Minnesota Industrial Stormwater MSGP due dates and duties

Every duty in the Authorization to Discharge Stormwater Associated with Industrial Activity Under the NPDES/SDS Program (Industrial Stormwater Multi-Sector General Permit), with when it is due and the section it comes from.

Get my permit calendar

Free, no account. Your own dates in a minute.

  • 76duties, each cited
  • 12on a schedule
  • 64when something happens

Set up your facility free to date the ones that count from your own records, such as your last training.

StormDue reminds and keeps records. It does not file anything with the agency and does not certify or guarantee compliance. Check each duty against your permit; you are responsible for your filings.

What is this permit, and where do I file?

Permit number
MNR050000
In force
June 1, 2025 to March 31, 2030
Official page
pca.state.mn.us
Rules last checked
November 27, 2026
Today
June 1, 2025 March 31, 2030
Notes on the permit's status and renewal

The permit was issued and took effect June 1, 2025 and expires at midnight March 31, 2030 (cover page). It replaced the 2020 permit, which expired March 31, 2025. The MPCA's e-Services application for the new permit was not available until August 2026 (MPCA bulletins of May 7 and May 21, 2025, October 2, 2025 and January 5, 2026 said so and told permittees to keep complying with their existing permit). A law firm summary of the MPCA's August 19, 2026 announcement reports that coverage under the 2020 permit expired September 30, 2026; an MPCA bulletin of October 28, 2026 set October 31, 2026 as the deadline for existing facilities to apply for this permit or a No Exposure certification. A facility's duties under this pack start from the issuance date on its own notice of coverage. No modification or extension of the permit was found on November 27, 2026. Industrial stormwater permit IDs start with MNR053 and No Exposure IDs with MNRNE.

What does full permit coverage require?

Permit coverage by application in MPCA e-Services, with the fee and a completed SWPPP; discharge is authorized from the issuance date on the notice of coverage.

Every month 1 duty

Inspect the facility every calendar month it is active and staffed

By the end of each month.

Inspect the facility at least once each calendar month it is active and staffed: storage tank, waste, maintenance, loading and storage areas, every BMP, and any newly exposed materials. Record date, time, weather, inspector, findings and corrective actions with the SWPPP.

  • Does not apply if: the facility is inactive and unstaffed.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 19.2, page 8
"the Permittee shall develop and implement an inspection schedule that includes a minimum of one facility inspection per calendar month that the facility is active and staffed."
Open the permit at this section

Every quarter 2 duties

Report benchmark monitoring by the 21st day after each quarter

By April 21 (Q1), July 21 (Q2), October 21 (Q3) and January 21 (Q4), starting with the first full calendar quarter after your coverage begins. Only in coverage years 1, counted from when your coverage began.

Submit the quarter's monitoring data in e-Services by the 21st day of the month after each sampling quarter: April 21, July 21, October 21 and January 21. A report is due even when no sample could be taken, with the reason.

  • Does not apply if: the facility is inactive and unstaffed.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 50.3, page 16
"The Permittee shall submit monitoring data to the MPCA no later than the 21st day of the month following the sampling quarter."
Open the permit at this section

Sample each benchmark monitoring location once a quarter for four quarters

By the end of each calendar quarter, starting with the first full calendar quarter after your coverage begins. Only in coverage years 1, counted from when your coverage began.

Collect at least one sample per calendar quarter from each benchmark monitoring location, for at least four quarters starting with the first full quarter after the coverage issuance date, from a measurable runoff event, within the first 30 minutes of discharge if possible. Average the four quarters for each parameter and compare with the benchmark value.

  • Does not apply if: the facility is inactive and unstaffed.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
  • The permit says this is done by an accredited laboratory.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 41.2, page 14
"Permittees shall collect at least one sample per quarter from each benchmark monitoring location and analyze each sample for the sector-specific benchmark parameters."
Open the permit at this section

Every year 4 duties

Make one monthly inspection each year during a rain or snowmelt runoff event

By December 31 each year.

At least one of the monthly inspections each calendar year must happen during a rain or snowmelt runoff event and check the runoff for discoloration or visible contaminants such as oil and grease.

  • Does not apply if: the facility is inactive and unstaffed.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 19.2, page 8
"the Permittee shall conduct a minimum of one of these inspections per calendar year during a rain or snowmelt runoff event."
Open the permit at this section

Submit the Annual Report by March 31

By March 31, for the calendar year before.

By March 31 each year, submit through e-Services an Annual Report for the parts of the previous calendar year the facility was covered: inspection dates and findings, oil and grease inspection results, SWPPP and impaired waters confirmations, SWPPP changes, spills and leaks, and mobile activities.

  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 38.2, page 13
"Permittees shall submit an annual report: Due annually, by the 31st of March."
Open the permit at this section

Review the SWPPP at least once a year

Within 1 year after the last SWPPP review.

Review the SWPPP at least annually. The pack shows the review one year after the last one.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.

Inferred from section 36.2. Check your copy of the permit.

Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 36.2, page 12
"The Permittee shall review the SWPPP at least annually."
Open the permit at this section

Train employees at least once a year

Within 1 year after the last training.

Run a training program on stormwater controls, the SWPPP, monitoring and permit requirements for the staff who write the SWPPP, maintain BMPs, work in industrial areas, monitor discharges or do winter maintenance, before they take on those duties and at least annually. Keep training records for three years.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.

Inferred from section 26.2. Check your copy of the permit.

Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 26.2, page 10
"The program must include a training schedule that includes training at least annually."
Open the permit at this section

One time 3 duties

Apply to continue coverage at least 180 days before the permit expires

By October 2, 2029.

To keep coverage past March 31, 2030, submit an application for permit reissuance at least 180 days before that date. A timely application lets the facility keep operating under this permit until the MPCA acts on it.

  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 5.4, page 4
"To continue permit coverage beyond the date of permit expiration, Permittees shall submit an application for permit reissuance: Due by 180 days prior to permit expiration."
Open the permit at this section

Install structural BMPs within 12 months of authorization

Within 1 year after you are authorized to discharge under this permit.

Put non-structural BMPs in place immediately and structural BMPs within 12 months of receiving authorization to discharge under this permit.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 12.2, page 6
"The Permittee shall implement all non-structural BMPs immediately and all structural BMPs within 12 months of receiving authorization to discharge industrial stormwater under this permit."
Open the permit at this section

Write and keep the SWPPP before applying

No set date. Completed before the permit application; the permit sets no other date.

Develop, implement and maintain a Stormwater Pollution Prevention Plan for the facility, finished before the permit application. It covers the facility description and map, activities and materials, BMPs for each control measure, inspections, maintenance, training, spill response and any sector-specific items.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 28.2.B, page 10
"The Permittee shall complete a SWPPP prior to submitting the permit application."
Open the permit at this section

When something happens 17 duties

Keep sampling quarterly while a four-quarter average is at or above the benchmark

By the end of each calendar quarter.

When the average of the four most recent quarters is at or above a benchmark value, keep sampling that location each quarter and recompute the average until it falls below the value. Report each quarter by the 21st of the following month.

  • When: the benchmark average is at or above the value.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 49.2, page 15
"The Permittee shall continue quarterly monitoring at the benchmark monitoring location until the average of the four most recent samples is below the applicable benchmark monitoring value."
Open the permit at this section

After a benchmark exceedance: update the SWPPP and BMPs within 14 days

Within 14 days after you discover a benchmark exceedance.

After discovering a benchmark exceedance, modify the SWPPP, document corrective actions and start upgrading BMPs immediately and within 14 days. A new or repaired control must be working as soon as possible; if it cannot be done in 14 days, document why, set a schedule and finish within 45 days.

Further steps with their own deadlines:

  • Finish the BMP installation or repair. Within 45 days after you discover a benchmark exceedance. Section 49.3.C.iii, page 16
    "Install or repair the BMP as soon as practicable, but no longer than 45 days after discovery"
  • When: a benchmark is exceeded.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 49.3.B, page 15
"Initiate modifications and upgrade the SWPPP and BMPs immediately, but no later than 14 days beyond discovery of a benchmark value exceedance"
Open the permit at this section

Apply for permit coverage, with the fee and a completed SWPPP, before discharging

No set date. The permit sets no lead time. Coverage starts on the issuance date printed on the MPCA notice of coverage (section 5.3).

A facility with industrial stormwater needs coverage or a No Exposure certification. Complete the SWPPP first, then submit the application and fee on the MPCA's form and certify that the SWPPP is done. Discharge is authorized from the issuance date on the notice of coverage.

  • When: the facility is not yet covered under the 2025 permit.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 4.2.C, page 4
"Submit a complete and accurate permit application with appropriate fee, on a form the MPCA provides, and certify that the applicant has completed a SWPPP"
Open the permit at this section

Correct an incomplete or incorrect monitoring report immediately

No set date. Immediately.

When the facility finds, or the MPCA says, that a submitted monitoring report is incomplete or incorrect, submit an amended report immediately with the corrected data and a cover letter explaining what happened.

  • When: you find a report was incomplete or incorrect.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 50.4, page 16
"the Permittee shall immediately submit an amended report to the MPCA."
Open the permit at this section

Give the MPCA the SWPPP within 72 hours of a request

Within 72 hours after the MPCA asks for it.

Keep the SWPPP at the facility and make it available to the MPCA within 72 hours of a request. Design records for benchmark monitoring waivers for infiltration systems and ponds have the same 72-hour rule (59.2, 63.2).

  • When: the MPCA asks for the SWPPP.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 37.2, page 13
"Permittees shall keep the SWPPP at the industrial facility and make it available to the MPCA within 72 hours of a request for review."
Open the permit at this section

Inspect a new infiltration system or pond after every rain for 30 days

No set date. After each precipitation event during the first 30 days of operation.

For a newly built or upgraded infiltration system or industrial stormwater pond, inspect it visually after all precipitation events for the first 30 days of operation, then with the regular inspections.

