Every duty in the NPDES Multi-Sector General Permit for Stormwater Discharges Associated with Industrial Activity, with when it is due and the section it comes from.

Get my permit calendar

Free, no account. Your own dates in a minute.

  • 47duties, each cited
  • 4on a schedule
  • 42when something happens

StormDue reminds and keeps records. It does not file anything with the agency and does not certify or guarantee compliance. Check each duty against your permit; you are responsible for your filings.

What is this permit, and where do I file?

Today
March 1, 2021 February 28, 2026
Permit number
One permit number per area (Appendix C), e.g. MAR050000 (Massachusetts), NHR050000 (New Hampshire), NMR050000 (New Mexico), PRR050000 (Puerto Rico), DCR050000 (District of Columbia), per Part 9 headings; each facility receives its own NPDES ID
In force
March 1, 2021 to February 28, 2026, administratively continued until a new permit is issued
Official page
epa.gov
Rules last checked
November 26, 2026 (version 2026-11-26.2)
Notes on the permit's status and renewal

The permit expired February 28, 2026 at 11:59 pm eastern time and is administratively continued for operators covered before expiration (EPA continuance page, last updated March 9, 2026, read 2026-11-25). New facilities and new operators cannot obtain coverage until a new MSGP is issued; EPA's No Action Assurance memorandum of February 27, 2026 covers new facilities that meet its conditions and send Appendix G to msgp@epa.gov before discharging. The proposed 2026 MSGP (Federal Register December 13, 2024; comments closed May 19, 2025) was still shown as proposed on EPA's page (last updated March 1, 2026) on 2026-11-25 and 2026-11-26; no final permit or newer Federal Register notice was found. Once a new MSGP is issued, existing operators have 90 days from its effective date to submit a new NOI. The "Change NOI" function in NeT-MSGP is disabled during the continuance.

What does full permit coverage require?

Every quarter 2 duties

Quarterly visual assessment of a stormwater sample from each discharge point

By the end of each calendar quarter.

Each quarter, collect a sample from each discharge point (substantially identical points may rotate) within the first 30 minutes of discharge from a storm at least 72 hours after the previous discharge, and inspect it in a clear container for color, odor, clarity, solids, foam and oil sheen. Document and sign.

  • Does not apply if: the facility is inactive and unstaffed.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 3.2.1-3.2.3, page 29
"Once each quarter for your entire permit coverage, you must collect a stormwater sample from each discharge point (except as noted in Part 3.2.4) and conduct a visual assessment of each of these samples."
Open the permit at this section

Routine facility inspection every calendar quarter

By the end of each calendar quarter.

Qualified personnel (with at least one pollution prevention team member if a contractor) inspect exposed areas, potential pollutant sources, spill areas from the last three years, discharge points and control measures, during operating hours. At least one inspection per calendar year must be during a discharge. Document findings with a signed statement.

  • Does not apply if: the facility is inactive and unstaffed.
  • If the facility is inactive and unstaffed: a different schedule.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 3.1.1-3.1.6, page 27
"The qualified personnel must conduct inspections at least quarterly (i.e., once each calendar quarter), or in some instances more frequently"
Open the permit at this section

Every year 2 duties

Submit the Annual Report by January 30

By January 30, for the calendar year before.

Submit the Annual Report in NeT-MSGP summarizing the past calendar year's routine inspections, visual assessments, corrective actions and AIM responses (with status of any open items) and any noncompliance, with a signed certification.

  • You file it in the agency's system (NeT-MSGP).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.4, page 67
"You must submit an Annual Report to EPA via NeT-MSGP, per Part 7.2, by January 30th for each year of permit coverage containing information generated from the past calendar year."
Open the permit at this section

Update the public SWPPP within 45 days after the year's last routine inspection

Within 45 days after final routine inspection of year.

Update the SWPPP made public through the NOI attachment, a URL, or SWPPP information in the NOI, no later than 45 days after the final routine facility inspection of the year.

  • You file it in the agency's system (NeT-MSGP Change NOI, or the facility's SWPPP URL).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 6.4.1, page 63
"no later than 45 days after conducting the final routine facility inspection for the year required in Part 3.1."
Open the permit at this section

When something happens 14 duties

Call the National Response Center as soon as you know of a reportable-quantity spill

No set date. As soon as you have knowledge of the discharge (2.1.2.4); no number of hours stated.

When a leak, spill or other release of a hazardous substance or oil at or above a reportable quantity (40 CFR 110, 117 or 302) occurs in a 24-hour period, notify the National Response Center at (800) 424-8802 as soon as you know of it. State or local rules may require other calls. Document the spill under Part 5.3.

  • When: reportable quantity release.
  • You send it to the agency (National Response Center by phone; EPA Regional Office and MS4 operator (7.6.3)).
  • Keep the records 3 years.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 2.1.2.4; 7.6.3, page 23
"you must notify the National Response Center (NRC) at (800) 424-8802 or, in the Washington, DC, metropolitan area, call (202) 267-2675"
Open the permit at this section

Document the triggering condition within 24 hours and the response within 14 days

Within 1 day after awareness of condition.

