Industrial stormwater inspection checklist you can copy

November 26, 2026

Get my permit calendar

Free, no account: your permit's recurring duties with due dates and the permit section for each.

An industrial stormwater inspection checklist should tell you where to look, what to record, and what needs attention before you finish the report. Copy the checklist below, then replace the general area names with the actual locations at your facility.

The permit examples here apply to facilities under EPA jurisdiction with continued coverage under the 2021 Multi-Sector General Permit (MSGP). EPA says that permit remains in effect for previously covered operators after its February 28, 2026, expiration. If you hold a state-issued permit, check its inspection provisions before using these examples. EPA’s permit continuation notice explains the federal coverage distinction.

Copy this industrial stormwater inspection checklist

Use this as a field checklist, then add the report fields in the next section. The inspection scope follows EPA’s industrial operator guide and the federal MSGP, Parts 3.1.2 and 3.1.3. Your permit and industry-specific conditions control what belongs on your final form. EPA’s industrial operator guide provides the inspection framework.

Check Look for and record
☐ Outdoor materials and work areas Exposed material, loose residue, uncovered waste, and pollutants that could reach runoff.
☐ Loading and unloading areas Spilled product, damaged containers, and material along the drainage path.
☐ Equipment, tanks, and containers Leaks, drips, staining, and failed covers or containment.
☐ Waste collection areas Escaped debris, leaking containers, and residue around the collection area.
☐ Vehicle entrances and exits Industrial material, waste, or sediment tracked offsite.
☐ Previous spill locations Remaining residue, recurring leaks, and unfinished cleanup.
☐ Drains, channels, and discharge points Deposits, erosion, staining, unexpected flow, and evidence of pollutants.
☐ Stormwater controls Damage, blockage, bypass, and maintenance or replacement needs.
☐ Conditions during runoff Where water actually flows and whether controls function as intended.
☐ Follow-up from the previous inspection Whether the recorded work was completed and the problem remains resolved.

For every applicable row, record the location, observation, and action needed. Use “not applicable” with a reason instead of leaving a blank. Treat checking previous work as a practical addition to the permit-based inspection scope.

Add the fields that make it an inspection record

A checked box doesn’t explain what you saw. Give each inspection its own record, with enough space for observations rather than a single comment box at the bottom.

For federally covered facilities, EPA’s 2021 MSGP Part 3.1.6 requires inspection findings, inspector names and signatures, date and time, weather, discharge observations, control deficiencies, additional controls needed, incidents of noncompliance, and a signed certification under Appendix B, Subsection 11. Keep the report with the stormwater pollution prevention plan (SWPPP). See the federal permit, Part 3.1.6.

Build your working form around these fields, and check the required wording against your permit before use.

Inspection header

  • Facility name, address, permit number, and inspection type.
  • Inspection date, start time, and finish time.
  • Inspector names, roles, and signatures.
  • Weather and whether stormwater was discharging.
  • Permit-required certification and authorized signature.

Observation entry

  • Area or control inspected, using the site map label.
  • Condition observed, including any potential route to a drain.
  • Photograph reference, if you took a photograph.
  • Maintenance, repair, replacement, or further investigation needed.
  • Person assigned, applicable timing, and completion record.

The assignment and photograph fields are useful working additions. Don’t assume they replace a separate corrective-action record required by your permit.

For example, write “Loose metal shavings on pavement beside the scrap bin; pavement drains toward the yard inlet.” That gives the person doing the cleanup a location and a problem to address. “Housekeeping needs improvement” does neither.

Turn the checklist into a route through your facility

Start with your site map and write the same location names on the checklist. “Outside storage” is too broad if you have separate raw-material, finished-product, and waste areas. Give each its own row.

I’d use a fixed walking route for a small facility. It makes the form easier to hand to a backup inspector and helps you compare conditions between inspections. The tradeoff is that the route can become mechanical. Leave space for newly observed activities and sources that aren’t already printed on the form.

EPA’s industrial operator guide recommends documenting an inspection sequence and procedures that staff can follow. Use that approach to connect the checklist to your SWPPP’s site map and inspection procedures. EPA’s guide, section on routine facility inspections.

Before the walk, pull the previous inspection and any open work records. Highlight the locations you need to revisit. Bring the map rather than relying on memory about which inlet receives runoff from which work area.

At each stop, separate the source from the control. A covered container may be intact while spilled material remains on the pavement beside it. Give yourself room to record both observations.