  • When: an infiltration system or pond is built or upgraded.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 58.3, page 18
"The Permittee shall visually inspect all newly constructed or up-graded infiltration systems after all precipitation events for 30 days after initiation of operation"
Open the permit at this section

New owner or operator: apply for the permit transfer on or before the date of the change

Before the change takes effect.

When ownership or operational control changes, the new owner or operator signs, certifies and submits the transfer application to the MPCA on or before the effective date of the change.

  • When: ownership or control changes.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 7.2, page 5
"The new Owner/Operator shall sign, certify, and submit the application to the MPCA on or before the effective date of the change."
Open the permit at this section

Remove materials tracked off-site within one day

Within 1 day after you discover the problem.

Where vehicles track significant materials off-site, remove and properly dispose of them within one day of discovery.

  • When: significant material is tracked off site.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 13.2.C, page 6
"the Permittee shall remove and properly dispose of significant materials that have been tracked off-site within one day of discovery."
Open the permit at this section

Repair or replace a failed BMP within seven days

Within 7 days after you discover the problem.

Replace, maintain or repair a BMP that is not working within seven calendar days of discovery. If that is not possible, put effective backup BMPs in place within 48 hours and document why the repair takes longer.

Further steps with their own deadlines:

  • Install backup BMPs if the repair takes longer than seven days. Within 48 hours after you discover the problem. Section 21.2, page 8
    "the Permittee shall implement effective backup BMPs within 48 hours of discovery"
  • When: a BMP is not working.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 21.2, page 8
"the Permittee shall replace, maintain, or repair the BMPs within seven calendar days of discovery."
Open the permit at this section

Report a spill to the Minnesota Duty Officer immediately

No set date. Immediately.

When a spill or discharge of a potentially polluting material occurs, call the Minnesota Department of Public Safety Duty Officer immediately. Any use or release of PFAS-containing foam is also reported immediately.

  • When: potentially polluting material is spilled.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 24.2.E, page 9
"When a spill or discharge of a potentially polluting material occurs, the Permittee shall immediately notify the Minnesota Department of Public Safety Duty Officer"
Open the permit at this section

Restart benchmark monitoring after a new impairment listing nearby

No set date. Before the first full calendar quarter after EPA approves the listing; the product does not count quarters from a listing date.

If EPA approves a new impairment of a water within one mile that receives the discharge, and the pollutant or its surrogate is a benchmark parameter for the sector, submit an administrative modification before the next full calendar quarter and restart monitoring for that pollutant.

  • When: a water within one mile is newly listed as impaired.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 47.3, page 15
"Prior to the first full calendar quarter following the US EPA-approved listing of the impaired water, the Permittee shall submit an administrative modification application to restart benchmark monitoring."
Open the permit at this section

Send the MPCA a plan within a year if ponds or infiltration spread contamination

Within 1 year after you are authorized under the permit, or you later find the problem.

If industrial stormwater ponds or infiltration systems contribute to contaminant increases or movement, submit a plan to reduce contaminants or redesign, relocate or eliminate them, within one year of authorization or of discovery, and carry it out once the MPCA approves.

  • When: ponds or infiltration contribute to contamination.
  • You send it to the agency (MPCA (the permit names no channel)).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 18.6, page 7
"The Permittee shall submit the plan to the MPCA within one year of the Permittee's authorization to discharge under this permit or within one year of discovery"
Open the permit at this section

Submit a Notice of Termination within 30 days when coverage should end

Within 30 days after a condition for ending coverage is met.

Within 30 days after the facility stops the regulated industrial activity and eliminates contact of stormwater with significant materials, or obtains an individual or industry- specific permit for its stormwater, sign and submit a Notice of Termination. The permit applies until the MPCA confirms termination.

  • When: a condition for ending coverage is met.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 8.2, page 5
"The Permittee shall sign and submit a Notice of Termination request within 30 days after one or more of the following conditions are met:"
Open the permit at this section

Submit an administrative modification when facility details change

No set date. The permit sets no deadline for an administrative modification.

Submit an administrative modification to update the facility name, the description of business activity, contact information or industrial acreage, to discharge to a newly impaired water, or when ownership changes.

  • When: the facility's details change.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 5.6, page 5
"Permittees of existing facilities with coverage under the Industrial Stormwater General Permit shall submit an administrative modification to the permit if they need to:"
Open the permit at this section

Tell the MS4 operator within 30 days of receiving the notice of coverage

Within 30 days after you receive the notice of coverage.

If the facility discharges directly into a regulated municipal separate storm sewer system, notify the MS4 operator that it discharges industrial stormwater into its system within 30 days of receiving the notice of coverage, and keep a record of the notice.

  • When: the facility discharges directly into a regulated MS4.
  • You send a copy to the operator of your storm sewer system (MS4).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 6.2, page 5
"the Permittee shall notify the MS4 operator that they are discharging industrial stormwater into their storm sewer system within 30 days of receiving a notice of coverage"
Open the permit at this section

Update the SWPPP within 30 days after a listed change

Within 30 days after a change listed in section 36.2 happens.