Record the condition (and spill details) within 24 hours of becoming aware of it, and the corrective action or AIM response taken or planned, with dates, within 14 days of discovery. Keep with the SWPPP; summarize in the Annual Report.

  • When: corrective action condition, or aim triggering event.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 5.3.1; 5.3.3, page 54
"You must document the existence of any of the conditions listed in Parts 5.1.1, 5.2.3, 5.2.4, or 5.2.5 within 24 hours of becoming aware of"
Open the permit at this section

Fix conditions requiring corrective action within 14 days (45 at most)

Within 14 days after discovery of condition (up to 45 days where the permit allows more time).

On a triggering condition (unauthorized release, effluent limit violation, inadequate or missing controls, visual evidence of pollution): take reasonable steps the same day, finish corrective action before the next storm if possible and within 14 calendar days, or document why not and finish within 45 days (notify the EPA Region to go beyond 45). Modify the SWPPP within 14 days of completing the work.

  • When: corrective action condition.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 5.1.1; 5.1.3, page 46
"within 14 calendar days from the time of discovery that the condition in Part 5.1.1 is not met."
Open the permit at this section

New operator files an NOI and the old operator files an NOT when the operator changes

No set date. Table 1-2 requires a new operator's NOI "At least 30 calendar days prior to the date of transfer of control", while 1.3.4.2 says "no later than thirty (30) calendar days after a change in operators". EPA must say which deadline governs.

On a change of operator, the new operator submits a new NOI and the previous operator submits a NOT no later than 30 days after the new operator's coverage is active. The permit gives two different deadlines for the new operator's NOI (see the open question).

  • When: change of operator.
  • If change of operator: a different schedule.
  • You file it in the agency's system (NeT-MSGP).
  • Keep the records 3 years.
  • Signed or certified by a responsible official per MSGP Appendix B 11.A.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 1.3.4.2, page 14
"the new operator must submit a new NOI no later than thirty (30) calendar days after a change in operators."
Open the permit at this section

Notify EPA at least 30 days before planned physical changes

At least 30 days before planned change date.

Give EPA notice no fewer than 30 days before planned physical alterations that make the facility a new source or could significantly change or increase pollutants discharged.

  • When: planned significant physical change.
  • You send it to the agency (EPA Regional Office (Part 7.8) and MS4 operator).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.6.4, page 68
"You must give notice to EPA promptly, no fewer than 30 days prior to making any planned physical alterations or additions to the permitted facility"
Open the permit at this section

Promptly correct missing or wrong information in the NOI or any report

No set date. "Promptly"; no number of days stated.

When you learn that you left relevant facts out of the NOI or submitted incorrect information in the NOI or any report, submit the facts promptly.

  • When: incorrect or missing information found.
  • You send it to the agency (EPA Regional Office (Part 7.8) and MS4 operator).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.6.8, page 68
"You must promptly submit facts or information if you become aware that you failed to submit relevant facts in your NOI, or that you submitted incorrect information in your NOI or in any report."
Open the permit at this section

Report any other noncompliance when you submit monitoring reports

No set date. At the time monitoring reports (DMRs) are submitted (7.6.7).

Report every instance of noncompliance not already reported in the Annual Report, a compliance-schedule report or a 24-hour report, at the time monitoring reports are submitted.

  • When: unreported noncompliance.
  • You send it to the agency (EPA Regional Office (Part 7.8) and MS4 operator).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.6.7, page 68
"You must report all instances of noncompliance not reported in your Annual Report, compliance schedule report, or 24-hour report at the time monitoring reports are submitted;"
Open the permit at this section

Report monitoring results in NetDMR within 30 days of complete lab results

Within 30 days after complete lab results received.

Submit indicator, benchmark, ELG, impaired-waters and other monitoring data in NetDMR no later than 30 days after receiving complete lab results for all monitored discharge points for the period; if a monitored point had no discharge, report "no discharge" within 30 days after the period ends.

  • When: monitoring required this period.
  • If no discharge in period: Within 30 days after end of monitoring period.
  • You file it in the agency's system (NetDMR).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.3.1; 7.3.4, page 65
"no later than 30 days after you have received your complete laboratory results for all monitoring discharge points for the reporting period."
Open the permit at this section

Report noncompliance that may endanger health or the environment within 24 hours

Within 1 day after awareness of noncompliance.

Report orally within 24 hours of becoming aware, then in writing within 5 days, to the EPA Regional Office (and the MS4 operator if discharging through an MS4).

  • When: noncompliance endangering health or environment.
  • You send it to the agency (EPA Regional Office (Part 7.8) and MS4 operator).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.6.1-7.6.2, page 68
"Any information must be provided orally within 24 hours from the time you become aware of the circumstances;"
Open the permit at this section

State or tribal monitoring required by Part 9

No set date. Frequency set by Part 9 for each state or tribe; once per year when Part 9 sets none.