For drains and discharge points, use the actual labels from your map. Record what you could inspect and any access limitation. Don’t turn an inaccessible location into a checked “satisfactory” box.

Match inspection timing to your permit

For active facilities covered by EPA’s 2021 MSGP, Part 3.1.4 requires routine inspections at least once each calendar quarter, with more frequent inspections where applicable. At least one routine inspection each calendar year must occur while stormwater is discharging. Parts 3.1.2 and 3.1.3.8 address operating hours and observations during discharge. See EPA’s explanation of inspection frequency and wet-weather observations.

Those are different timing conditions. The routine inspection has a calendar-based interval. The discharge-time inspection also depends on runoff occurring. An internal appointment on a dry day doesn’t establish that you completed the discharge-time observation.

Put a field near the top of your checklist for “stormwater discharging during inspection.” Below it, provide space to describe the discharge locations observed and how the controls performed. Keep that field visible so the inspector doesn’t have to remember it after returning indoors.

Don’t import a rainfall threshold from a sampling procedure into this checklist unless your inspection provision actually uses it. For the inspection frequency and permit sections that apply to your jurisdiction, use the inspection requirements by permit as a starting point, then confirm the requirement in your permit.

Also check your industry-specific provisions. For example, federally covered airport facilities have additional inspection requirements under EPA’s 2021 MSGP Part 8.S.6. A general facility checklist needs those applicable additions. EPA’s sector-specific permit requirements.

Give each finding a clear follow-up record

When you identify a problem, record when it was discovered. For federally covered facilities, EPA’s 2021 MSGP Part 5.1.3 requires immediate reasonable steps for conditions requiring corrective action, with subsequent-action timing measured from discovery. Read the full provision before assigning a completion date. Federal permit, Part 5.1.3.

Use a separate line for each finding. A practical entry might read as follows.

Location: Waste container beside shipping door. Observation: Liquid residue beneath the container and toward the yard drain. Immediate response: Record the actual containment and cleanup performed. Assigned person: Enter a name. Further work: Determine the source and arrange repair or replacement as appropriate. Closure: Record what was done, when, and who checked it.

This is an example of record structure, not a determination of the response required at your site.

Avoid closing a finding with “maintenance notified.” That records a handoff. Leave the item open until you can describe the completed work and its verification. If work is delayed, preserve the original discovery date and record the reason separately.

For recurring inspection duties, StormDue lists the duty, due date, and permit section, adds reminders, and keeps a dated record of completed work. It can support the scheduling and recordkeeping around your inspections. It doesn’t perform the inspection, file reports or certify findings; that stays with you and your permit.

Check the form before your next inspection

Take your draft checklist on a practice walk before adopting it. Use the form exactly as a backup inspector would, without filling gaps from memory.

  • Compare every mapped industrial area and control with a checklist row.
  • Replace broad labels with locations someone else can find.
  • Check the inspection, documentation, signature, and industry-specific provisions in your permit.
  • Add enough writing space to describe an actual finding.
  • Confirm where completed records and supporting photographs will be kept.

Use your facility’s permit document as the reference. If you need a starting point for finding it, use the permit lookup, then confirm the document and coverage with your permitting agency.

Ask the person responsible for follow-up work to read a sample finding. Can they locate the problem and tell what needs attention without calling the inspector? If not, revise the location labels or observation fields before printing the final form.

FAQ

Can I use this checklist instead of an agency form?

Use an agency-required form when your permit or agency requires it. Otherwise, check that your customized form contains every required element. For example, Oklahoma DEQ allows facilities covered by OKR05 to use their own inspection report if it covers Part 3 and applicable Part 10 requirements. Oklahoma DEQ’s inspection form guidance.

Who should complete the inspection checklist?

Choose someone who meets your permit’s inspector qualifications and knows the site. Under EPA’s 2021 MSGP Part 3.1.1, qualified personnel must inspect, and a pollution prevention team member must participate if the qualified inspector is an outside contractor. Federal permit, Part 3.1.1.

Should I attach photographs to the checklist?

I’d attach photographs for findings that need repair or follow-up. Label each with the location and observation reference. Keep written notes as well, since a photograph alone may not explain the drainage path, the response taken, or what remains unfinished.

What should I write when an area has no problems?

Record a specific observation, such as “Container closed; no visible leakage or loose material on surrounding pavement.” Use that wording only when it matches what you inspected. Keep “not applicable” separate from “inspected, no problem observed,” and explain any area you couldn’t inspect.