Modify the SWPPP within 30 days after construction or a change affecting stormwater, finding a monitoring location within one mile of an impaired water, an inspection that finds deficiencies, a need for more BMPs to meet standards or benchmarks, an unauthorized discharge, or a change in responsible personnel.

  • When: something happens that requires a SWPPP change.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 36.2, page 12
"The Permittee shall modify the SWPPP within 30 days if:"
Open the permit at this section

Write a Mercury Minimization Plan if mercury sources are exposed

No set date. The permit sets no date.

Evaluate the facility for mercury sources that stormwater could contact; if any are exposed, write a Mercury Minimization Plan describing how they will be kept out of precipitation and runoff. Sector M and N vehicle recyclers have added mercury switch rules (198.2, 212.2).

  • When: mercury sources are exposed to stormwater.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 25.2, page 10
"If mercury sources are exposed to stormwater, the Permittee shall develop a Mercury Minimization Plan"
Open the permit at this section

Ongoing 2 duties

Keep a spill prevention and response plan

No set date. A standing duty with no date.

Develop and implement a spill prevention and response plan covering where materials are stored and handled, affected areas and waters, reporting, cleanup procedures and contacts. An existing SPCC or Chapter 115E plan may be incorporated by reference. Infiltration may not be part of spill containment.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 24.2, page 9
"The Permittee shall develop and implement a spill prevention and response plan."
Open the permit at this section

Keep permit records and monitoring records for three years

No set date. A standing duty with no date.

Keep copies of the application, the information used for it, and all data and records related to the permit for at least three years, and monitoring records (place, date and time, analysis date, who sampled and analyzed, methods, results) for at least three years. The period extends during an unresolved enforcement action or on MPCA request.

  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 369.4, page 59
"The Permittee shall keep all monitoring records for at least three years, including any calculations, original recordings from automatic monitoring devices, and laboratory sheets."
Open the permit at this section

Only if... 44 duties

These apply only in the situation named on each one. Answer the questions to sort them.

Sector C: inspect milling areas every week

By the end of each week.

Chemical and allied products facilities with milling areas (for example ethanol plants) inspect the milling areas and their BMPs at least weekly, and clean up spilled organic product daily.

  • Only if: your permit sector is C; the facility has milling areas.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 89.2, page 23
"The facility milling areas and related BMPs shall be inspected at least weekly."
Open the permit at this section

Sector E: sweep paved areas every week when handling cement, aggregate or dust

By the end of each week.

Facilities handling or processing cement, aggregate, kiln dust, fly ash or settled dust sweep (or equivalent) paved areas exposed to stormwater at least once a week.

  • Only if: your permit sector is E; the facility handles cement, aggregate, kiln dust, fly ash or settled dust.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 103.2, page 24
"the Permittee shall perform this action least once per week if the Permittee is handling or processing cement, aggregate, kiln dust, fly ash, or settled dust."
Open the permit at this section

Sample each effluent monitoring location twice a year, 30 days apart

By December 31 each year, 2 times; at least 30 days apart.

Facilities with an activity that has a numeric effluent limit (Subsectors A4, C1, D2, E3, K2, L3, O3 and S3) collect two samples each calendar year, at least 30 days apart, from each effluent monitoring location, within the first 30 minutes of a measurable runoff event where possible. A result above a limit is a permit violation.

  • Only if: your discharge is subject to federal effluent limitation guidelines (ELGs).
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
  • The permit says this is done by an accredited laboratory.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 65.3, page 19
"Permittees shall collect two samples annually, at least 30 days apart, from each effluent monitoring location and analyze the sample for each required effluent limit parameter."
Open the permit at this section

Sector H: quarterly inspections of SMCRA mining-related areas

By the end of each calendar quarter.

For active coal mining-related areas and inactive areas under SMCRA bond authority, inspect all mining-related areas each quarter, at the same time as the SMCRA inspector's inspections, and keep the SMCRA inspector's records.

  • Only if: your permit sector is H; the site has areas under SMCRA authority.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.

Inferred from section 139.3. Check your copy of the permit.

Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 139.3, page 30
"For active mining-related areas and inactive areas under SMCRA Bond Authority, the Permittee shall perform quarterly inspections, corresponding with the inspections performed by SMCRA inspectors"
Open the permit at this section

Sectors with oil and grease checks: two runoff-event inspections a year

By December 31 each year, 2 times.

In Sectors C, D, F, H, I, M, N, O, P, Q, R, S, U, V, AA and AB, two of the monthly inspections must occur during runoff events, at least one during snowmelt if possible, each with a visual check for sheens or films of oil or grease; sheens need corrective action documented in the SWPPP.

  • Only if: your permit sector is C, D, F, H, I, M, N, O, P, Q, R, S, U, V, AA, AB.
  • Does not apply if: the facility is inactive and unstaffed.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.

Inferred from section 89.3. Check your copy of the permit.

Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 89.3, page 23
"the Permittee shall ensure that a total of two monthly inspections occur during runoff events, with at least one inspection occurring during a snowmelt runoff event if possible."
Open the permit at this section

Report effluent monitoring by January 21

By January 21, for the calendar year before.

Submit the effluent monitoring report in e-Services no later than 21 days after the end of each calendar year, for every effluent monitoring location, even if no discharge occurred.

  • Only if: your discharge is subject to federal effluent limitation guidelines (ELGs).
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 67.4, page 20
"The Permittee shall submit the annual monitoring report no later than 21 days after the end of each calendar year following issuance of ISW permit coverage."
Open the permit at this section

After an effluent limit violation: update the SWPPP and BMPs within 14 days

Within 14 days after you discover an effluent limit violation.

A result above an effluent limit is a violation. Verify it with more samples, investigate, modify the SWPPP and start upgrading BMPs within 14 days of discovery, finish controls within 45 days, re-sample within 30 days of the corrective actions, and keep monitoring monthly until results meet the limit.

Further steps with their own deadlines:

  • Finish the control measure work. Within 45 days after you discover an effluent limit violation. Section 66.4.C.ii, page 20
    "as soon as practicable after the 14-day timeframe but no longer than 45 days after discovery"
  • Follow-up monitoring after the corrective actions. Within 30 days after the corrective actions are in place. Section 66.3, page 20
    "conduct follow-up monitoring within 30 calendar days (or during the next qualifying runoff event, should none occur within 30 days) of implementing the corrective actions"
  • Monitor monthly until the discharge complies. The permit gives the timing in words, quoted below. Section 66.5, page 20
    "Additional effluent monitoring must be conducted monthly, at a minimum, until the discharge is in compliance with the effluent limit"
  • Only if: your discharge is subject to federal effluent limitation guidelines (ELGs); an effluent limit is exceeded.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 66.4.B, page 20
"Initiate modifications and upgrade the SWPPP and BMPs immediately, but no later than 14 days beyond discovery of an effluent limit violation"
Open the permit at this section

Discharges near impaired or special waters: added BMPs and a 65 mg/L TSS benchmark

No set date. A standing duty with no date.

Where a monitoring location discharges to an impaired water, or to a special water such as a trout stream or lake, within one mile, document BMPs that restrict the discharge in the SWPPP. Where TSS is a sector benchmark and the water is impaired for TSS or a surrogate, the TSS benchmark is 65 mg/L instead of 100 mg/L.

  • Only if: your stormwater reaches an impaired water body.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 378.4, page 60
"A benchmark monitoring value of 65 mg/L for Total Suspended (TSS) applies to the discharge at a benchmark monitoring location, instead of 100 mg/L"
Open the permit at this section

PFAS sectors: complete a Source and Exposure Reduction Plan within 180 days if a threshold is exceeded

Within 180 days after the final PFAS sample.

If the average of the four quarterly PFAS results is above a threshold, complete and begin implementing a PFAS Source and Exposure Reduction Plan on the MPCA template within 180 days of the final sampling quarter, review it every year and submit it with the Annual Report.

  • Only if: your SIC code starts with 2621, 2656, 2671, 2672, 2673, 2821, 2824, 2842, 2844, 2851, 2899, 2952, 2992, 3399, 2911, 5093, 4581, 2221, 2262, 2273, 2295, 2297, 2299, 2385, 3131, 3161, 3172, 3199, 2752, 2796, 3069, 3081, 3082, 3083, 3111, 3471, 3497, 3567, 3589, 3599, 3674, 3695, 3841, 3861; the PFAS average is above the threshold.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.

Inferred from section 396.2. Check your copy of the permit.

Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 396.2, page 64
"The Permittee, if required, shall complete and begin implementing a PFAS source and exposure reduction plan (SERP) within 180 days of its final sampling quarter."
Open the permit at this section

PFAS sectors: report PFAS results by the 21st day after each quarter

By April 21 (Q1), July 21 (Q2), October 21 (Q3) and January 21 (Q4), starting with the first full calendar quarter after your coverage begins. Only in coverage years 1, counted from when your coverage began.

Submit a quarterly PFAS Stormwater Monitoring Report by the 21st day of the month after each sampling quarter, even when no runoff or snow sample could be collected, with the reason.

  • Only if: your SIC code starts with 2621, 2656, 2671, 2672, 2673, 2821, 2824, 2842, 2844, 2851, 2899, 2952, 2992, 3399, 2911, 5093, 4581, 2221, 2262, 2273, 2295, 2297, 2299, 2385, 3131, 3161, 3172, 3199, 2752, 2796, 3069, 3081, 3082, 3083, 3111, 3471, 3497, 3567, 3589, 3599, 3674, 3695, 3841, 3861.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 391.2, page 63
"The Permittee must submit PFAS monitoring data to the MPCA no later than the 21st day of the month following the sampling quarter."
Open the permit at this section

PFAS sectors: sample each area of concern once a quarter for four quarters

By the end of each calendar quarter, starting with the first full calendar quarter after your coverage begins. Only in coverage years 1, counted from when your coverage began.