Follow any Part 9 monitoring requirement for the facility's location; once per year if Part 9 sets no frequency. The New Mexico PFAS and Massachusetts conditions are separate duties below.

  • When: part9 monitoring applies.
  • You file it in the agency's system (NetDMR).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 4.2.4, page 42
"If a monitoring frequency is not specified foran applicable requirement in Part 9, you must monitor once per year for the duration of your permit coverage."
Open the permit at this section

Submit a Change NOI within 30 days of any change

Within 30 days after change date.

If any information on the NOI changes, submit a Change NOI in NeT-MSGP within 30 calendar days.

  • When: noi information changed.
  • You file it in the agency's system (NeT-MSGP).
  • Keep the records 3 years.
  • Signed or certified by a responsible official per MSGP Appendix B 11.A.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 1.3.4.1, page 14
"you must submit a Change NOI form within thirty (30) calendar days after the change occurs."
Open the permit at this section

Submit a new NOI within 90 days after a new MSGP takes effect

Within 90 days after new permit effective date.

Once EPA issues the replacement MSGP, existing covered operators must submit a new NOI in NeT-MSGP within 90 days of its effective date to keep coverage.

  • When: new msgp issued.
  • You file it in the agency's system (NeT-MSGP).
  • Keep the records 3 years.
  • Signed or certified by a responsible official per MSGP Appendix B 11.A.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: Administrative Continuance of EPA's 2021 MSGP (web page, last updated March 9, 2026), section Existing Facilities with Active MSGP Coverage
"existing operators will have 90 days from the effective date of the new MSGP to submit a new NOI using NeT-MSGP in order to obtain coverage under the new MSGP."
Open the permit at this section

Submit a Notice of Termination within 30 days when coverage ends

Within 30 days after termination condition date.

Submit a NOT in NeT-MSGP within 30 days after a new operator is authorized, operations and industrial discharges have ceased (with erosion controls in place), Sector G/H/J termination conditions are met, or alternative permit coverage is obtained.

  • When: termination condition met.
  • You file it in the agency's system (NeT-MSGP).
  • Keep the records 3 years.
  • Signed or certified by a responsible official per MSGP Appendix B 11.A.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 1.4.2, page 16
"You must submit a NOT within 30 days after one or more of the following conditions have been met:"
Open the permit at this section

Tell EPA in advance about planned changes you expect will cause noncompliance

No set date. "Advance notice"; no number of days stated.

Give EPA advance notice of any planned change in the facility or activity that you anticipate will result in noncompliance with the permit.

  • When: planned change anticipated to cause noncompliance.
  • You send it to the agency (EPA Regional Office (Part 7.8) and MS4 operator).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.6.5, page 68
"You must give advance notice to EPA of any planned changes in the permitted facility or activity which you anticipate will result in noncompliance with permit requirements;"
Open the permit at this section

Ongoing 4 duties

Keep records for three years after coverage ends

Ongoing, no set date.

Keep the SWPPP and modifications, Part 6.5 documentation, corrective action and AIM records, reports, certifications, monitoring data and NOI data.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 after coverage expires or is terminated years.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.7, page 68
"for a period of at least three years from the date that your coverage under this permit expires or is terminated."
Open the permit at this section

Keep the SWPPP current, signed and on site

Ongoing, no set date.

Keep a complete, signed SWPPP at the facility, immediately available at inspections; modify it based on corrective actions and deadlines under Part 5 and sign each modification.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 6.1; 6.3; 6.4, page 62
"You must modify your SWPPP based on any corrective actions and deadlines required under Part 5."
Open the permit at this section

Post a public sign of permit coverage

No set date. standing duty from authorization.

Post and maintain a legible sign at a safe, publicly accessible location near the facility with the coverage statement, NPDES ID, a contact phone number and the SWPPP URL or EPA contact statement.

Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 1.3.5, page 14
"You must post a sign or other notice of your permit coverage at a safe, publicly accessible location in close proximity to your facility."
Open the permit at this section

Train employees on the SWPPP

No set date. The permit requires the SWPPP to state the training frequency/schedule (6.2.5.1.e) but does not set one.

Train all employees who work in exposed areas or carry out permit duties (including the pollution prevention team) on the topics in Part 2.1.2.8, on the frequency set in the SWPPP, and keep a training log.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 2.1.2.8; 6.2.5.1.e, page 23
"You must train all employees who work in areas where industrial materials or activities are exposed to stormwater, or who are responsible for implementing activities necessary to comply with this permit"
Open the permit at this section

Only if... 24 duties

These apply only in the situation named on each one. Answer the questions to sort them.

(Sector A) Inspect wood preservation areas every month

By the end of each month.

Timber products facilities that do wood surface protection and preservation inspect processing areas, transport areas and treated wood storage areas monthly, to check that treatment chemicals are kept off unprotected soils and away from stormwater.

