than 30 days after construction/installation is complete"
- **Implementation deadline.** The permit gives the timing in words, quoted below. [Section S8.D.5 , page 56](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=65)
  > "as soon as possible, but no later than September 30th of the following year provided."

- **When:** three quarters exceeded same parameter in calendar year.

- You file it in the agency's system (Engineering report and O&M manual to Ecology; SWPPP kept on site).
- Keep the records 5 years.
- The permit says this is done by a qualified industrial stormwater professional.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S8.D , page 55](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=64)

> "A qualified industrial stormwater professional shall review the revised SWPPP, sign the SWPPP Certification Form, and certify that it is reasonably expected to meet the ISGP benchmarks upon implementation."

#### Newly covered facilities certify the SWPPP by the end of the first full quarter

A facility that was not permitted before must develop and certify its SWPPP by the end of the first full monitoring period (quarter) after coverage starts, and implement the SWPPP and sampling by the first day of the second full monitoring period.

No set date. End of the first full quarter after coverage begins; depends on the facility's coverage date (S3.A.3.c).

- **When:** new permit coverage.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S3.A.3.c , page 15](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=24)

> "Unpermitted facilities shall develop and certify their SWPPP no later than the end of the first full monitoring period following the effective date of permit coverage,"

#### Notify Ecology of new or changed sampling locations and discharge points

Submit the Discharge/Sample Point Update Form to Ecology whenever sample locations, discharge points or outfalls change; Ecology may ask for more information before the change.

No set date. No deadline stated in S4.B.2.e; Ecology may require information before the change.

- **When:** sample point or outfall changed.

- You file it in the agency's system (Discharge/Sample Point Update Form (Ecology)).
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S4.B.2.e , page 28](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=37)

> "The Permittee shall notify Ecology of any changes or updates to sample locations, discharge points, and/or outfalls by submitting an "Industrial Stormwater General Permit Discharge/Sample Point Update Form" to Ecology."

#### Phone the regional office within 24 hours; written report within 5 days

Report noncompliance that may endanger health or the environment, or a violation of a maximum daily limit, to the Ecology regional office by phone within 24 hours, and submit a detailed written report through WQWebPortal within 5 days.

Within 1 day after awareness of noncompliance.

- **When:** noncompliance endangering or daily limit exceeded.

- You file it in the agency's system (Regional office phone; WQWebPortal Permit Submittals).
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S9.F , page 61](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=70)

> "Submit a detailed written report to Ecology within 5 days of the time the Permittee becomes aware of the circumstances, unless Ecology requests an earlier submission."

#### Report an illicit discharge within 7 days; eliminate it within 30 days

If an inspection finds an illicit discharge or connection, notify Ecology within 7 days, eliminate the discharge within 30 days and the connection within 6 months (unless an Ecology order sets another date).

Within 7 days after discovery date.

Further steps with their own deadlines:

- **Eliminate the illicit discharge.** Within 30 days after discovery date. [Section S7.B.4.b , page 51](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=60)
  > "The Permittee shall eliminate the illicit discharge within 30 days"
- **Eliminate the illicit connection.** The permit gives the timing in words, quoted below. [Section S7.B.4.b , page 51](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=60)
  > "The illicit connection shall be eliminated within 6 months unless an alternative deadline is specified in an Ecology order."

- **When:** illicit discharge found.

- You file it in the agency's system (Ecology (method not stated)).
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S7.B.4 , page 51](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=60)

> "If an illicit discharge or illicit connection is discovered, the Permittee shall notify Ecology within seven days."

#### Sample the first fall storm on or after September 1

Sample the stormwater discharge from the first storm event on or after September 1 each year that produces a discharge, within the first 12 hours where possible.

Within 12 hours of first discharge on or after sep 1.

- **When:** first fall storm discharge.

- You file it in the agency's system (WQWebPortal DMR (third or fourth quarter)).
- Keep the records 5 years.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S4.B.1.b , page 27](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=36)

> "Permittees shall sample the stormwater discharge from the first fall storm event each year."

#### Send a new duly authorized representative authorization before the next signed report

If the written authorization of a duly authorized representative is no longer accurate (a different person or position now runs the facility), send Ecology a new authorization before or with the next report, information or application that person signs.

No set date. Before or together with the next document signed by the representative (G2.C).

- **When:** duly authorized representative changed.

- You file it in the agency's system (Ecology (written authorization)).
- Keep the records 5 years.
- Signed or certified by a responsible official per isgp G2A.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section G2.C , page 66](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=75)

> "a new authorization satisfying the requirements of paragraph G2.B.2 above shall be submitted to Ecology prior to, or together with, any reports, information, or applications to be signed by an authorized representative."