Collect a PFAS stormwater sample from each area of concern in at least four calendar quarters, starting with the first full quarter after the coverage issuance date, from a measurable runoff event (or an acceptable snow sample), analyzed by EPA Method 1633.

  • Only if: your SIC code starts with 2621, 2656, 2671, 2672, 2673, 2821, 2824, 2842, 2844, 2851, 2899, 2952, 2992, 3399, 2911, 5093, 4581, 2221, 2262, 2273, 2295, 2297, 2299, 2385, 3131, 3161, 3172, 3199, 2752, 2796, 3069, 3081, 3082, 3083, 3111, 3471, 3497, 3567, 3589, 3599, 3674, 3695, 3841, 3861.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
  • The permit says this is done by an accredited laboratory.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 388.3, page 62
"PFAS Stormwater samples must be collected for at least four calendar quarters. Sampling requirements begin the first full calendar quarter following the facility's coverage issuance date."
Open the permit at this section

PFAS sectors: write the PFAS Stormwater Monitoring Plan and update it every year

Within 1 year after the last PFAS plan review.

A facility whose primary SIC code is in Appendix D develops and implements a PFAS Stormwater Monitoring Plan describing its areas of concern, monitoring locations and materials, with a map, kept in the SWPPP, reviewed and updated annually. The pack shows the update one year after the last one.

  • Only if: your SIC code starts with 2621, 2656, 2671, 2672, 2673, 2821, 2824, 2842, 2844, 2851, 2899, 2952, 2992, 3399, 2911, 5093, 4581, 2221, 2262, 2273, 2295, 2297, 2299, 2385, 3131, 3161, 3172, 3199, 2752, 2796, 3069, 3081, 3082, 3083, 3111, 3471, 3497, 3567, 3589, 3599, 3674, 3695, 3841, 3861.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.

Inferred from section 387.2. Check your copy of the permit.

Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 387.2, page 62
"The Permittee must develop and implement a PFAS Stormwater Monitoring Plan for its facility, which must be reviewed and updated annually."
Open the permit at this section

Sector A: benchmark values for timber products

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table A-1 of Appendix B, by subsector: A1 (general sawmills and planing mills), A2 (wood preserving), A3 (log storage and handling), A5 (hardwood dimension and flooring mills). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is A.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 76.2, page 21
"applicable parameters in Table A-1 in Appendix B"
Open the permit at this section

Sector AA: benchmark values for fabricated metal products

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table AA-1 of Appendix B, by subsector: AA1 (fabricated metal products), AA2 (fabricated metal coating and engraving). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is AA.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 343.2, page 57
"applicable parameters in Table AA-1 in Appendix B"
Open the permit at this section

Sector AB: benchmark values for transportation equipment and industrial or commercial machinery

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table AB-1 of Appendix B, by subsector: AB1 (transportation equipment and industrial or commercial machinery). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is AB.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 350.2, page 57
"applicable parameters in Table AB-1 in Appendix B"
Open the permit at this section

Sector AC: benchmark values for electronic and electrical equipment and components, photographic and optical goods

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table AC-1 of Appendix B, by subsector: AC1 (electronic, electrical, photographic and optical goods), AC2 (electronic and electrical equipment and components, except computers). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is AC.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 355.2, page 58
"applicable parameters in Table AC-1 in Appendix B"
Open the permit at this section

Sector B: benchmark values for paper and allied products manufacturing

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table B-1 of Appendix B, by subsector: B1 (pulp, paper and paperboard products). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is B.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 82.2, page 22
"applicable parameters in Table B-1 in Appendix B"
Open the permit at this section

Sector C: benchmark values for chemical and allied products manufacturing

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table C-1 of Appendix B, by subsector: C2 (agricultural chemicals), C3 (industrial inorganic chemicals), C4 (soaps, detergents, cosmetics and perfumes), C5 (plastics, synthetics and resins), C6 (medicinal chemicals and botanical products), C7 (ethanol facilities). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is C.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 91.2, page 23
"applicable parameters in Table C-1 in Appendix B"
Open the permit at this section

Sector D: benchmark values for asphalt paving and roofing materials and lubricant manufacturing

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table D-1 of Appendix B, by subsector: D1 (asphalt paving and roofing materials), D3 (miscellaneous products of petroleum and coal). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is D.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 98.2, page 24
"applicable parameters in Table D-1 in Appendix B"
Open the permit at this section

Sector E: benchmark values for glass, clay, cement, concrete, and gypsum products

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table E-1 of Appendix B, by subsector: E1 (clay products), E2 (concrete and gypsum products), E4 (glass, stone, abrasive and asbestos products). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is E.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 107.2, page 24
"applicable parameters in Table E-1 in Appendix B"
Open the permit at this section

Sector F: benchmark values for primary metals

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table F-1 of Appendix B, by subsector: F1 (steel works, blast furnaces, rolling and finishing mills), F2 (iron and steel foundries), F3 (rolling, drawing and extruding of nonferrous metals), F4 (nonferrous foundries), F5 (smelting and refining of nonferrous metals and miscellaneous primary metal products). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is F.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 115.2, page 25
"applicable parameters in Table F-1 in Appendix B"
Open the permit at this section

Sector G: benchmark values for metal mining (ore mining and dressing)

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table G-1 of Appendix B, by subsector: G1 (active copper ore mining and dressing), G2 (waste rock and overburden piles at active metal mines). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is G.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 128.3, page 28
"applicable parameters in Table G-1 and G-2 of Appendix B"
Open the permit at this section

Sector H: benchmark values for coal mines and coal mining-related facilities

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table H-1 of Appendix B, by subsector: H1 (coal mines and related areas). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is H.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 141.2, page 30
"applicable parameters in Table H-1 in Appendix B"
Open the permit at this section

Sector I: benchmark values for oil and gas extraction and refining

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table I-1 of Appendix B, by subsector: I1 (oil and gas extraction), I2 (oil refining). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is I.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 150.2, page 31
"applicable parameters in Table I-1 in Appendix B"
Open the permit at this section

Sector J: benchmark values for mineral mining and dressing

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table J-1 of Appendix B, by subsector: J1 (sand and gravel mining), J2 (dimension and crushed stone, nonmetallic minerals), J3 (clay, ceramic, refractory, chemical and fertilizer mineral mining). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is J.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 161.2, page 33
"applicable parameters in Table J-1 in Appendix B"
Open the permit at this section

Sector K: benchmark values for hazardous waste treatment, storage, or disposal facilities

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table K-1 of Appendix B, by subsector: K1 (hazardous waste facilities not subject to 40 CFR 445 Subpart A). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is K.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 168.2, page 35
"applicable parameters in Table K-1 in Appendix B"
Open the permit at this section

Sector L: benchmark values for landfills and land application sites

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table L-1 of Appendix B, by subsector: L1 (municipal solid waste landfill areas closed under 40 CFR 258.60), L2 (landfills and land application sites that do not discharge contact stormwater to surface water), L3 (landfills that discharge contact stormwater to surface water). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is L.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 185.2, page 38
"applicable parameters in Table L-1 in Appendix B"
Open the permit at this section

Sector M: benchmark values for automobile salvage yards

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table M-1 of Appendix B, by subsector: M1 (automobile salvage yards). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is M.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 194.2, page 39
"applicable parameters in Table M-1 in Appendix B"
Open the permit at this section

Sector M: inspect arriving vehicles immediately

No set date. Immediately on arrival.

Automobile salvage yards inspect vehicles as they arrive for leaks of fluids and for mercury switches, drain fluids before storage or crushing, and contain any leak immediately.

  • Only if: your permit sector is M.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 192.2, page 39
"The Permittee shall immediately inspect vehicles arriving at the facility."
Open the permit at this section

Sector N: benchmark values for scrap recycling and waste recycling facilities

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table N-1 of Appendix B, by subsector: N1 (scrap recycling facilities). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is N.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 208.2, page 41
"applicable parameters in Table N-1 in Appendix B"
Open the permit at this section

Sector O: benchmark values for steam electric generating facilities

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table O-1 of Appendix B, by subsector: O1 (coal and oil fired plants), O2 (nuclear, gas and other steam electric plants). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is O.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 223.2, page 43
"applicable parameters in Table O-1 in Appendix B"
Open the permit at this section

Sector P: benchmark values for land transportation and warehousing

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table P-1 of Appendix B, by subsector: P1 (rail transportation), P2 (petroleum bulk stations and terminals), P3 (motor vehicle facilities), P4 (warehousing and storage). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is P.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 236.2, page 44
"applicable parameters in Table P-1 In Appendix B"
Open the permit at this section

Sector Q: benchmark values for water transportation

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table Q-1 of Appendix B, by subsector: Q1 (water transportation facilities). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is Q.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 248.2, page 46
"applicable parameters in Table Q-1 in Appendix B"
Open the permit at this section

Sector R: benchmark values for ship and boat building and repair yards

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table R-1 of Appendix B, by subsector: R1 (ship and boat building and repairing yards). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is R.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 260.2, page 47
"applicable parameters in Table R-1 in Appendix B"
Open the permit at this section

Sector S: benchmark values for air transportation

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table S-1 of Appendix B, by subsector: S1 (airports using glycol-based deicers or urea), S2 (airports not using glycol-based deicers or urea). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is S.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 274.3, page 49
"applicable parameters in Table S-1 in Appendix B"
Open the permit at this section

Sector S: two inspections a month during the deicing season

No set date. The deicing season is the one the facility names in its SWPPP, so the product cannot place these months.

Airports inspect twice a month, at least 10 days apart, during the deicing season named in the SWPPP, in addition to the regular inspections.