  • Only if: your permit sector is A; wood surface protection and preservation.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: 2021 MSGP Part 8 Sector-Specific Requirements (as modified), section 8.A.5, page 72
"inspect processing areas, transport areas, and treated wood storage areas monthly"
Open the permit at this section

(Sector S) Inspect the airport every month of the deicing season

By the end of each month.

Air transportation facilities inspect at least monthly during the deicing season (for example October through April at most mid-latitude airports), and in every other month when deicing chemicals may be used.

  • Only if: your permit sector is S; deicing season month.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Part 8 Sector-Specific Requirements (as modified), section 8.S.6, page 184
"you must conduct facility inspections at least monthly during the deicing season"
Open the permit at this section

Quarterly indicator monitoring for pH, TSS and COD (report only)

By the end of each calendar quarter.

Sample each quarter for pH, TSS and COD and report in NetDMR; no threshold applies.

  • Only if: your permit subsector is B2, C5, D2, E3, F5, I1, J3, L2, N2, O1, P1, R1, T1, U3, V1, W1, X1, Y2, Z1, AB1, AC1, AD1.
  • Does not apply if: the facility is inactive and unstaffed.
  • You file it in the agency's system (NetDMR).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 4.2.1.1.a, page 36
"You must conduct indicator monitoring of stormwater discharges for pH, TSS, and COD each quarter, beginning in your first full quarter of permit coverage as identified in Part 4.1.7."
Open the permit at this section

(District of Columbia) Report endangering noncompliance to DOEE orally within 24 hours

Within 1 day after awareness of noncompliance.

Facilities in the District of Columbia also report noncompliance that may endanger health or the environment to the Associate Director, Inspection and Enforcement Division, orally within 24 hours.

  • Only if: the facility is in District of Columbia; noncompliance endangering health or environment.
  • You send it to the agency (DC Associate Director, Inspection and Enforcement Division (by phone)).
  • Keep the records 3 years.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.3.1.3, page 213
"All information shall be provided orally within 24 hours from the time the permittee becomes aware of the circumstances."
Open the permit at this section

(Guam) Give Guam EPA a copy of every final and local permit within two weeks of receiving it

Within 14 days after permit receipt date.

Facilities in Guam provide Guam EPA a copy of all final and local permits within two weeks of receipt.

  • Only if: the facility is in Guam; permit received.
  • You send it to the agency (Guam EPA, 401 Federal Permit Manager (condition A7: mail and email)).
  • Keep the records 3 years.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.9.4.1.m, page 230
"A copy of all final and local permits shall be provided to Guam EPA within two weeks of receipt"
Open the permit at this section

(Guam) Keep a Spill Prevention and Containment Plan and spill response materials

Ongoing, no set date.

Facilities in Guam develop and implement a Spill Prevention and Containment Plan and keep adequate spill response materials on hand for releases of oil, petroleum or other materials into territorial waters.

  • Only if: the facility is in Guam.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.9.4.2.g, page 231
"The Permittee shall develop and implement a Spill Prevention and Containment Plan."
Open the permit at this section

(Guam) Send Guam EPA a copy of every report and monitoring result you send EPA, at the same time

No set date. Concurrently with the EPA submission (9.9.4.1.n, condition A14).

Facilities in Guam send DMRs, follow-up monitoring reports, Exceedance Reports and other reports and monitoring data to Guam EPA at the same time they go to EPA, by mail and email to the addresses in condition A7, identified with WQC Order 2020-10 and the permit number.

  • Only if: the facility is in Guam; report submitted to epa.
  • You send it to the agency (Guam EPA, 401 Federal Permit Manager (condition A7: mail and email)).
  • Keep the records 3 years.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.9.4.1.n, page 230
"submitted to EPA shall be concurrently submitted to Guam EPA, consistent with condition A7."
Open the permit at this section

(Guam) Send the Notice of Termination to Guam EPA for approval before submitting it to EPA

No set date. Before the NOT is submitted to EPA (9.9.4.1.l, condition A12); the EPA NOT itself is due within 30 days (msgp.not).

Facilities in Guam submit the NOT to Guam EPA for review and approval before submitting it to EPA in NeT-MSGP. Guam EPA may inspect to confirm termination conditions are met.

  • Only if: the facility is in Guam; termination condition met.
  • You send it to the agency (Guam EPA, 401 Federal Permit Manager (condition A7: mail and email)).
  • Keep the records 3 years.
  • Signed or certified by a responsible official per MSGP Appendix B 11.A.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.9.4.1.l, page 230
"The NOT application shall be submitted to Guam EPA for review and approval prior to submittal to U.S. EPA"
Open the permit at this section

(Guam) Tell Guam EPA immediately of any unpermitted discharge or noncompliance, and report in writing within five days

Within 5 days after noncompliance date.

Facilities in Guam that have an unpermitted discharge or spill, or any noncompliance with the Guam certification, stop operations at the location, correct the problem, notify Guam EPA immediately (petroleum spills also to 911, Guam EPA's spill line, the Coast Guard and the National Response Center), and send Guam EPA a detailed written report within five days.

  • Only if: the facility is in Guam; unpermitted discharge or noncompliance.
  • You send it to the agency (Guam EPA (condition A7; spills by phone, 9.9.4.2.i)).
  • Keep the records 3 years.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.9.4.2.i.iv, page 232
"Submit a detailed written report to Guam EPA within five days of noncompliance"
Open the permit at this section

(Massachusetts) Sectors Q and R add copper (and for R aluminum and lead) benchmarks, and every quarterly sample must meet them

No set date. Part 9.1.2.5 adds copper (Sector Q) and aluminum, lead and copper (Sector R) "with a benchmark monitoring concentration as is included in the MSGP 2020 Table 1 of Appendix J", but the 2021 Appendix J Table 1 covers only hardness-dependent metals. EPA or MassDEP must say which values apply, and whether year 4 applies during the continuance (q1).. Only in coverage years 1 and 4, counted from when your coverage began.

Water transportation (Sector Q) facilities in Massachusetts add copper to benchmark monitoring; ship and boat yards (Sector R) add aluminum, lead and copper. For both sectors, benchmark monitoring stops only when all four quarterly samples meet the benchmark, not their average. Which benchmark values apply and the year-4 schedule are unclear (see the open question).

  • Only if: the facility is in Massachusetts; your permit sector is Q, R.
  • Does not apply if: the facility is inactive and unstaffed.
  • If your permit sector is R: a different schedule.
  • You file it in the agency's system (NetDMR).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.1.2.5, page 210
"Modify the monitoring requirements for Sectors Q and R such that all four of the quarterly monitoring samples must meet the benchmarks rather than the average of the four"
Open the permit at this section

(Massachusetts) Send results showing a limit or benchmark exceedance to MassDEP

No set date. No deadline stated in 9.1.2.4.

Facilities in Massachusetts send monitoring results that show a violation of an effluent limit or a benchmark exceedance, plus any follow-up monitoring and the corrective actions taken, to the MassDEP regional office (Bureau of Air and Waste).

  • Only if: the facility is in Massachusetts; limit or benchmark exceeded.
  • You send it to the agency (MassDEP regional office, attention Bureau of Air and Waste).
  • Keep the records 3 years.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.1.2.4, page 210
"shall be sent to the appropriate Regional Office of MassDEP (attention: Bureau of Air and Waste)."
Open the permit at this section

(Massachusetts) Send the SWPPP to MassDEP within 14 days of a request

Within 14 days after massdep request date.

Facilities in Massachusetts (MAR050000) submit the SWPPP to MassDEP within 14 days after MassDEP asks for it.

  • Only if: the facility is in Massachusetts; massdep swppp request.
  • You send it to the agency (MassDEP).
  • Keep the records 3 years.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.1.2.2, page 209
"the permittee is required to submit the SWPPP to MassDEP within 14 days of such a request."
Open the permit at this section

(New Hampshire) Inspect on-site infiltration BMPs at least once a year

No set date. At least annually under the SWPPP's inspection procedures; the permit does not say whether this means each calendar year or every 12 months.

Facilities in New Hampshire with on-site infiltration best management practices inspect them at least annually under procedures written in the SWPPP, including checks that infiltrated stormwater is not exposed to industrial pollutants and drains properly, and keep records of maintenance, inspections and corrective actions.

  • Only if: the facility is in New Hampshire; onsite infiltration bmp installed.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by your pollution prevention team.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.1.4.2.c, page 211
"The inspection procedures that will be followed at least annually."
Open the permit at this section

(New Hampshire) Notify NHDES immediately of infiltration permits, new non-stormwater discharges and reportable releases

No set date. "Immediately"; no number of hours stated.

Facilities in New Hampshire notify the relevant NHDES bureau immediately if an infiltration BMP may need a permit or registration, before any new non-stormwater discharge, and of reportable releases into a drinking-water source or source protection area.

  • Only if: the facility is in New Hampshire; nhdes notice condition.
  • You send it to the agency (NHDES (bureau depends on the notice; see 9.1.4.4)).
  • Keep the records 3 years.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.1.4.4, page 211
"Immediately notify the NHDES Drinking Water and Groundwater Bureau at (603) 271-2513 of reportable releases"
Open the permit at this section

(New Mexico) Compare benchmark results with the most restrictive of the MSGP and New Mexico values

No set date. Part 9.6.2 says "Most restrictive value (highlighted below) must be chosen" between a column headed "2020 proposed MSGP Benchmark" and the New Mexico values; several 2020 proposed values differ from the final 2021 Table 4-2 (copper 14 against 5.19 ug/L). EPA or NMED must say which MSGP value New Mexico facilities compare with.

Facilities in New Mexico (NMR050000) that do benchmark monitoring must use the most restrictive of the MSGP benchmark and the New Mexico benchmark for each pollutant. New Mexico sets its own values for pH, antimony, arsenic, chromium (VI), cyanide, lead, mercury and selenium, and hardness-dependent dissolved values for cadmium, chromium (III), copper, nickel, silver and zinc. Which MSGP values are the comparison is unclear (see the open question).

