Montana Multi-Sector General Permit (MSGP) MTR000000 due dates and duties

Every duty in the Montana Pollutant Discharge Elimination System (MPDES) Multi-Sector General Permit for Storm Water Discharges Associated with Industrial Activity, with when it is due and the section it comes from.

Get my permit calendar

Free, no account. Your own dates in a minute.

  • 65duties, each cited
  • 11on a schedule
  • 54when something happens

Set up your facility free to date the ones that count from your own records, such as your last training.

StormDue reminds and keeps records. It does not file anything with the agency and does not certify or guarantee compliance. Check each duty against your permit; you are responsible for your filings.

What is this permit, and where do I file?

Permit number
MTR000000
In force
February 1, 2023 to January 31, 2028
Official page
deq.mt.gov
Rules last checked
November 27, 2026
Today
February 1, 2023 January 31, 2028
Notes on the permit's status and renewal

Cover page: "This Permit shall become effective February 1, 2023" and "This Permit and the authorization to discharge shall expire at midnight, January 31, 2028", issuance date October 4, 2022, signed for the Water Protection Bureau. The fact sheet says the previous permit ran from February 1, 2018 to January 31, 2023; this is DEQ's seventh issue of the MSGP. On November 27, 2026 it was current, not administratively continued: DEQ's MPDES page links this file as "General Permit (effective February 1, 2023)" under Stormwater Industrial (MSGP) MTR000000, and no modification, draft renewal or notice for MTR000000 was found. The renewal deadline for 2018 permittees (30 days after January 31, 2023) has passed and is not shown. Part 4.3 asks for reapplication at least 30 days before expiry (open question q4). The permit covers metal mining, coal mining, oil and gas and mineral mining (Sectors G to J) as well; stormwater subject to a federal effluent guideline (Part 6) needs a separate MPDES permit. Fees apply under ARM 17.30.201; amounts are left out.

What does full permit coverage require?

Authorization under the MSGP: an application package (NOI-SWI form, SWPPP, sage grouse letter if needed, fee); coverage starts on the date of DEQ's authorization letter.

Every quarter 2 duties

Inspect the facility each calendar quarter

By the end of each calendar quarter.

A qualified inspector inspects, during normal operating hours, all areas where industrial materials or activities are exposed, potential pollutant sources, areas with spills or leaks in the past three years, non-stormwater discharge points, outfalls and control measures, at least quarterly, and documents each inspection with the SWPPP, signed by the SWPPP Administrator.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 2.4.3. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.4.3, page 18
"Routine facility inspections must be conducted at least quarterly."
Open the permit at this section

Submit the quarterly DMR by the 28th of the month after each quarter

By April 28 (Q1), July 28 (Q2), October 28 (Q3) and January 28 (Q4), starting with the first full calendar quarter after your coverage begins.

Report all monitoring results for each calendar quarter on the electronic Discharge Monitoring Report in EPA's NetDMR by the 28th of the following month (April 28, July 28, October 28 and January 28), reporting "No Discharge" for a quarter without one.

  • You file it in the agency's system (NetDMR).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.9.1, page 27
"All monitoring data collected pursuant to Part 2.6 must be submitted to the Department no later than the 28th day of the month following the reporting period."
Open the permit at this section

Every year 4 duties

Do one routine inspection each calendar year while stormwater is discharging

By December 31 each year.

At least once each calendar year, conduct the routine facility inspection while a stormwater discharge is occurring; if the outfall does not usually discharge, during a rainfall or snowmelt event with prominent wet-weather conditions at the site.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.4.3, page 18
"At least once each calendar year, the routine facility inspection must be conducted during a period when a storm water discharge is occurring."
Open the permit at this section

Submit the Annual Report by February 1

By February 1, for the calendar year before.

Complete and submit DEQ's Annual Report Form for each calendar year of active coverage by February 1 of the next year, summarizing routine and significant storm inspections, corrective actions, noncompliance, monitoring results and SWPPP revisions, certified and signed by the permit signatory.

Further steps with their own deadlines:

  • Include a summary of SWPPP changes with each Annual Report. The permit gives the timing in words, quoted below. Section 3.3, page 35
    "the permittee must report a summary of any modifications or updates to the SWPPP (originally submitted with the NOI-SWI) with each required annual report."
  • You file it in the agency's system (FACTS (or mail to the DEQ Water Protection Bureau)).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.

Inferred from section 2.9.3. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.9.3, page 27
"The Annual Report for a given calendar year must be completed by February 1 of the year following that respective calendar year."
Open the permit at this section

Pay the annual fee

No set date. The due date is set by DEQ's fee notice under ARM 17.30.201, not by the permit.

Pay the annual permit fee set by ARM 17.30.201 for each calendar year of coverage. If it is not paid within 90 days after the due date, DEQ may add an assessment and suspend the authorization.

  • You file it in the agency's system (DEQ fee notice).
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 4.28, page 116
"The permittee is required to submit payment of an annual fee as set forth in ARM 17.30.201."
Open the permit at this section

Train employees once a year

Within 1 year after the last training.