  • Only if: your permit sector is S.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 268.2, page 48
"the Permittee shall conduct two inspections per month with no less than 10 days between inspections during the deicing season, as specified in the Permittee's SWPPP."
Open the permit at this section

Sector T: benchmark values for treatment works

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table T-1 of Appendix B, by subsector: T1 (treatment works). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is T.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 286.2, page 51
"applicable parameters in Table T-1in Appendix B"
Open the permit at this section

Sector U: benchmark values for food and kindred products

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table U-1 of Appendix B, by subsector: U1 (grain mill products), U2 (fats and oils products), U3 (food and tobacco products, food preparation). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is U.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 296.2, page 52
"applicable parameters in Table U-1 in Appendix B"
Open the permit at this section

Sector V: benchmark values for textile mills, apparel, and other fabric products manufacturing

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table V-1 of Appendix B, by subsector: V1 (textile, fabric, apparel and leather products). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is V.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 306.2, page 54
"applicable parameters in Table V-1 in Appendix B"
Open the permit at this section

Sector W: benchmark values for furniture and fixtures

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table W-1 of Appendix B, by subsector: W1 (furniture and fixtures). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is W.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 310.2, page 54
"applicable parameters in Table W-1 in Appendix B"
Open the permit at this section

Sector X: benchmark values for printing and publishing

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table X-1 of Appendix B, by subsector: X1 (printing and publishing). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is X.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 317.2, page 54
"applicable parameters in Table X-1 in Appendix B"
Open the permit at this section

Sector Y: benchmark values for rubber, miscellaneous plastic products, and miscellaneous manufacturing industries

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table Y-1 of Appendix B, by subsector: Y1 (fabricated rubber products), Y2 (plastic products). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is Y.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 324.2, page 55
"applicable parameters in Table Y-1 in Appendix B"
Open the permit at this section

Sector Z: benchmark values for leather tanning and finishing

No set date. These are the values the four-quarter average is compared with. The sampling schedule is in the quarterly benchmark monitoring duty.

Benchmark values from Table Z-1 of Appendix B, by subsector: Z1 (leather tanning and finishing). The average of four quarterly samples is compared with each value.

  • Only if: your permit sector is Z.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 332.2, page 56
"applicable parameters in Table Z-1 in Appendix B"
Open the permit at this section

Sectors J and L: notify the MPCA before earth-disturbing work

No set date. Before the work starts; the permit sets no number of days.

Before starting earth-disturbing activities ahead of active mining (Sector J) or ancillary to active landfill activities (Sector L), notify the MPCA at csw.notify.pca@state.mn.us with the facility, county, start and end dates and acres to be disturbed, and follow the named sections of the construction stormwater permit.

  • Only if: your permit sector is J, L; an earth-disturbing activity is planned.
  • You send it to the agency (csw.notify.pca@state.mn.us).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 157.2, page 32
"Permittees must notify the MPCA prior to initiating earth-disturbing activities conducted prior to active mining."
Open the permit at this section

What does no-exposure certification require?

No Exposure Exclusion under Minn. R. 7090.3060: an application certifying that all industrial materials and activities are protected by a storm-resistant shelter, submitted once every five years.

Every few years 1 duty

No Exposure: apply again at least once every five years

Within 5 years after your last no exposure application.

Minnesota's rule requires a No Exposure application to be submitted once every five years. The pack counts five years from the last application.

  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.

Inferred from Minn. R. 7090.3060, subp. 3. Check your copy of the permit.

Source: Minn. R. 7090.3060, Conditional No Exposure Exclusion (Minnesota Revisor of Statutes), section Minn. R. 7090.3060, subp. 3
"An application for no-exposure certification must be submitted to the commissioner once every five years."
Open the permit at this section

One time 1 duty

No Exposure: submit a new application under this permit

No set date. The permit sets no date. The MPCA application deadline for the 2025 permit cycle (October 31, 2026) is an agency notice that has passed; see open question q1.

A facility with no exposure of industrial materials or activities to stormwater applies for the No Exposure Exclusion instead of coverage. A No Exposure certification obtained before this permit took effect does not carry over: a new application is required.

  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Industrial Stormwater Multi-Sector General Permit MNR050000 (MPCA wq-strm3-102g), with Appendices A to E, section 5.7, page 5
"Any facility that obtains a conditional exclusion for No Exposure prior to the effective date of this permit must submit a new application for the No Exposure Exclusion."
Open the permit at this section

When something happens 1 duty

No Exposure: apply for permit coverage before exposure starts

No set date. Before the change; the rule sets no number of days.

If a facility expects a change that will end its no exposure condition, it must apply for and obtain permit coverage before the change.

  • When: a change is expected that will end no exposure.
  • You file it in the agency's system (MPCA e-Services).
  • Keep the records 3 years.
Source: Minn. R. 7090.3060, Conditional No Exposure Exclusion (Minnesota Revisor of Statutes), section Minn. R. 7090.3060, subp. 5.C
"the operator shall apply for and obtain a permit under part 7090.3010 before the change of circumstance."
Open the permit at this section

Get your own dates

Choose your coverage and answer a few questions. You get each duty's next date and a calendar file.

Minnesota Industrial Stormwater MSGP duties, topic by topic

How the Minnesota Industrial Stormwater MSGP compares with the other checked permits on each kind of duty, in the permit's own words with the section for each: