Get my permit calendar

No exposure certification checklist

A facility whose industrial materials and activities are all under a storm-resistant roof or cover can certify "no exposure" instead of holding full permit coverage. These are the eleven questions the federal rule and EPA's form ask. Answer each one for the whole facility: one "yes" means it does not qualify as it is.

Free, no account. Each question links to the regulation it comes from.

Last checked November 25, 2026. StormDue does not guarantee that these facts are accurate or current. Verify them with your agency before you rely on them.

Are any of the following materials or activities exposed to precipitation, now or in the foreseeable future? Answer for the whole facility: the exclusion is facility-wide, not per outfall.

  1. Using, storing or cleaning industrial machinery or equipment, and areas where residuals from using, storing or cleaning industrial machinery or equipment remain and are exposed to storm waterSource
    What it saysUsing, storing or cleaning industrial machinery or equipment, and areas where residuals from using, storing or cleaning industrial machinery or equipment remain and are exposed to storm water40 CFR 122.26(g)(4)(iii)(A) (ecfr.gov). Retrieved November 25, 2026.
  2. Materials or residuals on the ground or in storm water inlets from spills/leaksSource
    What it saysMaterials or residuals on the ground or in storm water inlets from spills/leaks40 CFR 122.26(g)(4)(iii)(B) (ecfr.gov). Retrieved November 25, 2026.
  3. Materials or products from past industrial activitySource
    What it saysMaterials or products from past industrial activity40 CFR 122.26(g)(4)(iii)(C) (ecfr.gov). Retrieved November 25, 2026.
  4. Material handling equipment (except adequately maintained vehicles)Source
    What it saysMaterial handling equipment (except adequately maintained vehicles)40 CFR 122.26(g)(4)(iii)(D) (ecfr.gov). Retrieved November 25, 2026.
  5. Materials or products during loading/unloading or transporting activitiesSource
    What it saysMaterials or products during loading/unloading or transporting activities40 CFR 122.26(g)(4)(iii)(E) (ecfr.gov). Retrieved November 25, 2026.
  6. Materials or products stored outdoors (except final products intended for outside use, e.g., new cars, where exposure to storm water does not result in the discharge of pollutants)Source
    What it saysMaterials or products stored outdoors (except final products intended for outside use, e.g., new cars, where exposure to storm water does not result in the discharge of pollutants)40 CFR 122.26(g)(4)(iii)(F) (ecfr.gov). Retrieved November 25, 2026.
  7. Materials contained in open, deteriorated or leaking storage drums, barrels, tanks, and similar containersSource
    What it saysMaterials contained in open, deteriorated or leaking storage drums, barrels, tanks, and similar containers40 CFR 122.26(g)(4)(iii)(G) (ecfr.gov). Retrieved November 25, 2026.
  8. Materials or products handled/stored on roads or railways owned or maintained by the dischargerSource
    What it saysMaterials or products handled/stored on roads or railways owned or maintained by the discharger40 CFR 122.26(g)(4)(iii)(H) (ecfr.gov). Retrieved November 25, 2026.
  9. Waste material (except waste in covered, non-leaking containers, e.g., dumpsters)Source
    What it saysWaste material (except waste in covered, non-leaking containers, e.g., dumpsters)40 CFR 122.26(g)(4)(iii)(I) (ecfr.gov). Retrieved November 25, 2026.
  10. Application or disposal of process wastewater (unless otherwise permitted)Source
    What it saysApplication or disposal of process wastewater (unless otherwise permitted)40 CFR 122.26(g)(4)(iii)(J) (ecfr.gov). Retrieved November 25, 2026.
  11. Particulate matter or visible deposits of residuals from roof stacks/vents not otherwise regulated, i.e., under an air quality control permit, and evident in the storm water outflowSource
    What it saysParticulate matter or visible deposits of residuals from roof stacks/vents not otherwise regulated, i.e., under an air quality control permit, and evident in the storm water outflow40 CFR 122.26(g)(4)(iii)(K) (ecfr.gov). Retrieved November 25, 2026.
What does not need a roof or cover?
  • Drums, barrels, tanks, and similar containers that are tightly sealed, provided those containers are not deteriorated and do not leak ("Sealed" means banded or otherwise secured and without operational taps or valves)
  • Adequately maintained vehicles used in material handling
  • Final products, other than products that would be mobilized in storm water discharge (e.g., rock salt)
Source
What it saysAdequately maintained vehicles used in material handling40 CFR 122.26(g)(2) (ecfr.gov). Retrieved November 25, 2026.

