Permit
JanFebMarAprMayJunJulAugSepOctNovDec
California Industrial General Permit (IGP)
January 31, 2027: Do the monthly visual observation of every drainage area.
February 28, 2027: Do the monthly visual observation of every drainage area.
March 31, 2027: Do the monthly visual observation of every drainage area.
April 30, 2027: Do the monthly visual observation of every drainage area.
May 31, 2027: Do the monthly visual observation of every drainage area.
June 30, 2027: Do the monthly visual observation of every drainage area.
June 30, 2027: Do the Annual Comprehensive Facility Compliance Evaluation.
July 31, 2027: Do the monthly visual observation of every drainage area.
August 31, 2027: Do the monthly visual observation of every drainage area.
September 30, 2027: Do the monthly visual observation of every drainage area.
October 31, 2027: Do the monthly visual observation of every drainage area.
November 30, 2027: Do the monthly visual observation of every drainage area.
December 31, 2027: Do the monthly visual observation of every drainage area.
Texas MSGP
March 31, 2027: Quarterly visual examination of each outfall's discharge.
March 31, 2027: Routine facility inspection every quarter (monthly for Sector E).
June 30, 2027: Quarterly visual examination of each outfall's discharge.
June 30, 2027: Routine facility inspection every quarter (monthly for Sector E).
September 30, 2027: Quarterly visual examination of each outfall's discharge.
September 30, 2027: Routine facility inspection every quarter (monthly for Sector E).
December 31, 2027: Quarterly visual examination of each outfall's discharge.
December 31, 2027: Routine facility inspection every quarter (monthly for Sector E).
Washington ISGP
January 31, 2027: Monthly site inspection, at least a week apart, signed by two people.
February 28, 2027: Monthly site inspection, at least a week apart, signed by two people.
March 31, 2027: Monthly site inspection, at least a week apart, signed by two people.
April 30, 2027: Monthly site inspection, at least a week apart, signed by two people.
May 31, 2027: Monthly site inspection, at least a week apart, signed by two people.
June 30, 2027: Monthly site inspection, at least a week apart, signed by two people.
July 31, 2027: Monthly site inspection, at least a week apart, signed by two people.
August 31, 2027: Monthly site inspection, at least a week apart, signed by two people.
September 30, 2027: Monthly site inspection, at least a week apart, signed by two people.
October 31, 2027: Monthly site inspection, at least a week apart, signed by two people.
November 30, 2027: Monthly site inspection, at least a week apart, signed by two people.
December 31, 2027: Monthly site inspection, at least a week apart, signed by two people.
December 31, 2027: Inspect dumpsters for holes or defects once a year.
EPA 2021 MSGP
March 31, 2027: Quarterly visual assessment of a stormwater sample from each discharge point.
March 31, 2027: Routine facility inspection every calendar quarter.
June 30, 2027: Quarterly visual assessment of a stormwater sample from each discharge point.
June 30, 2027: Routine facility inspection every calendar quarter.
September 30, 2027: Quarterly visual assessment of a stormwater sample from each discharge point.
September 30, 2027: Routine facility inspection every calendar quarter.
December 31, 2027: Quarterly visual assessment of a stormwater sample from each discharge point.
December 31, 2027: Routine facility inspection every calendar quarter.