  • Only if: the facility is in New Mexico; your permit subsector is A1, A2, A3, A4, B1, C1, C2, C3, C4, D1, E1, E2, F1, F2, F3, F4, G1, G2, H1, J1, J2, K1, L1, M1, N1, Q1, S1, U1, U2, Y1, AA1, AA2.
  • You file it in the agency's system (NetDMR).
  • Keep the records 3 years.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.6.2, page 218
"Most restrictive value (highlighted below) must be chosen"
Open the permit at this section

(New Mexico) PFAS monitoring, then annually while above the screening level

No set date. Once in the first year of coverage, then annually only while PFOA plus PFOS exceed 0.070 ug/L; no due date within the year is stated.

New Mexico facilities in NAICS codes listed in EPA's December 4, 2019 TRI PFAS advance notice sample once in the first year of coverage for all 18 PFAS analytes (EPA Method 537.1) by an accredited lab, and annually after that if PFOA plus PFOS exceed 0.070 ug/L; send the results to NMED's Surface Water Quality Bureau.

  • Only if: the facility is in New Mexico; naics listed in 2019 tri pfas advance notice.
  • If pfoa plus pfos above nm screening level: a different schedule.
  • You send it to the agency (NMED Surface Water Quality Bureau, Point Source Program Manager).
  • Keep the records 3 years.
  • The permit says this is done by an accredited laboratory.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.6.2.1, page 216
"covered under this MSGP shall monitor and report PFAS in effluent once during the first"
Open the permit at this section

After an effluent-limit exceedance, flag it and re-sample within 30 days of the fix

Within 30 days after corrective action implemented.

Indicate the exceedance on a Change NOI, do corrective action, then follow-up sample within 30 calendar days of implementing it (or at the next measurable storm). If the follow-up still exceeds, submit an Exceedance Report within 30 days of the lab results and keep monitoring at least quarterly until results meet the limit.

  • Only if: your discharge is subject to federal effluent limitation guidelines (ELGs); elg exceedance.
  • You file it in the agency's system (NeT-MSGP Change NOI; NetDMR; EPA Regional Office (Part 7.8) for the Exceedance Report).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 4.2.3.3; 7.5, page 41
"you must conduct follow-up monitoring within 30 calendar days (or during the next measurable storm event, should none occur within 30 days) of implementing corrective action(s) taken per Part 5.1."
Open the permit at this section

AIM Level 1 after a benchmark annual-average exceedance

Within 14 days after lab results showing aim trigger (up to 45 days where the permit allows more time).

Immediately review the SWPPP and controls; implement additional measures within 14 days of receiving lab results (45 if infeasible, documented), or document why existing controls will work; then continue quarterly benchmark monitoring for four more quarters.

  • Only if: a parameter is at AIM level 1.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 5.2.2; 5.2.3, page 48
"you must implement those modifications or control measures within 14 days of receipt of laboratory results, unless doing so within 14 days is infeasible."
Open the permit at this section

AIM Level 2 after a continued exceedance in Level 1

Within 14 days after lab results showing aim trigger (up to 45 days where the permit allows more time).

Implement additional pollution prevention and good housekeeping measures beyond Level 1 within 14 days of the lab results (up to 45 days if documented; EPA may grant more on a demonstration), document how they will meet the benchmark, then continue quarterly monitoring for four quarters.

  • Only if: a parameter is at AIM level 2.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 5.2.4.2, page 49
"You must implement additional pollution prevention/good housekeeping SCMs within 14 days of receipt of laboratory results that indicate an AIM triggering event has occurred"
Open the permit at this section

AIM Level 3 structural or treatment controls

No set date. Part 5.2.5.2 says "identify the schedule ... within 14 days and install such measures within 60 days" without a start date; the Fact Sheet says "within 60 days of the Level 3 triggering event". EPA must say whether the clocks start at receipt of lab results or at the triggering event.

Identify the schedule for structural source controls and/or treatment within 14 days and install them within 60 days (90 if documented as infeasible; EPA may extend), then continue quarterly monitoring for four quarters. The permit does not say what starts the 14 and 60 days.

  • Only if: a parameter is at AIM level 3.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 5.2.5.2, page 50
"You must identify the schedule for installing the appropriate structural source and/or treatment stormwater control measures within 14 days and install such measures within 60 days."
Open the permit at this section

Annual effluent limitation monitoring for ELG-regulated discharges

Once each year of your coverage, counted from when it began.

Once per year, sample each discharge point carrying a Table 4-3 regulated discharge (e.g. cement storage piles, hazardous and non-hazardous landfills, coal piles, airport urea deicing, mine dewatering, asphalt emulsion, phosphate fertilizer, wet log decks) for the Part 8 limits.