Train employees who work where industrial materials or activities are exposed to stormwater, or who carry out permit duties (inspectors, maintenance staff, the stormwater pollution prevention team), on an annual basis, and keep a training log with the date, trainer, attendance and topics.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.

Inferred from section 2.2.8. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.2.8, page 14
"including the members of the storm water pollution prevention team, must receive appropriate training on an annual basis."
Open the permit at this section

One time 3 duties

Reapply at least 30 days before the permit expires

By January 1, 2028.

To keep discharging after the permit expires on January 31, 2028, apply for and obtain coverage under the new permit. Part 4.3 asks for the reapplication at least 30 days before expiry, which is January 1, 2028.

  • You file it in the agency's system (FACTS (or mail to the DEQ Water Protection Bureau)).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 4.3, page 111
"The reapplication must be submitted at least 30 days before the expiration date of this permit."
Open the permit at this section

Evaluate the site for non-stormwater discharges before applying

No set date. Before the application package is submitted (Part 2.2.9); no separate date.

Before submitting the application package, evaluate the site for non-stormwater discharges by testing stormwater or from knowledge of on-site activities, document the evaluation in the SWPPP, and eliminate any discharge the permit does not allow. Repeat the check during inspections.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.2.9, page 15
"The presence of non-storm water discharges must be evaluated prior to submitting an application package"
Open the permit at this section

Write the SWPPP before applying

No set date. Before authorization; the SWPPP is part of the application package (Parts 1.2 and 3.1).

Develop the Storm Water Pollution Prevention Plan (SWPPP) before authorization, prepared by a qualified person and signed by the permit signatory or a duly authorized representative. It goes in with the application package, and must be implemented and kept up to date once coverage starts.

  • You file it in the agency's system (FACTS, with the application package).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.1, page 28
"The SWPPP must be developed prior to authorization under this permit and implemented and maintained upon permit coverage."
Open the permit at this section

When something happens 16 duties

Anticipated bypass: give notice at least 10 days before

At least 10 days before the date of the bypass.

If a bypass of a treatment facility is known in advance, submit prior notice, if possible, at least ten days before the bypass. An unanticipated bypass is reported under the 24-hour rule.

  • When: you know in advance that a bypass of a treatment facility is needed.
  • You send it to the agency (DEQ Water Protection Bureau).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 4.26, page 116
"If the permittee knows in advance of the need for anticipated bypass, it shall submit prior notice, if possible, at least ten days before the date of the bypass."
Open the permit at this section

Change in size or outfalls: submit a modified application package

No set date. The permit sets no deadline for a modification request.

To modify an authorization, for example when the regulated facility grows or shrinks or outfalls are added or removed, submit a complete modified application package (NOI-SWI marked Modification, updated SWPPP, sage grouse letter if needed, fee). The permit sets no deadline.

  • When: the authorization needs a modification, for example a change in facility size or outfalls.
  • You file it in the agency's system (FACTS (or mail to the DEQ Water Protection Bureau)).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 1.2.3, page 8
"Permittees requiring a modification to their authorization under the 2023-2028 MSGP must submit a complete modified application package to the Department."
Open the permit at this section

Change of owner or name: submit the Permit Transfer Notification at least 30 days before

At least 30 days before the transfer takes effect.

To transfer ownership or change the name of the entity holding the authorization, submit DEQ's Permit Transfer Notification form (PTN-SWI) with the fee at least 30 days before the transfer takes effect, signed by both the existing and the new owner or operator.

  • When: the owner, or the name of the entity holding the authorization, changes.
  • You file it in the agency's system (FACTS (Permit Transfer Notification form)).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 1.4, page 9
"The PTN-SWI must be submitted at least 30 days before the effective date of the proposed transfer."
Open the permit at this section

Compliance schedule: report within 14 days after each schedule date

Within 14 days after each date in the compliance schedule.

Where DEQ sets a compliance schedule, report compliance or noncompliance with each interim and final requirement, or progress, no later than 14 days after each schedule date.

  • When: DEQ sets a compliance schedule for the facility.
  • You send it to the agency (DEQ Water Protection Bureau).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 4.22, page 115
"shall be submitted no later than 14 days following each schedule date."
Open the permit at this section

Corrective action: complete it within 14 days of discovery

Within 14 days after you discover the condition.

When a corrective action condition is found (an unauthorized release, controls not stringent enough for water quality standards, controls missing or not maintained, a DEQ finding, visual evidence of pollution, a change that adds pollutant sources, or a rolling benchmark average above a benchmark), complete the corrective actions before the next storm if possible and within 14 calendar days of discovery. The SWPPP Administrator oversees them.

