Guides / Exceedance response

What to do after a benchmark or NAL exceedance

A result above a benchmark or action level starts a set of steps, each with its own deadline. The first step under each permit:

  • California Industrial General Permit (IGP): Designate a trained QISP when Level 1 begins. When: By October 1 after the status begins (after level 1 start). Then 6 more steps.
  • Texas MSGP: Investigate each benchmark exceedance within 90 days. When: Within 90 days after sampling event date.
  • Washington ISGP: Level 1 corrective action after any benchmark exceedance. When: Within 14 days after later of results receipt or quarter end. Then 2 more steps.
  • EPA 2021 MSGP: AIM Level 1 after a benchmark annual-average exceedance. When: Within 14 days after lab results showing aim trigger (up to 45 days where the permit allows more time). Then 2 more steps.

Get my permit calendar

Free, no account. Pick your state and coverage and see the next date for each duty.

Next: answer a few questions about your site. You get your dates, the permit section for each, and a calendar file.

StormDue reminds and keeps records. It does not file anything with the agency and does not certify or guarantee compliance. Check each duty against your permit; you are responsible for your filings.

Compared here: California Industrial General Permit (IGP), rules checked November 25, 2026; Texas MSGP, rules checked November 25, 2026; Washington ISGP, rules checked November 25, 2026; EPA 2021 MSGP, rules checked November 26, 2026. Duties for other states are not listed until their rules are checked: find your state.

The steps after an exceedance, permit by permit

  1. California Industrial General Permit (IGP)

    1. Designate a trained QISP when Level 1 begins By October 1 after the status begins (after level 1 start)
    2. Complete the Level 1 ERA Evaluation by October 1 By October 1 after the status begins (after level 1 start)
    3. Submit the Level 1 ERA Report by January 1 By January 1 after the status begins (after level 1 start)
    4. Submit the Level 2 ERA Action Plan by January 1 By January 1, after each reporting year ends (after end of reporting year with level 2 exceedance)
    5. Finish the Level 2 Action Plan within one year Within 365 days after level 2 action plan submitted
    6. Submit the Level 2 ERA Technical Report No set date. XII.D.2: "On January 1 of the reporting year following the submittal of the Level 2 ERA Action Plan"; SMARTS guide: "by January 1 following the submission". Which date applies to Action Plans filed July to December?
    7. Update (or certify no change to) the Level 2 Technical Report with each Annual Report By July 15, after each reporting year ends
  2. Texas MSGP

    1. Investigate each benchmark exceedance within 90 days Within 90 days after sampling event date
  3. Washington ISGP

    1. Level 1 corrective action after any benchmark exceedance Within 14 days after later of results receipt or quarter end
    2. Level 2 structural source control after two exceeding quarters in a calendar year By August 31, for the calendar year before (after level 2 triggered)
    3. Level 3 treatment after three exceeding quarters in a calendar year By September 30, for the calendar year before (after level 3 triggered)
  4. EPA 2021 MSGP

    1. AIM Level 1 after a benchmark annual-average exceedance Within 14 days after lab results showing aim trigger (up to 45 days where the permit allows more time)
    2. AIM Level 2 after a continued exceedance in Level 1 Within 14 days after lab results showing aim trigger (up to 45 days where the permit allows more time)
    3. AIM Level 3 structural or treatment controls No set date. Part 5.2.5.2 says "identify the schedule ... within 14 days and install such measures within 60 days" without a start date; the Fact Sheet says "within 60 days of the Level 3 triggering event". EPA must say whether the clocks start at receipt of lab results or at the triggering event.

How many parameters have a benchmark or action level?

Parameters in each permit's benchmark, action level and limit tables. Which ones apply to you depends on your sector and the water you discharge to. The benchmark comparison checks a lab result against them.

  • California Industrial General Permit (IGP) 21
  • Texas MSGP 12
  • Washington ISGP 5
  • EPA 2021 MSGP 23

Worked example: if it happens on March 3, 2027

Some deadlines count from something that happens at the site. If that event fell on March 3, 2027, the permit's rule puts the deadline here. Your own dates come from your own events.

