Routine site inspection twice a year
By the end of each half year (June 30 and December 31), once.
In each calendar half year (January to June, July to December) visually inspect: areas where industrial materials or activities are exposed to stormwater; the potential pollutant sources named in the PPC Plan; areas where spills or leaks happened in the past three years; outfalls and places where authorized non-stormwater discharges may mix with stormwater; and the physical BMPs. Record the findings in the Annual Report.
- Nothing is filed; keep the record at the facility.
- Keep the records 3 years.
Source: PAG-03 General Permit (3800-PM-BCW0083d, revision 12/2022), section Part C III.A, page 21
"The permittee shall visually inspect the following areas and BMPs on a semiannual basis (calendar periods), at a minimum:"Open the permit at this section