  • Only if: your discharge is subject to federal effluent limitation guidelines (ELGs).
  • You file it in the agency's system (NetDMR).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 4.2.3.1, page 41
"you must monitor once per year at each stormwater discharge point containing the discharges identified in Table 4-3 for the parameters specified in the sector-specific section of Part 8."
Open the permit at this section

Annual impaired-waters monitoring in coverage years 1 and 4

Once each year of your coverage, counted from when it began. Only in coverage years 1 and 4, counted from when your coverage began.

If the first receiving water is impaired without a TMDL, sample each discharge point once in year 1 for all impairment pollutants (TSS for sediment/turbidity), and once in year 4 for those associated with the activity or benchmark list; keep monitoring annually while detected. With a TMDL, monitor only if EPA says so.

  • Only if: your stormwater reaches an impaired water body.
  • Does not apply if: the facility is inactive and unstaffed.
  • You file it in the agency's system (NetDMR).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 4.2.5.1.a, page 42
"Monitoring is required annually in the first year of permit coverage and again in the fourth year of permit coverage as follows, unless you detect a pollutant causing an impairment, in which case annual monitoring must continue."
Open the permit at this section

PAH indicator monitoring twice a year in coverage years 1 and 4

Once each year of your coverage, counted from when it began, 2 times.

Sample twice a year for the 16 priority PAHs in coverage years 1 and 4 if paved areas are (re)sealed with coal-tar sealcoat during coverage, or for the listed sectors (A with creosote, C SIC 2911, D, F, H, I, M, O, P SIC 4011/4013/5171, Q SIC 4493, R, S).

  • Only if: coal tar sealcoat during coverage, or your permit sector is D, F, H, I, M, O, R, S, or your SIC code starts with 2911, 4011, 4013, 5171, 4493, or sector a creosote.
  • You file it in the agency's system (NetDMR).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 4.2.1.1.b, page 36
"You must conduct indicator monitoring of stormwater discharges for PAHs bi-annually (i.e., sample twice per year) in the first and fourth years of permit coverage."
Open the permit at this section

Quarterly benchmark monitoring in coverage years 1 and 4

No set date. Part 4.2.2.3.b skips year-4 benchmarks "unless the first quarter of your fourth year of permit coverage occurs on or after the date this permit expires", but Part 4.2 says monitoring continues "at their original frequency during any continuance". EPA must say whether year-4 benchmarks apply when year 4 starts after February 28, 2026.. Only in coverage years 1 and 4, counted from when your coverage began.

For the benchmark parameters of the facility's subsectors (primary and co-located), sample every quarter in coverage year 1 and year 4. Stop a parameter for the next eight quarters (or for good after year 4) if its four-quarter average is at or below the benchmark; keep sampling quarterly and follow AIM if it exceeds. Whether year 4 applies when it starts during the administrative continuance is an open question.

  • Only if: your permit subsector is A1, A2, A3, A4, B1, C1, C2, C3, C4, D1, E1, E2, F1, F2, F3, F4, G1, G2, H1, J1, J2, K1, L1, M1, N1, Q1, S1, U1, U2, Y1, AA1, AA2.
  • Does not apply if: the facility is inactive and unstaffed.
  • You file it in the agency's system (NetDMR).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 4.2.2.3, page 39
"Benchmark monitoring of stormwater discharges is required quarterly, as identified in Part 4.1.7, in the first and fourth year of permit coverage"
Open the permit at this section

What does no-exposure certification require?

Conditional no exposure exclusion under 40 CFR 122.26(g); not permit coverage. Submitted in NeT-MSGP and renewed every five years. Unaffected by the permit's expiration.

Every few years 1 duty

Renew the No Exposure Certification every five years

Within 5 years after last nec submission date.

Facilities excluded under no exposure submit a new NEC to EPA in NeT-MSGP once every five years.

  • You file it in the agency's system (NeT-MSGP).
  • Signed or certified by a responsible official per MSGP Appendix B 11.A.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 1.5, page 17
"You must submit a NEC form to EPA once every five years."
Open the permit at this section

When something happens 7 duties

Call the National Response Center as soon as you know of a reportable-quantity spill

No set date. As soon as you have knowledge of the discharge (2.1.2.4); no number of hours stated.

When a leak, spill or other release of a hazardous substance or oil at or above a reportable quantity (40 CFR 110, 117 or 302) occurs in a 24-hour period, notify the National Response Center at (800) 424-8802 as soon as you know of it. State or local rules may require other calls. Document the spill under Part 5.3.

  • When: reportable quantity release.
  • You send it to the agency (National Response Center by phone; EPA Regional Office and MS4 operator (7.6.3)).
  • Keep the records 3 years.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 2.1.2.4; 7.6.3, page 23
"you must notify the National Response Center (NRC) at (800) 424-8802 or, in the Washington, DC, metropolitan area, call (202) 267-2675"
Open the permit at this section

New operator files an NOI and the old operator files an NOT when the operator changes

No set date. Table 1-2 requires a new operator's NOI "At least 30 calendar days prior to the date of transfer of control", while 1.3.4.2 says "no later than thirty (30) calendar days after a change in operators". EPA must say which deadline governs.

On a change of operator, the new operator submits a new NOI and the previous operator submits a NOT no later than 30 days after the new operator's coverage is active. The permit gives two different deadlines for the new operator's NOI (see the open question).

  • When: change of operator.
  • If change of operator: a different schedule.
  • You file it in the agency's system (NeT-MSGP).
  • Keep the records 3 years.
  • Signed or certified by a responsible official per MSGP Appendix B 11.A.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 1.3.4.2, page 14
"the new operator must submit a new NOI no later than thirty (30) calendar days after a change in operators."
Open the permit at this section

Notify EPA at least 30 days before planned physical changes

At least 30 days before planned change date.

Give EPA notice no fewer than 30 days before planned physical alterations that make the facility a new source or could significantly change or increase pollutants discharged.

  • When: planned significant physical change.
  • You send it to the agency (EPA Regional Office (Part 7.8) and MS4 operator).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.6.4, page 68
"You must give notice to EPA promptly, no fewer than 30 days prior to making any planned physical alterations or additions to the permitted facility"
Open the permit at this section

Promptly correct missing or wrong information in the NOI or any report

No set date. "Promptly"; no number of days stated.

When you learn that you left relevant facts out of the NOI or submitted incorrect information in the NOI or any report, submit the facts promptly.

  • When: incorrect or missing information found.
  • You send it to the agency (EPA Regional Office (Part 7.8) and MS4 operator).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.6.8, page 68
"You must promptly submit facts or information if you become aware that you failed to submit relevant facts in your NOI, or that you submitted incorrect information in your NOI or in any report."
Open the permit at this section

Report any other noncompliance when you submit monitoring reports

No set date. At the time monitoring reports (DMRs) are submitted (7.6.7).

Report every instance of noncompliance not already reported in the Annual Report, a compliance-schedule report or a 24-hour report, at the time monitoring reports are submitted.

  • When: unreported noncompliance.
  • You send it to the agency (EPA Regional Office (Part 7.8) and MS4 operator).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.6.7, page 68
"You must report all instances of noncompliance not reported in your Annual Report, compliance schedule report, or 24-hour report at the time monitoring reports are submitted;"
Open the permit at this section

Report noncompliance that may endanger health or the environment within 24 hours

Within 1 day after awareness of noncompliance.

Report orally within 24 hours of becoming aware, then in writing within 5 days, to the EPA Regional Office (and the MS4 operator if discharging through an MS4).

  • When: noncompliance endangering health or environment.
  • You send it to the agency (EPA Regional Office (Part 7.8) and MS4 operator).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.6.1-7.6.2, page 68
"Any information must be provided orally within 24 hours from the time you become aware of the circumstances;"
Open the permit at this section

Tell EPA in advance about planned changes you expect will cause noncompliance

No set date. "Advance notice"; no number of days stated.

Give EPA advance notice of any planned change in the facility or activity that you anticipate will result in noncompliance with the permit.

  • When: planned change anticipated to cause noncompliance.
  • You send it to the agency (EPA Regional Office (Part 7.8) and MS4 operator).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 7.6.5, page 68
"You must give advance notice to EPA of any planned changes in the permitted facility or activity which you anticipate will result in noncompliance with permit requirements;"
Open the permit at this section

Only if... 2 duties

These apply only in the situation named on each one. Answer the questions to sort them.

(District of Columbia) Report endangering noncompliance to DOEE orally within 24 hours

Within 1 day after awareness of noncompliance.

Facilities in the District of Columbia also report noncompliance that may endanger health or the environment to the Associate Director, Inspection and Enforcement Division, orally within 24 hours.

  • Only if: the facility is in District of Columbia; noncompliance endangering health or environment.
  • You send it to the agency (DC Associate Director, Inspection and Enforcement Division (by phone)).
  • Keep the records 3 years.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.3.1.3, page 213
"All information shall be provided orally within 24 hours from the time the permittee becomes aware of the circumstances."
Open the permit at this section

(Guam) Tell Guam EPA immediately of any unpermitted discharge or noncompliance, and report in writing within five days

Within 5 days after noncompliance date.

Facilities in Guam that have an unpermitted discharge or spill, or any noncompliance with the Guam certification, stop operations at the location, correct the problem, notify Guam EPA immediately (petroleum spills also to 911, Guam EPA's spill line, the Coast Guard and the National Response Center), and send Guam EPA a detailed written report within five days.

  • Only if: the facility is in Guam; unpermitted discharge or noncompliance.
  • You send it to the agency (Guam EPA (condition A7; spills by phone, 9.9.4.2.i)).
  • Keep the records 3 years.
Source: 2021 MSGP Part 9 Conditions Applicable to States, Indian Country Lands, or Territories (as modified), section 9.9.4.2.i.iv, page 232
"Submit a detailed written report to Guam EPA within five days of noncompliance"
Open the permit at this section

When are my own dates?

Choose your coverage and answer a few questions. You get each duty's next date and a calendar file.