### Ongoing  2 duties

#### Keep records five years and produce them within 14 days of a written request

Keep the permit, coverage letter, sampling records, inspection reports, calibration and BMP maintenance records, lab reports, all reports and application data on site for five years (longer during litigation or on request); make them available immediately or within 14 days of Ecology's written request.

Ongoing, no set date.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S9.D , page 60](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=69)

> "The Permittee shall retain the following documents as hardcopies or electronically, onsite for a minimum of five years:"

#### Keep the SWPPP current and re-sign it after each required revision

Modify the SWPPP when it proves ineffective, within 30 days of Ecology's written notice of deficiencies, and when design or operations change pollutant discharges significantly; sign and certify it (Appendix 3 form) each time it is revised for an update, inspection or corrective action.

No set date. Event-driven; 30 days after an Ecology deficiency notice (S3.A.3.a.ii).

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S3.A.3; S3.A.5 , page 15](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=24)

> "The Permittee shall sign and certify all SWPPPs in accordance with General Condition G2, each time they revise or modify a SWPPP"

### Only if...  3 duties

These apply only in the situation named on each one. Answer the questions to sort them.

#### Annual dry-weather inspection for sewer cross-connections (bacteria-listed waters)

Facilities discharging to waters 303(d)-listed for bacteria do at least one dry-weather inspection of the stormwater system each year to find and eliminate sanitary sewer cross-connections, and keep the other mandatory bacteria BMPs in the SWPPP.

By December 31 each year.

- **Only if:** your stormwater reaches an impaired water body; receiving water listed for bacteria.

- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S6.C.1 Table 6 footnote h.2 , page 45](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=54)

> "Perform at least one annual dry weather inspection of the stormwater system to identify and eliminate sanitary sewer cross-connections;"

#### Table 6 sampling and effluent limits for discharges to 303(d)-listed waters

Facilities discharging directly or indirectly to a 303(d)-listed (Category 5) waterbody sample each such discharge point quarterly for the parameters the water is listed for (Table 6) and meet the numeric effluent limits; exceeding a limit is a permit violation, not a benchmark exceedance.

By the end of each calendar quarter.

- **Only if:** your stormwater reaches an impaired water body.

- You file it in the agency's system (WQWebPortal DMR).
- Keep the records 5 years.
- The permit says this is done by an accredited laboratory.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S6.C.1 , page 44](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=53)

> "Permittees discharging to a 303(d)-listed waterbody (Category 5), either directly or indirectly through a stormwater drainage system, shall comply with the applicable sampling requirements and numeric effluent limits in Table 6."

#### 6PPD-quinone sampling (from January 1, 2028)

Transportation, warehousing, petroleum bulk, waste management (562xxx) and hazardous waste treatment, storage and disposal facilities in Table 3 sample 6PPD-quinone (report only) quarterly from January 1, 2028; small businesses (50 or fewer employees) may sample once a year.

By the end of each calendar quarter, starting January 1, 2028.

- **Only if:** your NAICS code starts with 482, 485, 488210, 488490, 487110, 484, 491, 483, 487210, 4883, 532411, 481, 487990, 4247, 493, 531130, 562, or hazardous waste tsdf or dangerous waste recycler.
- If you are a small business as the permit defines it: a different schedule.

- You file it in the agency's system (WQWebPortal DMR).
- Keep the records 5 years.
- The permit says this is done by an accredited laboratory.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S5.B.3 , page 34](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=43)

> "The 6PPD-quinone (6PPDQ) sampling requirements in Table 3 go into effect on January 1, 2028."

## What does no-exposure certification require?

Conditional No Exposure (CNE) exemption, granted in writing by Ecology after an electronic application; must be renewed every five years. Permit coverage is terminated when it is granted.

- Every few years 1
- When something happens 6

### Every few years  1 duty

#### Renew the Conditional No Exposure certification every five years

Facilities granted a No Exposure exemption submit a new electronic No Exposure Certification application every five years; if anything becomes exposed, apply for and obtain a permit immediately.

No set date. S1.F.3.c requires a new No Exposure Certification application "once every five years". Does the five years run from Ecology's written approval of the exemption or from the date the previous application was submitted? Ecology must confirm before StormDue shows a renewal date.

- You file it in the agency's system (WQWebPortal (SAW)).
- Signed or certified by a responsible official per isgp G2A.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S1.F.3.c , page 10](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=19)

> "Facilities which are granted a No Exposure exemption must submit an electronic No Exposure Certification application to Ecology once every five years."