Further steps with their own deadlines:

  • Take reasonable steps to minimize the discharge the same day. When you discover the condition. Section 2.7.3, page 25
    "The permittee must take these reasonable steps on the same day of the discovery or within 24 hours of making such discovery."
  • If 14 days is infeasible: finish no later than 45 days after discovery. Within 45 days after you discover the condition. Section 2.7.3, page 25
    "which must be done as soon as practicable after the 14-day timeframe but no longer than 45 days after discovery."
  • Document the condition and the first actions within 24 hours. Within 24 hours after you discover the condition. Section 2.7.3.4, page 26
    "Within 24 hours of discovery of any condition listed in Parts 2.7.1 and 2.7.2, the permittee must document the following information:"
  • Document the corrective action within 14 days. Within 14 days after you discover the condition. Section 2.7.3.4, page 26
    "Within 14 days of discovery of any condition listed in Parts 2.7.1 and 2.7.2 the permittee must document the following information:"
  • When: you find a condition that needs corrective action.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.7.3, page 25
"before the next storm event if possible, and within 14 calendar days from the time of discovery of the corrective action condition."
Open the permit at this section

Facility contact change: notify DEQ in writing within 15 days

Within 15 days after the change.

Notify DEQ in writing within 15 calendar days of any change to the designated facility contact person or position, mailing address or telephone number, and keep a copy at the site.

  • When: the facility contact person or position, mailing address or phone number changes.
  • You send it to the agency (DEQ Water Protection Bureau, in writing).
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.9.2, page 27
"The permittee must notify the Department in writing of any change of the designated facility contact person/position, mailing address, and/or telephone number within 15 calendar days of this change."
Open the permit at this section

Inspect within 72 hours after a significant storm or snowmelt

Within 72 hours after the rain or snowmelt event ends.

After a significant storm event (0.5 inches or more of rain in 24 hours, or thawing that causes visible snowmelt runoff on the site), inspect within 72 hours of the end of the event, record the rainfall and how it was measured, and document the inspection. Only two such inspections a month are required, on different days.

  • When: a significant storm occurs (0.5 inches or more of rain in 24 hours, or snowmelt with visible runoff).
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.4.4, page 18
"The significant storm event inspections must be conducted within 72 hours of the end of a rainfall or snowmelt event or in the timeframe specified in Part 3.4 for the sector or subsector."
Open the permit at this section

Missing or wrong facts in an application or report: submit them promptly

No set date. Promptly; the permit sets no number of days.

When the permittee learns that it left relevant facts out of an application package, or submitted incorrect information in an application or report, it submits the facts or information promptly.

  • When: you learn that an application or report left out relevant facts or gave incorrect information.
  • You send it to the agency (DEQ Water Protection Bureau).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 4.25, page 116
"it shall promptly submit such facts or information."
Open the permit at this section

New duly authorized representative: submit a new authorization first

No set date. Before or together with the next document the representative signs.

If the written authorization of a duly authorized representative is no longer accurate, submit a new one to DEQ before or together with any report, information or application that representative signs.

  • When: the written authorization of your duly authorized representative is no longer accurate.
  • You send it to the agency (DEQ Water Protection Bureau).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 4.18.2, page 114
"a new authorization satisfying the above requirements must be submitted to the Department prior to or together with any reports, information, or applications to be signed by an authorized representative."
Open the permit at this section

New facility: submit the application package at least 30 days before discharge begins

At least 30 days before discharge begins.

A facility not previously authorized under the MSGP submits the full application package (NOI-SWI form with attachments, SWPPP, sage grouse consultation letter if applicable, new permit fee) at least 30 days before discharge begins. Coverage starts on the date of DEQ's authorization letter, which the facility must have before discharging.

  • When: the facility will start a new discharge under this permit.
  • You file it in the agency's system (FACTS (or mail to the DEQ Water Protection Bureau)).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 1.2.1, page 7
"the permittee must submit the application package to the Department at least 30 days prior to commencing discharge."
Open the permit at this section

Other noncompliance: report as soon as possible

No set date. As soon as possible; the permit sets no number of days.

Report any other noncompliance as soon as possible, with the description, cause, period, expected duration and steps taken that a written 24-hour report would contain.

  • When: other noncompliance occurs.
  • You send it to the agency (DEQ Water Protection Bureau).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 4.24, page 116
"Instances of noncompliance not required to be reported within 24 hours shall be reported as soon as possible."
Open the permit at this section

Planned change that may cause noncompliance: notify by phone, then in writing within 5 days

Within 5 days after you become aware of the condition.

Give DEQ advance notice of any planned change that may cause noncompliance: by phone as soon as possible, then in writing within five days of becoming aware, describing the discharge, cause, period and steps to reduce and prevent it.

  • When: a planned change may cause noncompliance.
  • You send it to the agency (DEQ Water Protection Bureau).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 4.20, page 114
"The permittee shall notify as soon as possible by phone and provide with the following information, in writing, within five (5) days of becoming aware of such condition:"
Open the permit at this section

Planned physical changes: notify DEQ as soon as possible

No set date. As soon as possible; the permit sets no number of days.

Notify DEQ as soon as possible of planned physical alterations or additions that could make the facility a new source or could significantly change the nature or increase the quantity of pollutants discharged.

  • When: a physical alteration or addition to the facility is planned.
  • You send it to the agency (DEQ Water Protection Bureau).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 4.19, page 114
"The permittee shall give notice to the Department as soon as possible of any planned physical alterations or additions to the permitted facility, activity, or operation."
Open the permit at this section

Request termination within 30 days after a termination condition is met

Within 30 days after the termination condition is met.

When operations have ceased and all regulated discharges are eliminated (with erosion and sediment controls in place), when a Sector G, H or J site meets its sector termination conditions, or when all discharges are covered by another MPDES permit, submit the Notice of Termination (NOT-SWI) within 30 days. Coverage and annual fees continue until DEQ processes it.

  • When: operations have ceased, the site meets its sector's reclamation conditions, or another permit covers all discharges.
  • You file it in the agency's system (FACTS (NOT-SWI form)).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.

Inferred from section 1.5. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 1.5, page 9
"The permittee may request termination within 30 days after one or more of the following conditions have been met:"
Open the permit at this section

Serious noncompliance: report orally within 24 hours, in writing within 5 days

Within 24 hours after you become aware of the noncompliance.

Report orally within 24 hours of becoming aware any noncompliance that may seriously endanger health or the environment, any unanticipated bypass or upset exceeding an effluent limit, or a violation of a maximum daily limit DEQ lists, to the Water Protection Bureau or the Office of Disaster and Emergency Services. Follow with a written submission within five days.

Further steps with their own deadlines:

  • Written submission within five days. Within 5 days after you become aware of the noncompliance. Section 4.23, page 115
    "A written submission shall also be provided within five days of the time that the permittee becomes aware of the circumstances."
  • When: noncompliance occurs that may seriously endanger health or the environment, or a bypass or upset exceeds an effluent limit.
  • You send it to the agency (DEQ Water Protection Bureau (406) 444-5546 or Office of Disaster and Emergency Services (406) 324-4777 (Part 4.23.1)).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 4.23, page 115
"Any information must be provided orally within 24 hours from the time the permittee first becomes aware of the following circumstances:"
Open the permit at this section

Update the SWPPP within the corrective action deadlines

Within 14 days after you discover the condition.

Modify the SWPPP whenever needed to address a corrective action condition, within the Part 2.7.3 deadlines (14 days, at most 45), signed and dated by the SWPPP Administrator or permit signatory, and keep it up to date with current site conditions.

  • When: you find a condition that needs corrective action.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.

Inferred from section 3.2. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.2, page 34
"Changes to the SWPPP document must be made in accordance with the corrective action deadlines in Part 2.7.3"
Open the permit at this section

Ongoing 3 duties

Keep permit records at the site for three years

No set date. A standing duty; each record is kept for three years.

Keep at the site the permit, the NOI and correspondence, DEQ's letter, the current SWPPP and maps, BMP specifications, inspection and corrective action reports, Annual Reports, DMRs, noncompliance reports, contact change notices, training records and the sage grouse letter, available immediately on request, for three years.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.8, page 27
"These records are to be maintained by the permittee for a period of three years."
Open the permit at this section

Keep the current SWPPP at the facility, available at once on inspection

No set date. A standing duty while covered.

Keep a complete copy of the current SWPPP at the facility, immediately available to DEQ at an onsite inspection, and make it or parts of it available to the public (for example at a URL given in the NOI-SWI).

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.3, page 34
"Regardless of the format, the SWPPP must be immediately available to the Department, or an authorized representative at the time of an onsite inspection."
Open the permit at this section

Post a sign at the site entrance confirming coverage

No set date. A standing duty while covered; the permit sets no date.

Post a large, readable sign at the site entrance (or the most visible entrance), visible from the nearest road, with the MPDES authorization number, the permittee name, and the two statements the permit gives for requesting permit information and reporting pollution.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 1.3, page 9
"The permittee must post a sign to publicly display confirmation of coverage under the MSGP."
Open the permit at this section

Only if... 34 duties

These apply only in the situation named on each one. Answer the questions to sort them.

Sector E: sweep at least weekly where cement, aggregate or dust is handled

By the end of each week.

Where cement, aggregate, kiln dust, fly ash or settled dust is handled or processed, sweep paved exposed areas (or use an equivalent measure) at least once a week, with the frequency written in the SWPPP.

  • Only if: your permit sector is E; cement, aggregate, kiln dust, fly ash or settled dust is handled or processed.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.

Inferred from section 3.4.5.3.1. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.5.3.1, page 47
"it must be performed at least once a week if cement, aggregate, kiln dust, fly ash, or settled dust are being handled or processed."
Open the permit at this section

Sector L, operating sites outside arid climates: inspect every 7 days

By the end of each week.

Except in arid and semi-arid climates, inspect operating landfills, open dumps and land application sites at least once every 7 days, focusing on areas not finally stabilized, active application areas, exposed storage, controls, leachate systems and vehicle entrances and exits.