What does "no exposure" mean?

In the regulation's words: "No exposure" means that all industrial materials and activities are protected by a storm resistant shelter to prevent exposure to rain, snow, snowmelt, and/or runoff. Source

What it says"No exposure" means that all industrial materials and activities are protected by a storm resistant shelter to prevent exposure to rain, snow, snowmelt, and/or runoff.40 CFR 122.26(g) (ecfr.gov). Retrieved November 25, 2026.

What are the limits?

  • This conditional exclusion from the requirement for an NPDES permit is available on a facility-wide basis only, not for individual outfalls. Source
    What it saysThis conditional exclusion from the requirement for an NPDES permit is available on a facility-wide basis only, not for individual outfalls.40 CFR 122.26(g)(3)(ii) (ecfr.gov). Retrieved November 25, 2026.
  • Storm water discharges from construction activities identified in paragraphs (b)(14)(x) and (b)(15) are not eligible for this conditional exclusion. Source
    What it saysStorm water discharges from construction activities identified in paragraphs (b)(14)(x) and (b)(15) are not eligible for this conditional exclusion.40 CFR 122.26(g)(3)(i) (ecfr.gov). Retrieved November 25, 2026.
  • If circumstances change and industrial materials or activities become exposed to rain, snow, snow melt, and/or runoff, the conditions for this exclusion no longer apply. Source
    What it saysIf circumstances change and industrial materials or activities become exposed to rain, snow, snow melt, and/or runoff, the conditions for this exclusion no longer apply.40 CFR 122.26(g)(3)(iii) (ecfr.gov). Retrieved November 25, 2026.
  • The NPDES permitting authority retains the authority to require permit authorization (and deny this exclusion) upon making a determination that the discharge causes, has a reasonable potential to cause, or contributes to an instream excursion above an applicable water quality standard. Source
    What it saysThe NPDES permitting authority retains the authority to require permit authorization (and deny this exclusion) upon making a determination that the discharge causes, has a reasonable potential to cause, or contributes to an instream excursion above an applicable water quality standard.40 CFR 122.26(g)(3)(iv) (ecfr.gov). Retrieved November 25, 2026.
  • Submit the signed certification to the NPDES permitting authority once every five years. The federal minimum. A state permit can ask for more often: see state_notes. Source
    What it saysSubmit the signed certification to the NPDES permitting authority once every five years.40 CFR 122.26(g)(1)(iii) (ecfr.gov). Retrieved November 25, 2026.

Do states ask for more?

Some do. A state can ask for renewal more often than every five years, charge a fee, or use its own form. California's Industrial General Permit asks facilities with no exposure coverage to recertify each reporting year by October 1, or apply for full coverage. Source

What it saysBy October 1 of each reporting year beginning in 2015, any Discharger who has previously registered for NEC coverage shall either submit and certify an NEC ... or apply for NOI coverage.Industrial General Permit, Order 2014-0057-DWQ, Section XVII.G, page 68, printed page 68 (waterboards.ca.gov). Retrieved November 23, 2026.
Your state's page has the agency and the official link: find your state's permit.

The form's own words: If you answer "Yes" to any of these questions, you are not eligible for the no exposure exclusion. Source

What it saysIf you answer "Yes" to any of these questions, you are not eligible for the no exposure exclusion.NPDES Form 3510-11, Section E, Exposure Checklist, printed page K-3 (epa.gov). Retrieved November 25, 2026.
. Download the questions as JSON. Not sure your industry is listed at all? Check your industry, or see all free tools.

See my checklist result