Deadlines counted from an event on March 3, 2027
PermitDutyCounts fromDue
California Industrial General Permit (IGP) Complete the Level 1 ERA Evaluation by October 1 level 1 start October 1, 2027
California Industrial General Permit (IGP) Designate a trained QISP when Level 1 begins level 1 start October 1, 2027
California Industrial General Permit (IGP) Finish the Level 2 Action Plan within one year level 2 action plan submitted March 2, 2028
California Industrial General Permit (IGP) Submit the Level 1 ERA Report by January 1 level 1 start January 1, 2028
California Industrial General Permit (IGP) Submit the Level 2 ERA Action Plan by January 1 end of reporting year with level 2 exceedance January 1, 2028
Texas MSGP Investigate each benchmark exceedance within 90 days sampling event date June 1, 2027
Washington ISGP Level 1 corrective action after any benchmark exceedance later of results receipt or quarter end March 17, 2027
Washington ISGP Level 2 structural source control after two exceeding quarters in a calendar year level 2 triggered August 31, 2028
Washington ISGP Level 3 treatment after three exceeding quarters in a calendar year level 3 triggered September 30, 2028
EPA 2021 MSGP AIM Level 1 after a benchmark annual-average exceedance lab results showing aim trigger March 17, 2027
Up to April 17, 2027 where the permit allows
EPA 2021 MSGP AIM Level 2 after a continued exceedance in Level 1 lab results showing aim trigger March 17, 2027
Up to April 17, 2027 where the permit allows

The deadline calculator works out the same dates from your own event date.

California Industrial General Permit (IGP)

General Permit for Storm Water Discharges Associated with Industrial Activities, run by State Water Resources Control Board (with the nine Regional Water Quality Control Boards). Rules checked November 25, 2026. Every duty in this permit · California permit facts · Official permit page

Only if... 7 duties

These apply only in the situation named on each one. Answer the questions to sort them.

Update (or certify no change to) the Level 2 Technical Report with each Annual Report

By July 15, after each reporting year ends.

While in Level 2, have the QISP update the Level 2 ERA Technical Report for new exceedances of the same parameter and drainage area, operational or source changes, or new information, and submit it with each Annual Report; if nothing changed, certify that in the Annual Report.

  • Only if: a parameter is at level 2; level 2 technical report submitted.
  • Does not apply if: inactive mining certification in effect.
  • You file it in the agency's system (SMARTS).
  • Keep the records 5 years.
  • The permit says this is done by a Qualified Industrial Storm Water Practitioner (QISP).
  • Signed or certified by the Legally Responsible Person or a Duly Authorized Representative.
Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XII.D.3.c, page 59
"The Level 2 ERA Technical Report shall be prepared by a QISP and be certified and submitted via SMARTS by the Discharger with each Annual Report."
Open the permit at this section

Complete the Level 1 ERA Evaluation by October 1

By October 1 after the status begins (after level 1 start).

With a QISP, evaluate the industrial pollutant sources related to the exceedance, identify the SWPPP BMPs and any additional BMPs and SWPPP revisions needed. All drainage areas must be evaluated.

  • Only if: a parameter is at level 1.
  • Does not apply if: inactive mining certification in effect.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 5 years.
  • The permit says this is done by a Qualified Industrial Storm Water Practitioner (QISP).
Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XII.C.1, page 55
"By October 1 following commencement of Level 1 status for any parameter with sampling results indicating an NAL/TNAL exceedance, the Discharger shall:"
Open the permit at this section

Designate a trained QISP when Level 1 begins

By October 1 after the status begins (after level 1 start).

Designate a Qualified Industrial Storm Water Practitioner who has completed the State Water Board QISP course, and have the QISP train the appropriate team members.

  • Only if: a parameter is at level 1 or higher.
  • Does not apply if: inactive mining certification in effect.
  • You file it in the agency's system (SMARTS (QISP ID, name and contact submitted with the Level 1 ERA Report)).
  • Keep the records 5 years.
  • Signed or certified by the Legally Responsible Person or a Duly Authorized Representative.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section IX.A.3, page 28
"Dischargers with Level 1 status shall: a. Designate a person to be the facility's QISP"
Open the permit at this section

Finish the Level 2 Action Plan within one year

Within 365 days after level 2 action plan submitted.

Implement all elements of the Level 2 ERA Action Plan as soon as practicable and no later than 1 year after submitting it.

  • Only if: a parameter is at level 2.
  • Does not apply if: inactive mining certification in effect.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 5 years.
Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XII.D.1.d, page 56
"All elements of the Level 2 ERA Action Plan shall be implemented as soon as practicable and completed no later than 1 year after submitting the Level 2 ERA Action Plan."
Open the permit at this section

Submit the Level 1 ERA Report by January 1

By January 1 after the status begins (after level 1 start).

Revise the SWPPP and implement the additional BMPs, then certify and submit a Level 1 ERA Report prepared by a QISP (evaluation summary and BMP/SWPPP changes per parameter) plus the QISP's ID number, name, phone and email.

  • Only if: a parameter is at level 1.
  • Does not apply if: inactive mining certification in effect.
  • You file it in the agency's system (SMARTS).
  • Keep the records 5 years.
  • The permit says this is done by a Qualified Industrial Storm Water Practitioner (QISP).
  • Signed or certified by the Legally Responsible Person or a Duly Authorized Representative.
Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XII.C.2.a, page 55
"as soon as practicable but no later than January 1 following commencement of Level 1 status:"
Open the permit at this section

Submit the Level 2 ERA Action Plan by January 1

By January 1, after each reporting year ends (after end of reporting year with level 2 exceedance).

Certify and submit a Level 2 ERA Action Plan prepared by a QISP for each new Level 2 exceedance, choosing the demonstration(s) to perform (industrial BMPs, non-industrial source, natural background), with a schedule and task list. Update QISP details if changed.

  • Only if: a parameter is at level 2.
  • Does not apply if: inactive mining certification in effect.
  • You file it in the agency's system (SMARTS).
  • Keep the records 5 years.
  • The permit says this is done by a Qualified Industrial Storm Water Practitioner (QISP).
  • Signed or certified by the Legally Responsible Person or a Duly Authorized Representative.
Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XII.D.1.a, page 56
"shall certify and submit via SMARTS a Level 2 ERA Action Plan prepared by a QISP that addresses each new Level 2 NAL/TNAL exceedance by January 1 following the reporting year during which the NAL/TNAL exceedance(s) occurred."
Open the permit at this section

Submit the Level 2 ERA Technical Report

No set date. XII.D.2: "On January 1 of the reporting year following the submittal of the Level 2 ERA Action Plan"; SMARTS guide: "by January 1 following the submission". Which date applies to Action Plans filed July to December?

Certify and submit a Level 2 ERA Technical Report prepared by a QISP containing one or more of the demonstrations (industrial activity BMPs, non-industrial source, natural background).

  • Only if: a parameter is at level 2.
  • Does not apply if: inactive mining certification in effect.
  • You file it in the agency's system (SMARTS).
  • Keep the records 5 years.
  • The permit says this is done by a Qualified Industrial Storm Water Practitioner (QISP).
  • Signed or certified by the Legally Responsible Person or a Duly Authorized Representative.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: Industrial General Permit Order (conformed, as amended 2015 and 2018), section XII.D.2; XII.D.3.a; XII.D.5, page 57
"On January 1 of the reporting year following the submittal of the Level 2 ERA Action Plan, a Discharger with Level 2 status shall certify and submit a Level 2 ERA Technical Report prepared by a QISP"
Open the permit at this section

Texas MSGP

TPDES Multi-Sector General Permit for Stormwater Discharges Associated with Industrial Activity, run by Texas Commission on Environmental Quality (TCEQ). Rules checked November 25, 2026. Every duty in this permit · Texas permit facts · Official permit page

When something happens 1 duty

Investigate each benchmark exceedance within 90 days

Within 90 days after sampling event date.

The pollution prevention team investigates the cause of each exceedance (spills, housekeeping, additional BMPs with a schedule, other SWP3 changes) and documents it in the SWP3 within 90 days of the sampling event.

  • When: benchmark exceedance.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • The permit says this is done by your pollution prevention team.
Source: 2026 Multi-Sector General Permit TXR050000, section IV.A.3, page 74
"The Pollution Prevention Team must investigate the cause for each exceedance and must document the results of this investigation in the SWP3 within 90 days following the sampling event."
Open the permit at this section

Washington ISGP

Industrial Stormwater General Permit (NPDES and State Waste Discharge General Permit), run by Washington State Department of Ecology, Water Quality Program. Rules checked November 25, 2026. Every duty in this permit · Washington permit facts · Official permit page

When something happens 3 duties

Level 1 corrective action after any benchmark exceedance

Within 14 days after later of results receipt or quarter end.

Within 14 days of results showing a quarterly exceedance (or the end of the quarter, if later, for parameters other than pH and oil sheen): inspect to find the cause, review the SWPPP, add operational source control BMPs. Sign and fully implement the revised SWPPP by the DMR due date for that quarter. Summarize in the Annual Report.

  • When: benchmark exceedance in quarter.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 5 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026), section S8.B, page 53
"Within 14 days of receipt of sampling results that indicate a benchmark exceedance during a given quarter"
Open the permit at this section

Level 2 structural source control after two exceeding quarters in a calendar year

By August 31, for the calendar year before (after level 2 triggered).

If a parameter exceeds its benchmark in any two quarters of a calendar year (facility-wide), review the SWPPP, add structural source control BMPs for the exceeding areas, and sign and fully implement by August 31 of the following year (or skip to Level 3). Extensions or waivers require a Modification of Coverage request before the deadline.

  • When: two quarters exceeded same parameter in calendar year.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 5 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026), section S8.C, page 54
"fully implement the revised SWPPP according to Permit Condition S3 and the applicable Stormwater Management Manual as soon as possible, but no later than August 31st of the following year."
Open the permit at this section

Level 3 treatment after three exceeding quarters in a calendar year

By September 30, for the calendar year before (after level 3 triggered).

If a parameter exceeds its benchmark in any three quarters of a calendar year, add treatment BMPs; a qualified industrial stormwater professional reviews and certifies the revised SWPPP; if treatment needs site-specific design, submit a PE-certified engineering report by June 30 of the following year and an O&M manual within 30 days after installation; implement by September 30 of the following year.

Further steps with their own deadlines:

  • Engineering report (certified by a licensed professional engineer). By June 30, for the calendar year before (after level 3 triggered). Section S8.D.3.b, page 56
    "The engineering report shall be submitted no later than 6 months after the last day of the calendar year in which the Level 3 was triggered, i.e., due June 30th"
  • Operation and Maintenance Manual. Within 30 days after installation complete. Section S8.D.3.c, page 56
    "An Operation and Maintenance Manual (O&M Manual) shall be submitted to Ecology no later than 30 days after construction/installation is complete"
  • Implementation deadline. The permit gives the timing in words, quoted below. Section S8.D.5, page 56
    "as soon as possible, but no later than September 30th of the following year provided."
  • When: three quarters exceeded same parameter in calendar year.
  • You file it in the agency's system (Engineering report and O&M manual to Ecology; SWPPP kept on site).
  • Keep the records 5 years.
  • The permit says this is done by a qualified industrial stormwater professional.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2026 Industrial Stormwater General Permit Modification (issued Dec 2, 2024, modified Oct 21, 2026), section S8.D, page 55
"A qualified industrial stormwater professional shall review the revised SWPPP, sign the SWPPP Certification Form, and certify that it is reasonably expected to meet the ISGP benchmarks upon implementation."
Open the permit at this section

EPA 2021 MSGP

NPDES Multi-Sector General Permit for Stormwater Discharges Associated with Industrial Activity, run by U.S. Environmental Protection Agency (EPA Regions 1-10). Rules checked November 26, 2026. Every duty in this permit · Official permit page

Only if... 3 duties

These apply only in the situation named on each one. Answer the questions to sort them.

AIM Level 1 after a benchmark annual-average exceedance

Within 14 days after lab results showing aim trigger (up to 45 days where the permit allows more time).

Immediately review the SWPPP and controls; implement additional measures within 14 days of receiving lab results (45 if infeasible, documented), or document why existing controls will work; then continue quarterly benchmark monitoring for four more quarters.

  • Only if: a parameter is at AIM level 1.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 5.2.2; 5.2.3, page 48
"you must implement those modifications or control measures within 14 days of receipt of laboratory results, unless doing so within 14 days is infeasible."
Open the permit at this section

AIM Level 2 after a continued exceedance in Level 1

Within 14 days after lab results showing aim trigger (up to 45 days where the permit allows more time).

Implement additional pollution prevention and good housekeeping measures beyond Level 1 within 14 days of the lab results (up to 45 days if documented; EPA may grant more on a demonstration), document how they will meet the benchmark, then continue quarterly monitoring for four quarters.

  • Only if: a parameter is at AIM level 2.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.
Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 5.2.4.2, page 49
"You must implement additional pollution prevention/good housekeeping SCMs within 14 days of receipt of laboratory results that indicate an AIM triggering event has occurred"
Open the permit at this section

AIM Level 3 structural or treatment controls

No set date. Part 5.2.5.2 says "identify the schedule ... within 14 days and install such measures within 60 days" without a start date; the Fact Sheet says "within 60 days of the Level 3 triggering event". EPA must say whether the clocks start at receipt of lab results or at the triggering event.

Identify the schedule for structural source controls and/or treatment within 14 days and install them within 60 days (90 if documented as infeasible; EPA may extend), then continue quarterly monitoring for four quarters. The permit does not say what starts the 14 and 60 days.

  • Only if: a parameter is at AIM level 3.
  • Nothing is filed; keep the record at the facility.
  • Keep the records 3 years.
  • Signed or certified by a responsible official or duly authorized representative.

Inferred: the permit implies this but does not state it in one place. Check it against the section cited.

Source: 2021 MSGP Permit Parts 1-7 (as modified September 2021), section 5.2.5.2, page 50
"You must identify the schedule for installing the appropriate structural source and/or treatment stormwater control measures within 14 days and install such measures within 60 days."
Open the permit at this section

Try it with your own numbers

The free tools use the same permit data as this page. No account.

Compare a lab result with my permit

Questions people ask

What do I do after a benchmark or NAL exceedance?

California Industrial General Permit (IGP): Designate a trained QISP when Level 1 begins. When: By October 1 after the status begins (after level 1 start). Complete the Level 1 ERA Evaluation by October 1. When: By October 1 after the status begins (after level 1 start). Submit the Level 1 ERA Report by January 1. When: By January 1 after the status begins (after level 1 start). Submit the Level 2 ERA Action Plan by January 1. When: By January 1, after each reporting year ends (after end of reporting year with level 2 exceedance). Finish the Level 2 Action Plan within one year. When: Within 365 days after level 2 action plan submitted. Submit the Level 2 ERA Technical Report. When: No set date. XII.D.2: "On January 1 of the reporting year following the submittal of the Level 2 ERA Action Plan"; SMARTS guide: "by January 1 following the submission". Which date applies to Action Plans filed July to December? Update (or certify no change to) the Level 2 Technical Report with each Annual Report. When: By July 15, after each reporting year ends. Texas MSGP: Investigate each benchmark exceedance within 90 days. When: Within 90 days after sampling event date. Washington ISGP: Level 1 corrective action after any benchmark exceedance. When: Within 14 days after later of results receipt or quarter end. Level 2 structural source control after two exceeding quarters in a calendar year. When: By August 31, for the calendar year before (after level 2 triggered). Level 3 treatment after three exceeding quarters in a calendar year. When: By September 30, for the calendar year before (after level 3 triggered). EPA 2021 MSGP: AIM Level 1 after a benchmark annual-average exceedance. When: Within 14 days after lab results showing aim trigger (up to 45 days where the permit allows more time). AIM Level 2 after a continued exceedance in Level 1. When: Within 14 days after lab results showing aim trigger (up to 45 days where the permit allows more time). AIM Level 3 structural or treatment controls. When: No set date. Part 5.2.5.2 says "identify the schedule ... within 14 days and install such measures within 60 days" without a start date; the Fact Sheet says "within 60 days of the Level 3 triggering event". EPA must say whether the clocks start at receipt of lab results or at the triggering event.

How many parameters have a benchmark or action level?

California Industrial General Permit (IGP): 21; Texas MSGP: 12; Washington ISGP: 5; EPA 2021 MSGP: 23. These are the parameters in each permit's tables as we transcribed them; which ones apply to you depends on your sector and receiving water.

Who has to do the corrective action work?

Where the permit names someone: California Industrial General Permit (IGP), Update (or certify no change to) the Level 2 Technical Report with each Annual Report: the permit says this is done by a Qualified Industrial Storm Water Practitioner (QISP). California Industrial General Permit (IGP), Complete the Level 1 ERA Evaluation by October 1: the permit says this is done by a Qualified Industrial Storm Water Practitioner (QISP). California Industrial General Permit (IGP), Submit the Level 1 ERA Report by January 1: the permit says this is done by a Qualified Industrial Storm Water Practitioner (QISP). California Industrial General Permit (IGP), Submit the Level 2 ERA Action Plan by January 1: the permit says this is done by a Qualified Industrial Storm Water Practitioner (QISP). California Industrial General Permit (IGP), Submit the Level 2 ERA Technical Report: the permit says this is done by a Qualified Industrial Storm Water Practitioner (QISP). Texas MSGP, Investigate each benchmark exceedance within 90 days: the permit says this is done by your pollution prevention team. Washington ISGP, Level 3 treatment after three exceeding quarters in a calendar year: the permit says this is done by a qualified industrial stormwater professional. Where it does not, the facility decides who does the work.