Further steps with their own deadlines:

  • Stabilized sites, completed land application areas, or arid and semi-arid climates: inspect monthly. By the end of each month. Section 3.4.12.6.1, page 71
    "For stabilized sites and areas where land application has been completed, or where the climate is arid or semi-arid, conduct inspections at least once every month."
  • Only if: your permit sector is L; the landfill, open dump or land application site is operating.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 3.4.12.6.1. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.12.6.1, page 71
"Except in arid and semi-arid climates, inspect operating landfills, open dumps, and land application sites at least once every 7 days."
Open the permit at this section

Sector A, wood surface protection or preserving: inspect treatment areas monthly

By the end of each month.

Facilities that protect or preserve wood surfaces inspect processing areas, transport areas and treated wood storage areas monthly to judge how well practices keep treatment chemicals off unprotected soils and areas that contact stormwater.

  • Only if: your permit sector is A; the facility protects or preserves wood surfaces.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 3.4.1. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.1, page 42
"If the facility performs wood surface protection and preservation activities, inspect processing areas, transport areas, and treated wood storage areas monthly"
Open the permit at this section

Sector G, discharging to outstanding or sediment- or nitrogen-impaired waters: inspect monthly

By the end of each month.

Metal mining sites are inspected at least quarterly unless adverse weather makes them inaccessible; sites that discharge to waters designated as outstanding, or impaired for sediment or nitrogen, are inspected monthly.

  • Only if: your permit sector is G; the site discharges to waters designated as outstanding, or impaired for sediment or nitrogen.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 3.4.7.6. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.7.6, page 54
"Sites which discharge to waters designated as outstanding waters or waters which are impaired for sediment or nitrogen must be inspected monthly."
Open the permit at this section

Sector J, discharging to outstanding or sediment- or nitrogen-impaired waters: inspect monthly

By the end of each month.

Mineral mining sites are inspected at least quarterly unless adverse weather makes them inaccessible; sites that discharge to waters designated as outstanding, or impaired for sediment or nitrogen, are inspected monthly.

  • Only if: your permit sector is J; the site discharges to waters designated as outstanding, or impaired for sediment or nitrogen.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 3.4.10.6. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.10.6, page 66
"Sites which discharge to waters which are designated as outstanding waters or waters which are impaired for sediment or nitrogen must be inspected monthly."
Open the permit at this section

Sector O: inspect coal, ash, fuel and storage areas monthly

By the end of each month.

As part of the routine inspection, steam electric facilities inspect monthly the coal handling, loading and unloading, switchyard, fueling, bulk storage, ash handling and maintenance areas, areas next to disposal ponds and landfills, liquid storage tanks and material storage areas.

  • Only if: your permit sector is O.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 3.4.15.6.1. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.15.6.1, page 80
"As part of the routine inspection, inspect the following areas monthly: coal handling areas, loading or unloading areas, switchyards, fueling areas, bulk storage areas, ash handling areas"
Open the permit at this section

Sector S: inspect monthly during the deicing season

By the end of each month.

Airports conduct routine facility inspections at least monthly during the deicing season (for example October through April), and in every month deicing chemicals may be used.

  • Only if: your permit sector is S; it is the deicing season, or a month in which deicing chemicals may be used.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 3.4.19.6.1. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.19.6.1, page 92
"At a minimum conduct routine facility inspections at least monthly during the deicing season (e.g., October through April for most mid-latitude airports)."
Open the permit at this section

Sector S: record deicing chemicals used each month

By the end of each month.

If deicing chemicals are used, keep a record of the types used (with their safety data sheets) and the monthly quantities, measured or estimated. Tenants that deice give this to the airport authority for the airport SWPPP.

  • Only if: your permit sector is S; the airport uses deicing chemicals.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.

Inferred from section 3.4.19.5.2. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.19.5.2, page 91
"If the permittee uses deicing chemicals, the permittee must maintain a record of the types (including the Material Safety Data Sheets [MSDS]) used and the monthly quantities"
Open the permit at this section

Sector V: inspect transfer lines, spill prevention and housekeeping monthly

By the end of each month.

Textile, apparel and leather product facilities inspect, at least monthly, transfer and transmission lines, spill prevention, good housekeeping, management of process waste products, and all structural and nonstructural management practices.

  • Only if: your permit sector is V.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 3.4.22. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.22, page 97
"Inspect, at least monthly, the following activities and areas (at a minimum): transfer and transmission lines, spill prevention, good housekeeping practices, management of process waste products, and all structural and nonstructural management practices."
Open the permit at this section

Benchmark subsectors: sample each outfall for the sector benchmarks each quarter

By the end of each calendar quarter, starting with the first full calendar quarter after your coverage begins.

Facilities in benchmark subsectors collect a grab sample from each monitored outfall each calendar quarter, within the first 30 minutes of a discharge from a storm event, starting the first full quarter after authorization, and analyze it for the Part 3.4 benchmark parameters of every sector at the site. Several samples in a quarter are averaged.

  • Only if: your permit subsector is A1, A2, A3, A4, B1, C1, C2, C3, C4, D1, E1, E2, F1, F2, F3, F4, G1, G2, H1, J1, J2, K1, L1, M1, N1, Q1, S1, U1, U2, Y1, AA1, AA2.
  • You file it in the agency's system (NetDMR).
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.5.5, page 21
"Monitoring requirements begin in the first full quarter following the effective date of the facility's authorization under this permit. Permittees with quarterly storm water monitoring must take samples at least once in each of the following three-month intervals:"
Open the permit at this section

Indicator subsectors: sample each outfall for pH, TSS and COD each quarter

By the end of each calendar quarter, starting with the first full calendar quarter after your coverage begins.

Facilities in indicator subsectors collect a grab sample from each monitored outfall each calendar quarter, within the first 30 minutes of a discharge from a storm event, starting the first full quarter of coverage, and report pH, total suspended solids and chemical oxygen demand. Results are report-only and have no threshold.

  • Only if: your permit subsector is B2, C5, D2, E3, F5, I1, J3, L2, N2, O1, P1, R1, T1, U3, V1, W1, X1, Y2, Z1, AB1, AC1, AD1.
  • You file it in the agency's system (NetDMR).
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.6.1, page 22
"The permittee must conduct indicator monitoring of stormwater discharges for pH, TSS, and COD each quarter, beginning in the first full quarter of permit coverage (Part 2.5.5)."
Open the permit at this section

Sector L, inactive sites: inspect each quarter

By the end of each calendar quarter.

Qualified personnel inspect inactive landfills, open dumps and land application sites at least quarterly: stabilization and structural erosion controls, leachate collection and treatment, and closed land application areas.

  • Only if: your permit sector is L; the landfill, open dump or land application site is inactive.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 3.4.12.6.2. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.12.6.2, page 71
"Inspect inactive landfills, open dumps, and land application sites at least quarterly."
Open the permit at this section

Sector M: inspect equipment and fluid storage for leaks each quarter

By the end of each calendar quarter.

Each quarter, inspect all equipment containing oily parts, hydraulic fluids, other fluids or mercury switches, and all vessels and areas storing hazardous materials and automotive fluids, for signs of leakage.

  • Only if: your permit sector is M.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by qualified personnel, as the permit defines them.

Inferred from section 3.4.13. Check your copy of the permit.

Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.13, page 72
"Inspect quarterly for signs of leakage all equipment containing oily parts, hydraulic fluids, any other types of fluids, or mercury switches."
Open the permit at this section

Hardness-dependent benchmarks: submit a receiving water hardness value

No set date. The permit names two times: with the application package (Part 2.6.2) and with the first benchmark report (Part 2.6.2 footnote 2, Part 3.5.1). Open question q6.

Facilities whose benchmarks include hardness-dependent metals determine the receiving water hardness (by their own grab sample, a group of dischargers, or third-party data under 10 years old, using 40 CFR Part 136 methods), document the method, and give DEQ the value. The benchmark for each metal is then read from the hardness table.

  • Only if: your permit subsector is A1, C1, C3, C4, F1, F2, F3, F4, G2, K1, M1, N1, Q1, Y1, AA1, AA2.
  • You file it in the agency's system (FACTS with the application package, or NetDMR with the first benchmark report).
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 2.6.2, page 23
"the permittee must include a hardness value in the application package, established consistent with the procedures in Part 3.5 that is representative of the receiving water."
Open the permit at this section

Sector A: benchmark values for timber products (Table 3.4.1-A)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each quarterly sample is compared with: A1 (COD, TSS, total zinc), A2 (total arsenic, total copper), A3 (TSS), A4 (COD, TSS). Zinc depends on receiving water hardness.

  • Only if: your permit sector is A.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.1, page 42
"Table 3.4.1-A identifies benchmarks that apply to the specific subsectors of Sector A. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector AA: benchmark values for fabricated metal products (Table 3.4.27-A)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each quarterly sample is compared with: AA1 (total aluminum, total zinc, nitrate plus nitrite nitrogen), AA2 (total zinc, nitrate plus nitrite nitrogen). Zinc depends on receiving water hardness.

  • Only if: your permit sector is AA.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.27, page 105
"Table 3.4.27-A identifies benchmarks that apply to the specific subsectors of Sector AA. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector AD: get DEQ's written permission before submitting the NOI

No set date. Before the NOI is submitted; the permit sets no number of days.

A facility designated by DEQ as needing a stormwater permit, or whose industrial activity fits no Sector A to AC, needs DEQ's written permission to use this permit before submitting an NOI. DEQ sets any added monitoring before authorizing it. Facilities cannot choose Sector AD themselves.

  • Only if: your permit sector is AD.
  • You send it to the agency (DEQ Water Protection Bureau).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.30.1.1, page 107
"the permittee must obtain the Department's written permission to use this permit prior to submitting an NOI."
Open the permit at this section

Sector B: benchmark value for paperboard mills (Table 3.4.2-B)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameter each quarterly sample is compared with: B1 (COD). B2 has indicator monitoring only.

