Quarterly visual monitoring of a storm discharge at each outfall
By the end of each calendar quarter.
In each calendar quarter, look at a sample of stormwater discharge from each outfall during a qualifying storm event, taken in the first 30 minutes of discharge (or as soon as practical, within one hour), and record it on the Department's Quarterly Visual Monitoring form kept with the SWPPP. No lab analysis is needed. If no qualifying storm produced runoff in the quarter, document that in the SWPPP.
Further steps with their own deadlines:
-
Repeat the visual check after a corrective action.
The permit gives the timing in words, quoted below.
Section IV.E.5, page 32
"An additional visual inspection must be performed ... during a qualifying storm event following the implementation of the corrective action."
- Nothing is filed; keep the record at the facility.
- Keep the records 5 years.
- The permit says this is done by qualified personnel, as the permit defines them.
Source: SPDES Multi-Sector General Permit for Stormwater Discharges Associated with Industrial Activity, GP-0-23-001 (March 8, 2023), section IV.E.1, page 32
"The monitoring must be made at least once in each of the following quarters:"Open the permit at this section