### When something happens  6 duties

#### Apply for coverage at least 60 days before discharging

New facilities submit a complete application (NOI) in WQWebPortal at least 60 days before stormwater discharge begins, certifying public notice and SEPA compliance.

At least 60 days before start of stormwater discharge.

- **When:** new facility.

- You file it in the agency's system (WQWebPortal).
- Keep the records 5 years.
- Signed or certified by a responsible official per isgp G2A.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S2.A.1.b , page 11](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=20)

> "Submit a complete and accurate permit application to Ecology at least 60 days before the commencement of stormwater discharge from the facility."

#### Apply to modify coverage 60 days before a significant process change

Submit a Modification of Coverage form (with public notice and, for process changes, SEPA) at least 60 days before a significant process change; to request a Level 2 or 3 extension or waiver, submit it before that corrective action deadline.

At least 60 days before planned change date.

- **When:** planned significant process change.

- You file it in the agency's system (WQWebPortal).
- Keep the records 5 years.
- Signed or certified by a responsible official per isgp G2A.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S2.B.1 , page 12](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=21)

> "Apply for modification of coverage at least 60 days before implementing a significant process change;"

#### File a Transfer of Coverage form with the new owner

The current permittee and the new discharger submit a signed Transfer of Coverage form with a specific transfer date; coverage transfers on that date unless Ecology objects.

Before transfer date.

- **When:** change of operator.

- You file it in the agency's system (Transfer of Coverage Form (Ecology)).
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S2.D , page 13](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=22)

> "Coverage under this general permit shall automatically transfer to a new discharger, if all of the following conditions are met:"

#### Give 45 days' notice of planned changes that may cause noncompliance

Submit a new or supplemental application to Ecology at least 45 days before facility expansions, production increases or other planned changes that may result in noncompliance with permit limits or conditions.

At least 45 days before planned change date.

- **When:** planned change may cause noncompliance.

- You file it in the agency's system (Ecology (new or supplemental application)).
- Keep the records 5 years.
- Signed or certified by a responsible official per isgp G2A.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section G21 , page 72](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=81)

> "The Permittee shall give advance notice to Ecology by submission of a new application, or supplement to the existing application, at least 45 days prior to commencement of such discharges,"

#### Phone the regional office within 24 hours; written report within 5 days

Report noncompliance that may endanger health or the environment, or a violation of a maximum daily limit, to the Ecology regional office by phone within 24 hours, and submit a detailed written report through WQWebPortal within 5 days.

Within 1 day after awareness of noncompliance.

- **When:** noncompliance endangering or daily limit exceeded.

- You file it in the agency's system (Regional office phone; WQWebPortal Permit Submittals).
- Keep the records 5 years.
- Signed or certified by a responsible official or duly authorized representative.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section S9.F , page 61](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=70)

> "Submit a detailed written report to Ecology within 5 days of the time the Permittee becomes aware of the circumstances, unless Ecology requests an earlier submission."

#### Send a new duly authorized representative authorization before the next signed report

If the written authorization of a duly authorized representative is no longer accurate (a different person or position now runs the facility), send Ecology a new authorization before or with the next report, information or application that person signs.

No set date. Before or together with the next document signed by the representative (G2.C).

- **When:** duly authorized representative changed.

- You file it in the agency's system (Ecology (written authorization)).
- Keep the records 5 years.
- Signed or certified by a responsible official per isgp G2A.

Source: [2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026) , section G2.C , page 66](https://fortress.wa.gov/ecy/ezshare/wq/permits/ISGP-V12Mod-GeneralPermit.pdf#page=75)

> "a new authorization satisfying the requirements of paragraph G2.B.2 above shall be submitted to Ecology prior to, or together with, any reports, information, or applications to be signed by an authorized representative."

## When are my own dates?

Choose your coverage and answer a few questions to see each duty with its next due date, and download them as a calendar file.

[Every state's permit](https://stormdue.com/states). [How we check permit rules](https://stormdue.com/about-the-rules). [Deadline calculator](https://stormdue.com/tools/deadline-calculator), [benchmark comparison](https://stormdue.com/tools/benchmark-comparison) and [more free tools](https://stormdue.com/tools).

---

StormDue reminds and keeps records. It does not file anything with the agency and does not certify or guarantee compliance. Check each duty against your permit; you are responsible for your filings.

StormDue does not guarantee that these facts are accurate or current. Verify them with your agency before you rely on them.