  • Only if: your permit sector is B.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.2, page 43
"identifies benchmarks that apply to the specific subsectors of Sector B. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector C: benchmark values for chemicals and allied products (Table 3.4.3-B)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each quarterly sample is compared with: C1 (nitrate plus nitrite nitrogen, total lead, total iron, total zinc, phosphorus, total aluminum), C2 (total iron, nitrate plus nitrite nitrogen), C3 (nitrate plus nitrite nitrogen, total zinc), C4 (total zinc). Lead and zinc depend on receiving water hardness.

  • Only if: your permit sector is C.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.3, page 44
"Table 3.4.3-B identifies benchmarks that apply to the specific subsectors of Sector C. These benchmarks apply to the primary industrial activity at the site."
Open the permit at this section

Sector D: benchmark value for asphalt paving and roofing materials (Table 3.4.4-B)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameter each quarterly sample is compared with: D1 (TSS). D2 has indicator monitoring only.

  • Only if: your permit sector is D.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.4, page 46
"Table 3.4.4-B identifies benchmarks that apply to the specific subsectors of Sector D. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector E: benchmark values for clay and concrete products (Table 3.4.5-B)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each quarterly sample is compared with: E1 (total aluminum), E2 (TSS). E3 has indicator monitoring only.

  • Only if: your permit sector is E.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.5, page 47
"Table 3.4.5-B identifies benchmarks that apply to the specific subsectors of Sector E. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector F: benchmark values for primary metals (Table 3.4.6-B)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each quarterly sample is compared with: F1 (total aluminum, total zinc), F2 (total aluminum, TSS, total copper, total zinc), F3 (total copper, total zinc), F4 (total copper, total zinc). Zinc depends on receiving water hardness. F5 has indicator monitoring only.

  • Only if: your permit sector is F.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.6, page 49
"Table 3.4.6-B identifies benchmarks that apply to the specific subsectors of Sector F. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector G: benchmark values for metal mining (Tables 3.4.7-A and 3.4.7-B)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each sample is compared with: G1, active copper ore mining and dressing (TSS, nitrate plus nitrite nitrogen, COD); G2, waste rock and overburden piles at active metal mines (TSS, pH, hardness, total antimony, arsenic, beryllium, cadmium, copper, iron, lead, mercury, nickel, selenium, silver, zinc), plus the Table 3.4.7-C parameters for the type of ore mined. Cadmium, lead, nickel, silver and zinc depend on receiving water hardness.

Further steps with their own deadlines:

  • Waste rock and overburden piles: once in the first year, then twice a year for exceeded parameters. The permit gives the timing in words, quoted below. Section 3.4.7.7.2, page 54
    "perform the benchmark monitoring once in the first year for the parameters listed in Table 3.4.7-B, and twice annually in all subsequent years of coverage under this permit for any parameters for which the benchmark has been exceeded."
  • Only if: your permit sector is G.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.7.7.1, page 54
"Active copper ore mining and dressing facilities must sample and analyze storm water discharges for the pollutants listed in Table 3.4.7-A"
Open the permit at this section

Sector H: benchmark values for coal mines (Table 3.4.8-A)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each quarterly sample is compared with: H1 (total aluminum, TSS).

  • Only if: your permit sector is H.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.8, page 60
"Table 3.4.8-A identifies benchmarks that apply to the specific subsectors of Sector H. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector J: benchmark values for sand, gravel and stone (Table 3.4.10-B)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each quarterly sample is compared with: J1 (nitrate plus nitrite nitrogen, TSS), J2 (TSS). J3 has indicator monitoring only.

  • Only if: your permit sector is J.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.10, page 66
"Table 3.4.10-B identifies benchmarks that apply to the specific subsectors of Sector J. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector K: benchmark values for hazardous waste facilities (Table 3.4.11-A)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each quarterly sample is compared with, for discharges not subject to 40 CFR Part 445: K1 (ammonia, total magnesium, COD, total arsenic, cadmium, cyanide, lead, mercury, selenium, silver). Cadmium, lead and silver depend on receiving water hardness.

  • Only if: your permit sector is K.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.11, page 68
"Table 3.4.11-A identifies benchmarks that apply to the specific subsectors of Sector K. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector L: benchmark value for landfills and land application sites (Table 3.4.12-B)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameter each quarterly sample is compared with, for discharges not subject to 40 CFR Part 445 Subpart B: L1 (TSS). L2 has indicator monitoring only.

  • Only if: your permit sector is L.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.12, page 71
"Table 3.4.12-B identifies benchmarks that apply to the specific subsectors of Sector L. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector M: benchmark values for automobile salvage yards (Table 3.4.13-A)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each quarterly sample is compared with: M1 (TSS, total aluminum, total lead). Lead depends on receiving water hardness.

  • Only if: your permit sector is M.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.13, page 72
"Table 3.4.13-A identifies benchmarks that apply to the specific subsectors of Sector M. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector M: inspect arriving vehicles for leaks right away

When a vehicle arrives at the site.

Inspect vehicles arriving at the salvage yard for leaks immediately, or as soon as feasible.

  • Only if: your permit sector is M; a vehicle arrives at the salvage yard.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.13, page 72
"Immediately (or as soon as feasible) inspect vehicles arriving at the site for leaks."
Open the permit at this section

Sector N: benchmark values for scrap and waste recycling (Table 3.4.14-B)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each quarterly sample is compared with: N1 (COD, TSS, total aluminum, total recoverable copper, total lead, total recoverable zinc). Lead and zinc depend on receiving water hardness. N2 (source-separated recycling) has indicator monitoring only.

  • Only if: your permit sector is N.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.14, page 77
"Table 3.4.14-B identifies benchmarks that apply to the specific subsectors of Sector N. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector Q: benchmark values for water transportation (Table 3.4.17-A)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each quarterly sample is compared with: Q1 (total aluminum, total lead, total zinc). Lead and zinc depend on receiving water hardness.

  • Only if: your permit sector is Q.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.17, page 85
"Table 3.4.17-A identifies benchmarks that apply to the specific subsectors of Sector Q. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector S: benchmark values for airport deicing outfalls (Table 3.4.19-A)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters for airports that use more than 100,000 gallons of pure glycol or 100 tons or more of urea a year on average, sampled only at outfalls that collect stormwater from deicing areas and while deicing is occurring: S1 (TSS, COD, ammonia as N if urea is used, pH).

  • Only if: your permit sector is S.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.19, page 92
"Table 3.4.19-A identifies benchmarks that apply to the specific subsectors of Sector S. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector U: benchmark values for grain mills and fats and oils (Table 3.4.21-B)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameters each quarterly sample is compared with: U1 (TSS), U2 (BOD5, COD, nitrate plus nitrite nitrogen, TSS). U3 has indicator monitoring only.

  • Only if: your permit sector is U.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.21, page 96
"Table 3.4.21-B identifies benchmarks that apply to the specific subsectors of Sector U. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

Sector Y: benchmark value for rubber products (Table 3.4.25-B)

No set date. These are the values each sample is compared with; the schedule is in the quarterly benchmark monitoring duty.

Benchmark parameter each quarterly sample is compared with: Y1 (total zinc), which depends on receiving water hardness. Y2 has indicator monitoring only.

  • Only if: your permit sector is Y.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 3.4.25, page 101
"Table 3.4.25-B identifies benchmarks that apply to the specific subsectors of Sector Y. These benchmarks apply to the primary industrial activity which describes the site activities."
Open the permit at this section

What does no-exposure certification require?

Conditional Exclusion for No Exposure: an Industrial No Exposure Certification (MTR-NE) form and fee instead of MSGP coverage, recertified every five years.

Every few years 1 duty

No exposure: recertify every five years from the original certification letter

Within 5 years after the date of DEQ's original no exposure certification letter.

Recertify the no exposure exclusion once every five years from the date of DEQ's original certification letter by resubmitting the Industrial No Exposure Certification Form with the fee.

  • You file it in the agency's system (FACTS (MTR-NE form)).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 1.6, page 10
"The owner/operator must recertify the conditional exclusion for no exposure once every five years from the original Department issued certification letter date"
Open the permit at this section

One time 1 duty

No exposure: submit the Industrial No Exposure Certification

No set date. The permit sets no date for a first certification; the exclusion starts with DEQ's certification letter.

A facility whose industrial materials and activities are all protected by a storm-resistant shelter from rain, snow, snowmelt and runoff may submit an Industrial No Exposure Certification (MTR-NE) form and fee instead of obtaining MSGP coverage. The exclusion is facility-wide and applies only once DEQ issues a certification letter.

  • You file it in the agency's system (FACTS (MTR-NE form)).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 1.6, page 10
"Discharges composed entirely of storm water due to no exposure may submit an Industrial No Exposure Certification (MTR-NE) form instead of obtaining coverage under the MSGP."
Open the permit at this section

When something happens 1 duty

No exposure lost: apply for MSGP coverage

No set date. The permit sets no number of days; discharges need coverage before they occur (Part 1.2).

If pollutants at a facility with an MTR-NE become potentially exposed to stormwater, the no exposure condition is no longer valid and the facility must apply for and obtain MSGP coverage or an individual MPDES permit. The permit sets no number of days.

  • When: pollutants at the facility become exposed to stormwater.
  • You file it in the agency's system (FACTS (or mail to the DEQ Water Protection Bureau)).
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: MPDES Multi-Sector General Permit MTR000000 (2023-2028), 122 pages, section 1.6, page 10
"If a facility with coverage under a MTR-NE has pollutants potentially exposed to storm water, then the condition of no exposure is not valid"
Open the permit at this section

Get your own dates

Choose your coverage and answer a few questions. You get each duty's next date and a calendar file.

Montana Multi-Sector General Permit (MSGP) MTR000000 duties, topic by topic

How the Montana Multi-Sector General Permit (MSGP) MTR000000 compares with the other checked permits on each kind of duty, in the permit's own words with the section for each: